CCNA People: organizations, teams, and leadership Questions

75 of 335 questions · Page 3/5 · People: organizations, teams, and leadership · Answers revealed

151
MCQmedium

What is the key output of the 'Starting Up a Project' process?

A.Project Brief
B.Project Initiation Documentation
C.Business Case
D.Stage Plan
AnswerA

The Project Brief is created during Starting Up a Project.

Why this answer

The Project Brief is the key output of the Starting Up a Project process, providing the initial information to decide whether to proceed to initiation.

152
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Manager in PRINCE2?

Select 3 answers
A.Producing the Project Initiation Documentation
B.Reporting progress to the Project Board
C.Approving the Business Case
D.Managing the project's day-to-day activities
E.Providing independent assurance to the Project Board
AnswersA, B, D

The PM is responsible for creating the PID.

Why this answer

Option A is correct because the Project Manager is responsible for producing the Project Initiation Documentation (PID) in PRINCE2. The PID is a key deliverable that consolidates the project's scope, business justification, plans, and controls, and the Project Manager compiles it based on input from the Project Board and other stakeholders. This responsibility is explicitly defined in the PRINCE2 Project Manager role description.

Exam trap

The trap here is confusing the Project Manager's responsibility for maintaining the Business Case with the authority to approve it, which is reserved for the Project Board or Senior User.

153
MCQmedium

During the Managing a Stage Boundary process, the Project Manager produces an Exception Plan. What triggers this?

A.The stage is forecast to exceed its tolerance
B.A Team Manager reports a delay in the Work Package
C.The Project Board requests a new plan for the next stage
D.The Project Manager decides to change the project approach
AnswerA

An Exception Plan replaces the current plan when tolerances are breached.

Why this answer

An Exception Plan is produced when a stage is forecast to exceed its tolerances, as an alternative to the current Stage Plan, for approval by the Project Board.

154
MCQmedium

A Project Manager delegates the management of a Work Package to a Team Manager. What is the Team Manager's responsibility?

A.To perform Project Assurance for the Work Package
B.To deliver the Work Package within tolerances
C.To raise issues directly to the Project Board
D.To update the project plan with actual progress
AnswerB

The Team Manager manages the work and reports to the PM.

Why this answer

The Team Manager is responsible for delivering the Work Package within agreed tolerances and reporting progress via Checkpoint Reports.

155
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Initiation Documentation
B.Stage Plan
C.Project Brief
D.Project Plan
AnswerA

The PID is the comprehensive document created during Initiation.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process, providing a foundation for the project.

156
MCQmedium

In PRINCE2, what is the primary difference between Project Assurance and a quality review?

A.There is no difference; they are synonymous.
B.Project Assurance ensures the project is on track; a quality review checks product quality.
C.Project Assurance is performed by the Project Manager; quality review is performed by the team.
D.Project Assurance is a process; quality review is a role.
AnswerB

Project Assurance is about governance; quality review is about product verification.

Why this answer

Option B is correct because Project Assurance and quality reviews serve distinct purposes in PRINCE2. Project Assurance is an independent oversight function that ensures the project remains viable, compliant, and on track against the business case and plans. A quality review, on the other hand, is a structured technique used to assess whether a specific product meets its defined quality criteria and is fit for purpose.

Exam trap

The trap here is that candidates often confuse the independent oversight role of Project Assurance with the product-focused checking of a quality review, leading them to think they are the same or that the Project Manager performs assurance.

How to eliminate wrong answers

Option A is wrong because Project Assurance and a quality review are not synonymous; they have different objectives, participants, and timing within the project lifecycle. Option C is wrong because Project Assurance is performed by an independent person or group (often from the corporate, programme management, or customer side), not by the Project Manager; the Project Manager is responsible for day-to-day management, not assurance. Option D is wrong because Project Assurance is a role (or set of responsibilities), not a process; a quality review is a technique (or activity), not a role.

157
MCQmedium

A project is in the Initiating a Project process. Which document is the key output of this process?

A.Stage Plan
B.Project Initiation Documentation (PID)
C.Business Case
D.Project Brief
AnswerB

The PID is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. Option B is correct.

158
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Team Manager
B.Executive (Senior Responsible Owner)
C.Project Manager
D.Senior User
AnswerB

The Executive is accountable for the Business Case and its maintenance.

Why this answer

The Executive (Senior Responsible Owner) is the role accountable for the Business Case and its ongoing justification throughout the project. PRINCE2 requires the Business Case to be maintained and reviewed at every stage boundary to ensure continued viability, and this responsibility rests with the Executive, not the Project Manager or Team Manager.

