PRINCE2F People: organizations, teams, and leadership Practice Question
Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO)?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Ensuring the project delivers the expected benefits
The SRO owns the Business Case and is accountable for the project's success and benefits realization. They also chair the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Managing the day-to-day activities of the project
Why it's wrong here
This is the Project Manager's responsibility.
- ✓
Ensuring the project delivers the expected benefits
Why this is correct
Benefits realization is a key accountability of the SRO.
- ✓
Maintaining the Business Case
Why this is correct
The SRO is accountable for the Business Case.
- ✗
Preparing the Project Plan
Why it's wrong here
The Project Manager prepares the Project Plan.
- ✗
Approving the Work Packages
Why it's wrong here
Work Packages are authorized by the Project Manager, not the SRO.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.