Which THREE of the following are roles on the Project Board?

⚠ Common exam trap

Many exam-takers confuse the Project Manager (a management role) with a Project Board role, or mistakenly think Project Assurance is a board role rather than a separate oversight function.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior User

The PRINCE2 Project Board is the decision-making body responsible for overall project governance. It comprises three roles: the Executive (Senior Responsible Owner), the Senior User, and the Senior Supplier. The Senior User represents the interests of those who will use the project's outputs and is essential for defining requirements and benefits.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The PM is not on the Project Board.

  • Senior User

    Why this is correct

    The Senior User represents users on the Board.

  • Senior Supplier

    Why this is correct

    The Senior Supplier represents suppliers on the Board.

  • Project Assurance

    Why it's wrong here

    Project Assurance reports to the Board but is not a Board member.

  • Senior Responsible Owner (Executive)

    Why this is correct

    The SRO chairs the Project Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are roles that are part of the Project Board?

medium
  • A.Senior User
  • B.Team Manager
  • C.Executive
  • D.Project Assurance
  • E.Project Support

Why A: The Project Board is the PRINCE2 management layer responsible for overall project direction and key decision-making. The Senior User is a mandatory Project Board role representing the interests of those who will use the project's products, ensuring the project delivers the required benefits. The Executive is also a mandatory Project Board role, acting as the project's ultimate decision-maker and owner of the business case.

Variation 2. Which THREE of the following are roles on the PRINCE2 Project Board?

medium
  • A.Project Manager
  • B.Senior Responsible Owner (Executive)
  • C.Senior User
  • D.Senior Supplier
  • E.Team Manager

Why B: The Project Board consists of the Senior Responsible Owner (Executive), Senior User, and Senior Supplier.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.