Exam trap

PeopleCert often tests the misconception that the Project Manager is responsible for the Business Case because they create it, but the exam emphasizes that accountability (maintenance and approval) belongs to the Executive.

How to eliminate wrong answers

Option A is wrong because the Team Manager is responsible for delivering the work packages within a stage, not for maintaining the Business Case. Option C is wrong because the Project Manager manages the day-to-day project activities and produces the Business Case, but the accountability for its maintenance and approval lies with the Executive. Option D is wrong because the Senior User represents the users' interests and specifies the requirements, but does not own or maintain the Business Case.

159
MCQmedium

During the Controlling a Stage process, the Project Manager identifies that the project is forecast to exceed the agreed cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Close the project immediately as the Business Case is no longer viable
C.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

This is the correct escalation procedure per management by exception.

Why this answer

Option D is correct because PRINCE2's Controlling a Stage process requires the Project Manager to escalate any forecast deviation beyond the agreed stage tolerance to the Project Board via an Exception Report. The Project Manager cannot proceed without the Board's direction, as the tolerance is a delegated authority limit set by the Board.

Exam trap

PeopleCert often tests the misconception that the Project Manager can handle tolerance breaches by continuing and reporting later, but PRINCE2 mandates immediate escalation when tolerance is forecast to be exceeded.

How to eliminate wrong answers

Option A is wrong because the Project Manager does not have the authority to increase the project budget unilaterally; budget changes require Project Board approval. Option B is wrong because a cost overrun within a stage does not automatically invalidate the Business Case; the Board must assess viability after receiving the Exception Report. Option C is wrong because the Project Manager must report the issue immediately via an Exception Report, not wait for the next Highlight Report, as the deviation exceeds the agreed tolerance.

160
Multi-Selecteasy

Which TWO of the following are true about Project Assurance?

Select 2 answers
A.It can be performed by the Project Manager if no one else is available
B.It provides independent assurance to the Project Board
C.It prepares the Checkpoint Reports
D.It is responsible for ensuring the project remains viable
E.It includes administrative support tasks
AnswersB, D

Yes, that is the primary role.

Why this answer

Project Assurance provides an independent view of the project's progress, ensuring that the project remains viable and adheres to the business case. It reports directly to the Project Board, not the Project Manager, to maintain objectivity. This independence is critical for the Board to make informed decisions about project continuation.

Exam trap

The trap here is confusing Project Assurance with Project Support or the Project Manager's duties, leading candidates to think the Project Manager can step in for assurance or that administrative tasks belong to assurance.

161
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; they are synonyms
B.A Request for Change is about schedule changes; an Off-specification is about quality issues
C.A Request for Change is a proposal for a modification; an Off-specification is a deviation that has occurred
D.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Team Manager
AnswerC

An RFC is a request to change an approved product; an Off-specification is a non-conformance already present.

Why this answer

A Request for Change is a proposal for a change to a product that has been approved, while an Off-specification is an actual deviation from the specification (something that was supposed to be done but wasn't done correctly).

162
MCQeasy

A project manager notices that team members from different departments are unclear about their roles and responsibilities. According to PRINCE2, which management product should be used to clarify this?

A.Project Initiation Documentation (PID)
B.Business Case
C.Risk Register
D.Quality Register
AnswerA

The PID defines roles and responsibilities.

Why this answer

In PRINCE2, the Project Initiation Documentation (PID) provides a comprehensive baseline for the project, including defined roles and responsibilities. When team members are unclear about their roles, the PID is the management product that formally documents these assignments, ensuring everyone understands their accountabilities. This aligns with the PRINCE2 principle of 'defined roles and responsibilities' and the 'People' domain focus on organizational clarity.

Exam trap

PeopleCert often tests the distinction between the PID as the comprehensive 'rulebook' for the project and other registers or documents that serve narrower, specific purposes, leading candidates to mistakenly choose a register that tracks outputs rather than defines responsibilities.

How to eliminate wrong answers

Option B is wrong because the Business Case documents the justification for the project, including costs, benefits, and risks, but it does not define individual roles or responsibilities. Option C is wrong because the Risk Register captures identified risks, their analysis, and responses, not role assignments. Option D is wrong because the Quality Register records planned and executed quality activities and their results, not who is responsible for specific tasks or deliverables.

163
MCQmedium

A project is in the Initiating a Project process. Which key document is produced as an output of this process?

