Courseiva
PRINCE2 ProcessesmediumMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

During the Managing Product Delivery process, who produces Checkpoint Reports?

⚠ Common exam trap

Watch out — candidates often confuse the roles of Project Manager and Team Manager, assuming the Project Manager produces all reports, but PRINCE2 specifically assigns Checkpoint Reports to the Team Manager to maintain clear delegation and control.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Team Manager

In PRINCE2, the Team Manager is responsible for producing Checkpoint Reports during the Managing Product Delivery process. These reports provide the Project Manager with progress updates on work packages, including actual versus planned progress, quality activities, and any issues or risks. The Team Manager is the role that manages the day-to-day work of the team and reports back to the Project Manager.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The PM produces Highlight Reports, not Checkpoint Reports.

  • Project Board

    Why it's wrong here

    The Board receives reports but does not produce them.

  • Project Support

    Why it's wrong here

    Project Support may assist but does not own Checkpoint Reports.

  • Team Manager

    Why this is correct

    The Team Manager produces Checkpoint Reports at intervals defined in the Work Package.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

5 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?

medium
  • A.The Senior Supplier
  • B.The Project Support
  • C.The Team Manager
  • D.The Project Board

Why C: Checkpoint Reports are prepared by the Team Manager and sent to the Project Manager.

Variation 2. During the Controlling a Stage process, the Project Manager receives a Checkpoint Report. Who prepared this report?

medium
  • A.Project Manager
  • B.Project Board
  • C.Team Manager
  • D.Project Support

Why C: In PRINCE2, the Checkpoint Report is a progress report prepared by the Team Manager on behalf of the team. It provides the Project Manager with a snapshot of the work completed, planned, and any issues or risks within a work package. The Project Manager uses this report during the Controlling a Stage process to monitor progress and make informed decisions.

Variation 3. During the Controlling a Stage process, who is responsible for producing Checkpoint Reports?

medium
  • A.Team Manager
  • B.Project Manager
  • C.Project Board
  • D.Project Support

Why A: Checkpoint Reports are produced by the Team Manager and sent to the Project Manager to inform about progress within a Work Package.

Variation 4. During the Managing Product Delivery process, who produces the Checkpoint Report?

medium
  • A.Project Manager
  • B.Team Manager
  • C.Project Support
  • D.Project Board

Why B: The Team Manager is responsible for producing Checkpoint Reports to inform the Project Manager of progress within a Work Package.

Variation 5. Who produces Checkpoint Reports during the Managing Product Delivery process?

medium
  • A.Project Board
  • B.Team Manager
  • C.Project Support
  • D.Project Manager

Why B: The Team Manager is responsible for producing Checkpoint Reports during the Managing Product Delivery process. These reports provide the Project Manager with progress information on the work package assigned to the team, including achievements, next steps, and any issues or risks. This aligns with PRINCE2's principle of management by exception, where the Team Manager reports at intervals defined in the Work Package.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.