PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are purposes of the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorise the project's initiation
Directing a Project ensures the Project Board provides direction and makes key decisions, including authorising initiation, stage plans, and closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Produce the Project Plan
Why it's wrong here
The Project Plan is produced in Initiating a Project.
- ✓
Authorise the project's initiation
Why this is correct
Correct. The Board authorises initiation.
- ✓
Authorise the project closure
Why this is correct
Correct. The Board authorises closure.
- ✗
Deliver work packages
Why it's wrong here
Work packages are delivered by the Team Manager in Managing Product Delivery.
- ✗
Manage day-to-day work of the project
Why it's wrong here
Day-to-day management is done by the Project Manager in Controlling a Stage.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.