Which process covers the Project Board's decision to authorize a stage?
⚠ Common exam trap
The trap is thinking that Managing a Stage Boundary includes the authorization decision. Candidates often confuse the preparation of the stage boundary documentation with the actual authorization, which is a Board decision in Directing a Project.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Directing a Project
The Project Board's decision to authorize a stage is made within the Directing a Project process. Specifically, the activity 'Authorize a Stage or Exception Plan' is part of Directing a Project, where the Project Board reviews the Stage Plan and approves it. This decision is based on the information provided in the End Stage Report and Next Stage Plan from the Managing a Stage Boundary process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Directing a Project
Why this is correct
Directing a Project is the process where the Project Board exercises its authority, including the decision to authorise each stage. The Board's stage authorisation decision sits squarely within this process, not within Managing a Stage Boundary, which merely prepares the request.
- ✗
Controlling a Stage
Why it's wrong here
Controlling a Stage covers the Project Manager's day-to-day work of delivering a stage, not the Project Board's authority decision. It tempts because stage authorisation happens at stage boundaries within that wider control cycle, but the board's authorise-a-stage activity sits in Directing a Project.
- ✗
Managing a Stage Boundary
Why it's wrong here
Managing a Stage Boundary is the Project Manager's process for preparing the End Stage Report and Next Stage Plan for the board. It tempts because it produces exactly the material the board reviews, yet the board's actual authorise-a-stage decision belongs to Directing a Project.
- ✗
Managing Product Delivery
Why it's wrong here
Managing Product Delivery governs the Team Manager's acceptance, execution and delivery of work packages. It tempts because stage work is delivered through it, but it contains no Project Board authorisation activity; that decision sits in Directing a Project.
Go deeper
Related to this question
About these practice questions
One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PeopleCert exam blueprint
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.