A.Project Initiation Documentation
B.Project Brief
C.Stage Plan
D.Benefits Review Plan
AnswerA

The PID is the main output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key document produced as an output of the Initiating a Project process. It consolidates the Project Brief, Business Case, and detailed plans into a single source of information that defines the project's scope, objectives, and controls, and is used to obtain authorization to proceed.

Exam trap

PeopleCert often tests the distinction between documents produced in different processes; the trap here is confusing the Project Brief (output of Starting Up a Project) with the PID (output of Initiating a Project), leading candidates to select the Brief as the key output of the initiation process.

How to eliminate wrong answers

Option B (Project Brief) is wrong because the Project Brief is created during the Starting Up a Project process, not Initiating a Project; it serves as input to the Initiating a Project process. Option C (Stage Plan) is wrong because Stage Plans are produced during the Managing a Stage Boundary process, not Initiating a Project; the PID includes the Project Plan, not a Stage Plan. Option D (Benefits Review Plan) is wrong because the Benefits Review Plan is created during the Initiating a Project process but is a separate document, not the key document; the PID is the primary output that contains the project strategy and controls.

164
MCQhard

What is the key difference between Project Assurance and a quality review?

A.Project Assurance provides continuous independent oversight, while a quality review is a specific event to examine a product
B.Project Assurance focuses on the Business Case, while a quality review focuses on the Project Plan
C.Project Assurance is a role, while a quality review is a process in Managing a Stage Boundary
D.Project Assurance is performed by the Project Manager, while a quality review is performed by the Project Board
AnswerA

This captures the continuous vs event-based distinction.

Why this answer

Project Assurance is a continuous, independent oversight function that ensures the project remains viable and compliant with standards throughout its lifecycle, while a quality review is a specific, time-boxed event focused on examining a product's fitness for purpose. In PRINCE2, Project Assurance is a role (often assigned to the Project Board or a separate person) that provides objective checks, whereas a quality review is a technique within the quality management approach used to verify that a product meets its quality criteria. This distinction is fundamental because it separates ongoing governance from discrete product verification activities.

Exam trap

The trap here is that candidates confuse the continuous, role-based nature of Project Assurance with the event-based, technique-driven nature of a quality review, often assuming both are 'checks' that serve the same purpose or that a quality review is a process rather than a technique.

How to eliminate wrong answers

Option B is wrong because Project Assurance covers all aspects of the project (including Business Case, risks, quality, and progress), not just the Business Case, and a quality review examines any product (not just the Project Plan) against its quality criteria. Option C is wrong because while Project Assurance is indeed a role, a quality review is a technique (not a process) that can be used in multiple PRINCE2 processes, including Managing Product Delivery and Managing a Stage Boundary, not exclusively the latter. Option D is wrong because Project Assurance is performed by an independent role (often a Project Board member or a dedicated assurance person), not by the Project Manager, and a quality review is performed by a review team (including the producer, reviewers, and a chair), not by the Project Board.

165
Multi-Selectmedium

Which TWO of the following are differences between Project Assurance and a quality review?

Select 2 answers
A.Project Assurance is performed by the Project Manager; a quality review is performed by the team
B.Project Assurance is optional; a quality review is mandatory in every stage
C.Project Assurance reports to the Project Board; a quality review reports to the Project Manager
D.Project Assurance is an ongoing role; a quality review is a specific event
E.Project Assurance focuses on governance; a quality review focuses on product quality
AnswersD, E

Assurance is continuous; a quality review is a scheduled check.

Why this answer

Project Assurance is a continuous role monitoring compliance and governance, while a quality review is a specific event to examine a product. Assurance is independent; quality reviews involve peers.

166
MCQhard

In the RACI model used in PRINCE2, what is the difference between accountability (A) and responsibility (R)?

A.They are interchangeable terms
B.Accountability means performing the task; responsibility means approving the outcome
C.Accountability is delegated to the Project Manager; responsibility is retained by the Project Board
D.Accountability means ultimate ownership; responsibility means performing the task
AnswerD

This correctly distinguishes the two concepts.

Why this answer

Accountability means ultimate ownership and final decision-making authority, while responsibility means performing the work. Option A is correct.

167
MCQmedium

In PRINCE2, which role provides independent assurance to the Project Board that the project is being conducted correctly?

A.Project Manager
B.Project Support
C.Project Assurance
D.Team Manager
AnswerC

Project Assurance is an independent role that assures the Project Board.

