Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

When should the Project Manager escalate an issue to the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

When the issue cannot be resolved within the delegated tolerances

Issues that threaten tolerances or require changes to baselines should be escalated. The PM manages issues within their authority.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • When the issue involves the Project Manager's own performance

    Why it's wrong here

    Not a standard criterion.

  • Only at the end of a stage

    Why it's wrong here

    Escalation can happen anytime.

  • When the issue cannot be resolved within the delegated tolerances

    Why this is correct

    Escalation is required when tolerances are forecast to be exceeded.

  • Only when the issue is identified

    Why it's wrong here

    Not every issue needs escalation.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.