PRINCE2F PRINCE2 Processes Practice Question
What is the difference between Starting Up a Project and Initiating a Project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
SU produces the Project Brief; IP produces the PID
SU is a pre-project process to check viability; IP is the full initiation to establish the project on a solid foundation, creating the PID.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
SU appoints the Project Manager; IP appoints the Executive
Why it's wrong here
The Executive is appointed during SU, not IP.
- ✓
SU produces the Project Brief; IP produces the PID
Why this is correct
Correct: SU creates the Project Brief; IP creates the PID.
- ✗
SU plans the entire project; IP plans only the first stage
Why it's wrong here
SU produces an initiation stage plan; IP produces a project plan and the next stage plan.
- ✗
SU is mandatory; IP is optional
Why it's wrong here
Both processes are mandatory.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.