mediumMultiple ChoiceObjective-mapped
PK0-005 Practice Question: During project execution, the team lead reports…
During project execution, the team lead reports that a key developer is leaving the company. The project sponsor is concerned about the impact on the project schedule. What should the project manager do FIRST?
⚠ Common exam trap
The trap here is that candidates may jump to a corrective action (like hiring or reassigning) without first performing the required risk assessment, which is the foundational step in the risk management process.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Update the risk register and assess the impact.
The correct first step is to update the risk register and assess the impact because the departure of a key developer is a known risk that should have been identified during planning. By documenting the event and evaluating its effect on the schedule, the project manager can make informed decisions about mitigation strategies. This aligns with the PMBOK risk management process, where risk response planning follows risk assessment.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Update the risk register and assess the impact.
Why this is correct
Correct. This is the immediate next step to document and evaluate the risk.
- ✗
Immediately hire a replacement developer.
Why it's wrong here
Hiring without analysis may not address the specific needs and could be premature.
- ✗
Reassign tasks to remaining team members.
Why it's wrong here
Task reassignment may overload resources and is not a first step without analysis.
- ✗
Inform stakeholders of the schedule delay.
Why it's wrong here
Informing stakeholders is important but should follow impact assessment and response planning.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.