PRINCE2F People: organizations, teams, and leadership Practice Question
Which role ensures that the project's products meet the needs of the users?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Senior User
The Senior User represents the users and ensures that the products meet their needs. The PM manages delivery but the Senior User defines requirements.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Senior User
Why this is correct
The Senior User ensures that the products meet user requirements.
- ✗
Project Assurance
Why it's wrong here
Project Assurance checks compliance but does not define user needs.
- ✗
Senior Supplier
Why it's wrong here
The Senior Supplier ensures that the products are feasible to deliver.
- ✗
Project Manager
Why it's wrong here
The PM manages the project but does not represent user needs.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.