Who is responsible for producing a Checkpoint Report?
⚠ Common exam trap
Watch out — candidates often confuse the Checkpoint Report with the Highlight Report, leading candidates to incorrectly select the Project Manager, who produces the Highlight Report, not the Checkpoint Report.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Team Manager
The Checkpoint Report is a progress report on the work completed within a Work Package during a specific period. According to PRINCE2, the Team Manager is responsible for producing the Checkpoint Report to inform the Project Manager of progress against the Work Package plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project Board
Why it's wrong here
The Board does not produce Checkpoint Reports.
- ✗
Project Manager
Why it's wrong here
The PM receives Checkpoint Reports but does not produce them.
- ✓
Team Manager
Why this is correct
The Team Manager produces Checkpoint Reports in MP.
- ✗
Project Support
Why it's wrong here
Project Support may assist but is not responsible for producing Checkpoint Reports.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.