Common Project Charter Components: High-Level Scope, Business Case, and Budget Summary
Which THREE items are typically found in a project charter? (Select THREE)
Quick Answer
The correct answer includes the budget summary, along with the high-level scope and business case, as three essential components of a project charter. The project charter serves as the formal authorization document that empowers the project manager to apply organizational resources, and it must define the high-level scope to establish project boundaries without detailed decomposition. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of what belongs in the charter versus the project management plan—a common trap is confusing detailed requirements or work breakdown structures with the charter’s high-level focus. The business case justifies the project’s existence, while the budget summary provides a top-level cost estimate, not a detailed budget. To remember these, think of the acronym “BBS” for Business case, Budget summary, and Scope—three pillars that authorize and frame the project from the start.
⚠ Common exam trap
CompTIA often tests the distinction between high-level charter content and detailed planning artifacts, so candidates mistakenly include the WBS or detailed risk analysis because they confuse the charter's authorization purpose with the project management plan's execution details.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
High-level scope
The project charter is the formal authorization document that establishes the project and provides the project manager with the authority to apply organizational resources. It must include the high-level scope to define the boundaries of the project without going into detailed decomposition, which is why option A is correct.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
High-level scope
Why this is correct
The charter provides a high-level description of the project scope.
- ✗
Work breakdown structure
Why it's wrong here
The WBS is developed during project planning, not included in the charter.
- ✓
Business case
Why this is correct
The charter includes the business need or justification for the project.
- ✓
Budget summary
Why this is correct
A high-level budget is often included in the charter.
- ✗
Detailed risk analysis
Why it's wrong here
Detailed risk analysis is part of the risk management process, not the charter.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Same concept, more angles
2 more ways this is tested on PK0-005
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. Refer to the exhibit. Which element of the project charter is missing from this exhibit?
hard- A.Success criteria
- B.Assumptions
- C.Constraints
- ✓ D.Project sponsor
Why D: The project charter must identify the project sponsor, who provides authority and funding. The exhibit lists the project manager, business case, and high-level scope but omits the sponsor, making option D correct.
Variation 2. Which THREE are common types of project management documentation? (Choose three.)
medium- A.Network diagram
- ✓ B.Project charter
- ✓ C.Risk register
- D.Server configuration file
- ✓ E.Scope statement
Why B: The project charter is a foundational document that formally authorizes a project, assigns the project manager, and provides a high-level summary of objectives, scope, and key stakeholders. It is one of the three common types of project management documentation, alongside the risk register and scope statement, as defined in the PMBOK Guide and tested in the PK0-005 exam.
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.