Which THREE of the following are components of the Project Initiation Documentation (PID)?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Plan

Options A, D, and E are correct. The Project Initiation Documentation (PID) includes the Project Plan, Risk Management Approach, and Business Case. The Highlight Report is a product of the Controlling a Stage process, and the Checkpoint Report is a product of the Managing Product Delivery process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Plan

    Why this is correct

    Project Plan is part of PID.

  • Highlight Report

    Why it's wrong here

    Highlight Report is produced during CS.

  • Checkpoint Report

    Why it's wrong here

    Checkpoint Report is from MP.

  • Risk Management Approach

    Why this is correct

    Risk Management Approach is part of PID.

  • Business Case

    Why this is correct

    Business Case is a key component of PID.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are components of the Project Initiation Documentation (PID)?

medium
  • A.Daily Log
  • B.Risk Management Approach
  • C.Project Plan
  • D.Business Case
  • E.Lessons Report

Why B: The PID includes the Project Plan, Business Case, and Risk Management Approach. The Daily Log is an ongoing log, and the Lessons Report is produced in Closing a Project.

Variation 2. Which THREE of the following are components of the Project Initiation Documentation (PID)?

medium
  • A.Daily Log
  • B.Project Plan
  • C.Risk Management Approach
  • D.Business Case
  • E.Checkpoint Report

Why B: The PID includes the Project Plan, Business Case, and Risk Management Approach. The Daily Log is a project log used throughout, not part of PID. The Checkpoint Report is a product of Managing Product Delivery.

Variation 3. Which TWO of the following are components of the Project Initiation Documentation (PID)?

easy
  • A.Checkpoint Report
  • B.Business Case
  • C.End Stage Report
  • D.Project Plan
  • E.Lessons Report

Why B: The Project Initiation Documentation (PID) is a key PRINCE2 management product that defines the project's scope, justification, and approach. The Business Case is a mandatory component of the PID because it provides the justification for the project, while the Project Plan is also a mandatory component as it defines the schedule, cost, and resource baselines for the entire project.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.