PK0-005 Project Life Cycle Practice Question
Which of the following is a key input to the change control process when a change request is submitted?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Impact analysis
When a change request is submitted, an impact analysis is performed to evaluate the effects on scope, schedule, cost, and quality. This analysis is then presented to the Change Control Board for decision.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Final project report
Why it's wrong here
The final report is produced at closure.
- ✗
Lessons learned
Why it's wrong here
Lessons learned are created during closing, not used as input to change control.
- ✓
Impact analysis
Why this is correct
Impact analysis assesses the effects of the change before approval.
- ✗
Performance measurement baseline
Why it's wrong here
The baseline is updated after approval, not an input to the change control process.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.