PRINCE2 ProcesseshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

In the Controlling a Stage process, a Team Manager reports that a product is complete. Which activity does the Project Manager perform next?

⚠ Common exam trap

Candidates often confuse the immediate operational step (quality review) with higher-level reporting or planning activities, assuming that a completion report automatically triggers a Highlight Report or stage approval without the necessary quality check first.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the product to confirm it meets quality criteria

In the Controlling a Stage process, after a Team Manager reports that a product is complete, the Project Manager must first review the product to confirm it meets the quality criteria defined in the Product Description. This is part of the 'Review Work Package' activity, ensuring that the product is fit for purpose before any further actions, such as reporting or planning, occur. Only after this quality check can the Project Manager proceed to other activities like updating logs or sending reports.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Send a Highlight Report to the Project Board

    Why it's wrong here

    Highlight Reports are periodic, not triggered by a single product completion.

  • Approve the next Stage Plan

    Why it's wrong here

    Stage Plan approval is done in Managing a Stage Boundary or Directing a Project.

  • Review the product to confirm it meets quality criteria

    Why this is correct

    The PM must check that the product meets the defined quality criteria before acceptance.

  • Update the Project Plan

    Why it's wrong here

    Updating the Project Plan typically occurs in Managing a Stage Boundary.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.