PRINCE2F PRINCE2 Practices Practice Question

The Project Board has set a cost tolerance of +/- 10% for a stage. The Project Manager forecasts that the stage will be completed 15% under budget. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

The cost tolerance for the stage is +/-10%, meaning the stage must be completed within 10% over or under the planned budget. A forecast of 15% under budget exceeds the -10% tolerance, constituting an exception. According to PRINCE2, when a forecast indicates that stage tolerance will be exceeded, the Project Manager must raise an Exception Report to the Project Board. Option A is incorrect because Highlight Reports are used for regular reporting within tolerance, not for exceptions. Option B is incorrect because the Project Manager cannot reallocate surplus without authorization. Option C is incorrect because being outside tolerance requires escalation, not inaction.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Report the underrun in the next Highlight Report

    Why it's wrong here

    Exceptions must be reported immediately via an Exception Report, not a Highlight Report.

  • Reallocate the surplus to other activities without informing the Project Board

    Why it's wrong here

    The Project Board must approve any changes to stage tolerances.

  • Continue as planned since being under budget is beneficial

    Why it's wrong here

    Under budget by more than tolerance is still an exception and must be escalated.

  • Raise an Exception Report to the Project Board

    Why this is correct

    When a tolerance is forecast to be exceeded (even beneficial), an Exception Report is required.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.