Courseiva
People: organizations, teams, and leadershipmediumMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

A project is forecast to exceed its cost tolerance for the current stage. What should the Project Manager do?

⚠ Common exam trap

A common mix-up: candidates think the Project Manager can adjust the budget or delay reporting, but PRINCE2 strictly requires immediate escalation via an Exception Report when tolerances are forecast to be exceeded.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board and await their direction before proceeding

In PRINCE2, when a stage is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have authority to exceed the agreed tolerance; the Project Board must decide whether to approve a revised plan or take other corrective action. Option D correctly follows the PRINCE2 exception management process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Increase the project budget to absorb the additional cost and continue with the current Stage Plan

    Why it's wrong here

    The Project Manager cannot unilaterally increase the budget. Only the Project Board can change tolerances.

  • Continue with the current Stage Plan and report the cost overrun in the next Highlight Report

    Why it's wrong here

    Continuing without escalation when a tolerance is forecast to be exceeded violates management by exception.

  • Close the project immediately as the Business Case is no longer viable

    Why it's wrong here

    A cost tolerance breach does not automatically mean the Business Case is unviable. The Project Board must decide.

  • Raise an Exception Report to the Project Board and await their direction before proceeding

    Why this is correct

    Correct. The PM must escalate immediately via an Exception Report.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.