Why this answer

Project Assurance is independent from the Project Manager and reports to the Project Board.

168
MCQmedium

Which of the following is NOT a responsibility of the Project Manager?

A.Preparing Highlight Reports for the Project Board
B.Performing Project Assurance
C.Authorizing work packages for the Team Manager
D.Managing the project within tolerances
AnswerB

Project Assurance is independent and cannot be performed by the PM.

Why this answer

Project Assurance is independent and cannot be delegated to the Project Manager.

169
MCQhard

What is the key difference between Project Assurance and a quality review?

A.There is no difference; they are different terms for the same activity
B.Project Assurance is performed by the Project Manager, while quality reviews are performed by team members
C.Project Assurance focuses on financial aspects only, while quality reviews focus on technical aspects
D.Project Assurance is an ongoing role, while a quality review is a specific event to evaluate a product
AnswerD

Assurance provides continuous oversight; quality reviews are discrete checks on specific products.

Why this answer

Project Assurance is an independent, ongoing role to ensure the project remains aligned with the Business Case and standards. A quality review is a specific technique to assess the quality of a product. Assurance is a role; quality review is a process.

170
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Manager?

Select 3 answers
A.Managing day-to-day project activities within tolerances
B.Preparing the Stage Plans
C.Maintaining the Business Case
D.Providing independent assurance to the Project Board
E.Escalating forecast tolerance deviations to the Project Board
AnswersA, B, E

The PM manages the project on a day-to-day basis.

Why this answer

Option A is correct because the Project Manager is responsible for the day-to-day management of the project within the tolerances set by the Project Board. This includes monitoring progress, managing the team, and ensuring that work packages are delivered on time and within budget. The Project Manager must operate within these tolerances and only escalate to the Project Board when forecasts deviate beyond them.

Exam trap

The trap here is confusing the Project Manager's operational responsibilities with the strategic or assurance roles of the Project Board and Project Assurance, leading candidates to incorrectly select 'Maintaining the Business Case' or 'Providing independent assurance'.

171
MCQmedium

A project is in the Initiating a Project process. Which role is responsible for preparing the Project Initiation Documentation (PID)?

A.Team Manager
B.Senior Responsible Owner
C.Project Manager
D.Project Assurance
AnswerC

The PM prepares the PID.

Why this answer

In PRINCE2, the Project Manager is responsible for preparing the Project Initiation Documentation (PID) during the Initiating a Project process. The PID is a key management product that defines the project's scope, objectives, and controls, and the Project Manager must compile it based on input from the project board and other stakeholders.

Exam trap

The trap here is that candidates often confuse the Project Manager's role in preparing the PID with the Project Board's role in approving it, or mistakenly assign the task to the Senior Responsible Owner due to the SRO's authority over the business case.

How to eliminate wrong answers

Option A is wrong because the Team Manager is responsible for delivering the work packages within a stage, not for creating the PID. Option B is wrong because the Senior Responsible Owner (SRO) is the executive role that owns the business case and provides overall direction, but does not prepare the PID. Option D is wrong because Project Assurance provides independent oversight and checks the PID for compliance, but does not prepare it.

172
MCQhard

Which statement correctly describes the relationship between Project Assurance and quality review?

A.They are the same thing
B.Quality review is a part of Project Assurance
C.Project Assurance is a role; quality review is a technique
D.Project Assurance performs quality reviews
AnswerC

Correct distinction.

Why this answer

Project Assurance is a role within the PRINCE2 framework, responsible for ensuring that the project remains viable and compliant with its business case, while quality review is a technique used to assess the quality of products. The correct relationship is that Project Assurance is a role, and quality review is a technique, making option C correct. They are distinct concepts: one is a governance role, the other is a specific method for evaluating deliverables.

Exam trap

The trap here is that candidates often confuse the governance role of Project Assurance with the execution of quality activities, leading them to incorrectly select option D, when in fact Project Assurance oversees quality but does not perform the quality review technique itself.

How to eliminate wrong answers

Option A is wrong because Project Assurance and quality review are not the same thing; Project Assurance is a role focused on objective oversight, while quality review is a technique for product evaluation. Option B is wrong because quality review is not a part of Project Assurance; rather, Project Assurance may use quality reviews as one of many techniques to fulfill its responsibilities, but quality review is a separate technique defined in the PRINCE2 quality theme. Option D is wrong because Project Assurance does not perform quality reviews; quality reviews are conducted by a review team including the producer, reviewers, and a chair, while Project Assurance provides independent oversight and may attend but does not execute the review itself.

