Which THREE of the following are defined as PRINCE2 project management team roles?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
PRINCE2 defines specific roles: Project Manager, Team Manager, Project Assurance, Project Support, and the Project Board (Executive, Senior User, Senior Supplier). 'Risk Manager' and 'Quality Manager' are not standard roles in PRINCE2; their responsibilities are typically covered by Project Assurance or delegated within the team.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Quality Manager
Why it's wrong here
Not a defined PRINCE2 role; quality is assured by Project Assurance.
- ✓
Project Manager
Why this is correct
A core role in the management team.
- ✗
Risk Manager
Why it's wrong here
Not a defined PRINCE2 role; risk management is everyone's responsibility.
- ✓
Project Support
Why this is correct
An optional but defined role.
- ✓
Project Assurance
Why this is correct
A key role providing independent oversight.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.