PRINCE2F PRINCE2 Processes Practice Question
Who is responsible for producing Highlight Reports?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
Highlight Reports are produced by the Project Manager and sent to the Project Board during the Controlling a Stage process. Checkpoint Reports are produced by Team Managers.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Manager
Why this is correct
The Project Manager produces Highlight Reports to inform the Project Board of stage progress.
- ✗
Team Manager
Why it's wrong here
Team Managers produce Checkpoint Reports, not Highlight Reports.
- ✗
Project Board
Why it's wrong here
The Project Board receives Highlight Reports, they do not produce them.
- ✗
Senior User
Why it's wrong here
The Senior User is a member of the Project Board, not the producer of Highlight Reports.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.