What is the purpose of the Risk Register?

⚠ Common exam trap

Many candidates confuse the Risk Register with other registers or reports, such as the Issue Register or Highlight Report, leading candidates to select options that describe functions of those products instead.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To capture and track information about identified risks throughout the project

The Risk Register is a PRINCE2 management product that captures and tracks all identified risks throughout the project lifecycle. It records risk descriptions, probability, impact, proximity, and responses, ensuring risks are actively managed and monitored. This aligns with the PRINCE2 principle of continued business justification by maintaining visibility of threats and opportunities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To approve risk budgets

    Why it's wrong here

    Risk budgets are approved by the Board, not recorded in the register.

  • To report progress to stakeholders

    Why it's wrong here

    Progress is reported via Highlight Reports.

  • To capture and track information about identified risks throughout the project

    Why this is correct

    Correct: the Risk Register is used for recording and tracking risks.

  • To record all decisions made by the Project Board

    Why it's wrong here

    That would be the Issue Register or decision log.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.