PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are typical activities in the Closing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Hand over the project's products to the operational environment
Closing a Project includes handing over products and producing the Lessons Report. The End Stage Report is from SB, and the Project Brief is from SU.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Update the Project Brief
Why it's wrong here
Project Brief is created in SU and may be updated in IP, not in closure.
- ✗
Produce the End Stage Report
Why it's wrong here
End Stage Report is produced in Managing a Stage Boundary.
- ✗
Authorize the next stage
Why it's wrong here
Authorization of stages is done in Directing a Project.
- ✓
Hand over the project's products to the operational environment
Why this is correct
Product handover is a key activity in Closing a Project.
- ✓
Produce the Lessons Report
Why this is correct
Lessons Report is produced in Closing a Project.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.