PRINCE2F PRINCE2 Practices Practice Question
Which practice defines the project management team structure?
⚠ Common exam trap
The PRINCE2 Foundation exam often tests the distinction between 'Organising' (structure and roles) and 'Plans' (scheduling and resources), leading candidates to confuse the practice that defines the team with the one that defines the work breakdown.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Organising
The Organising practice defines the project management team structure, including roles, responsibilities, and reporting lines. It establishes who is accountable for key decisions and how the team is organized to deliver the project. This is distinct from other practices that focus on justification, planning, or monitoring.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Business Case
Why it's wrong here
Business Case provides justification.
- ✗
Plans
Why it's wrong here
Plans define how the project will be delivered, not the team structure.
- ✗
Progress
Why it's wrong here
Progress defines tolerances and reporting.
- ✓
Organising
Why this is correct
Correct.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.