Which TWO of the following are activities performed during the Controlling a Stage process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the Business Case

CS includes authorizing Work Packages, reviewing progress, and reporting. Producing the PID is done in IP.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Produce the Project Initiation Documentation

    Why it's wrong here

    PID is produced in IP.

  • Review the Business Case

    Why this is correct

    The PM reviews the Business Case in CS.

  • Produce the End Project Report

    Why it's wrong here

    End Project Report is produced in CP.

  • Appoint the Executive

    Why it's wrong here

    Executive is appointed in SU.

  • Authorize Work Packages

    Why this is correct

    Yes, this is done in CS.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.