Which process covers the Project Board's decision to authorize a stage?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Directing a Project

The Directing a Project process covers Project Board decisions, including authorization to start a stage. Controlling a Stage is a Project Manager process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Directing a Project

    Why this is correct

    DP is the Project Board process for making key decisions.

  • Controlling a Stage

    Why it's wrong here

    CS is the Project Manager process for day-to-day management.

  • Managing a Stage Boundary

    Why it's wrong here

    MSB provides information to the Board for decision, but the decision itself is part of DP.

  • Managing Product Delivery

    Why it's wrong here

    MP is the Team Manager process for delivering work packages.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.