Courseiva
PRINCE2 Processes →easyMultiple Choice

PRINCE2F PRINCE2 Processes Practice Question

Who is responsible for producing Highlight Reports?

⚠ Common exam trap

PRINCE2F often tests the distinction between the various PRINCE2 reports and who produces them, trapping candidates who confuse Checkpoint Reports (Team Manager) with Highlight Reports (Project Manager).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Manager

In PRINCE2, the Project Manager is responsible for producing Highlight Reports, which are regular progress reports sent to the Project Board. The Highlight Report summarizes project status, including progress, issues, and risks, and is a key control document in the 'Controlling a Stage' process. The Project Manager owns this report as part of their day-to-day management of the stage.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Manager

    Why this is correct

    The Project Manager produces Highlight Reports as part of Controlling a Stage, regularly informing the Project Board of progress, status and exceptions. The board consumes these reports while directing; it does not author them, and the Project Assurance role only reviews them.

  • ✗

    Team Manager

    Why it's wrong here

    The Team Manager produces Checkpoint Reports covering work package progress, which feed into the Highlight Report rather than replacing it. It is tempting because Team Managers report progress upward, which would be correct if the question asked who reports on the delivery of a work package.

  • ✗

    Project Board

    Why it's wrong here

    The Project Board receives Highlight Reports and acts on escalations; producing them is delegated to the Project Manager. It is tempting because the Board owns project assurance and direction, which would be correct if the question asked who reviews progress and approves exception plans.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests on the Project Board, providing requirements and assurance; report authorship sits with the Project Manager. It is tempting because the Senior User consumes Highlight Reports and confirms benefits, which would be correct if the question asked who ensures the project delivers the expected user outcomes.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.