Which THREE of the following are responsibilities of the Project Board during the Directing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Authorizing the initiation of the project
The Project Board authorizes initiation, authorizes stage plans, and gives ad-hoc direction. Producing Highlight Reports and managing day-to-day issues are PM/CM responsibilities.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Producing Highlight Reports
Why it's wrong here
Highlight Reports are produced by the PM in CS.
- ✓
Authorizing the initiation of the project
Why this is correct
Correct. The Board authorizes initiation in DP.
- ✓
Authorizing stage plans
Why this is correct
Correct. The Board authorizes each stage plan.
- ✓
Giving ad-hoc direction to the Project Manager
Why this is correct
Correct. The Board provides direction as needed.
- ✗
Managing day-to-day issues within the stage
Why it's wrong here
The PM manages day-to-day issues in CS.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.