PRINCE2F PRINCE2 Practices Practice Question
Which TWO of the following are types of tolerance that can be set in PRINCE2?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Time
The six types of tolerance in PRINCE2 are Time, Cost, Quality, Scope, Risk, and Benefits. Options D and E (Time and Cost) are correct. Options A and B refer to management products (the Change Control Approach and the Quality Management Approach), which are not types of tolerance. Option C (Risk budget) is a type of budget, not a tolerance. Therefore, the correct answers are D and E.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Change control approach
Why it's wrong here
This is a management document, not a tolerance.
- ✗
Quality management approach
Why it's wrong here
This is a management document, not a tolerance.
- ✗
Risk budget
Why it's wrong here
Risk budget is a sum of money set aside for risk responses, not a tolerance.
- ✓
Time
Why this is correct
Time is one of the six PRINCE2 tolerances.
- ✓
Cost
Why this is correct
Cost is one of the six PRINCE2 tolerances.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.