Which TWO of the following are activities performed during the Controlling a Stage process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Review the Business Case
CS includes authorizing Work Packages, reviewing progress, and reporting. Producing the PID is done in IP.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Produce the Project Initiation Documentation
Why it's wrong here
PID is produced in IP.
- ✓
Review the Business Case
Why this is correct
The PM reviews the Business Case in CS.
- ✗
Produce the End Project Report
Why it's wrong here
End Project Report is produced in CP.
- ✗
Appoint the Executive
Why it's wrong here
Executive is appointed in SU.
- ✓
Authorize Work Packages
Why this is correct
Yes, this is done in CS.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.