173
MCQmedium

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To reduce the workload of the Project Manager
B.To align with a functional organizational structure
C.To provide independent assurance to the Project Board
D.To allow the Project Manager to focus on team management
AnswerC

Independence is key to avoid bias.

Why this answer

Separation ensures independent oversight. Project Assurance provides an objective check on the project's health, free from the PM's day-to-day pressures.

174
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To provide the Project Board with information to approve the next stage
B.To authorize the start of the project
C.To control the day-to-day work of the project
D.To produce the Project Initiation Documentation
AnswerA

Correct. The process enables stage boundary review and approval.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next Stage Plan, and decide whether to continue the project. It ensures that the project remains viable by assessing progress against the Business Case and updating plans accordingly.

Exam trap

PeopleCert often tests the distinction between processes that produce plans (Initiating a Project) versus processes that review and approve stage-level plans (Managing a Stage Boundary), leading candidates to confuse the production of the Project Initiation Documentation with stage boundary activities.

How to eliminate wrong answers

Option B is wrong because authorizing the start of the project is the purpose of the Starting Up a Project process, not Managing a Stage Boundary. Option C is wrong because controlling day-to-day work is the responsibility of the Managing Product Delivery process, which handles work package assignments and progress reporting. Option D is wrong because producing the Project Initiation Documentation is the output of the Initiating a Project process, which occurs before any stage boundaries are managed.

175
MCQmedium

Who is responsible for producing the Checkpoint Report?

A.Project Support
B.Team Manager
C.Project Manager
D.Senior User
AnswerB

Correct: The Team Manager produces the Checkpoint Report.

Why this answer

The Team Manager produces the Checkpoint Report for the Project Manager to report progress of a Work Package.

176
MCQhard

In PRINCE2, why is the Project Assurance role separated from the Project Manager?

A.To reduce the workload of the Project Manager.
B.To ensure that the Project Board has independent and objective advice.
C.To align with the PRINCE2 principle of continued business justification.
D.To allow the Project Manager to focus on delivery while Assurance handles quality.
AnswerB

Independence ensures that Project Assurance can objectively monitor the project.

Why this answer

Project Assurance provides independent oversight to ensure that the project is managed correctly. If the Project Manager also performed assurance, it would compromise objectivity and independence.

177
MCQmedium

A stakeholder is concerned that the project is not delivering value for money. Which role should this concern be raised with?

A.Senior User
B.Project Assurance
C.Executive
D.Project Manager
AnswerC

Correct.

Why this answer

The Executive is ultimately accountable for the project's business justification, including ensuring value for money. Concerns about cost versus benefits must be escalated to the Executive, who owns the Business Case and has the authority to approve changes or stop the project if value is not being delivered.

Exam trap

The trap here is confusing the Project Manager's responsibility for day-to-day cost control with the Executive's accountability for overall value for money and the Business Case.

How to eliminate wrong answers

Option A is wrong because the Senior User represents the users' needs and specifies the expected benefits, but is not accountable for overall value for money or the business case. Option B is wrong because Project Assurance provides independent oversight and checks compliance, but does not have the authority to make decisions on value for money; it reports issues to the Executive. Option D is wrong because the Project Manager manages day-to-day activities and escalates issues, but is not accountable for the business justification or value for money decisions.

178
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Project Brief
B.Project Plan
C.Business Case
D.Project Initiation Documentation (PID)
AnswerD

The PID is the formal document that defines the project and is created during Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides a baseline for the project and is used by the Project Board to decide whether to proceed.

179
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change relates to a change in scope; an Off-specification relates to a change in quality
B.There is no difference; they are synonyms
C.A Request for Change is raised by the Project Manager; an Off-specification is raised by the Team Manager
D.A Request for Change is a proposed change to a baselined product; an Off-specification is a product that does not meet its specification
AnswerD

This correctly describes the difference.

Why this answer

Option D is correct because in PRINCE2, a Request for Change (RFC) is a formal proposal to modify a baselined product, while an Off-specification (Off-spec) is a notification that a product does not meet its agreed specification. The key distinction is that an RFC addresses a change to a product that has already been approved, whereas an Off-spec identifies a failure to meet the original requirements. This aligns with PRINCE2's change control approach, where both are captured in the Issue Register but serve different purposes.

Exam trap

The trap here is that candidates confuse the terms by associating RFCs with scope changes and Off-specs with quality defects, when in fact both can relate to any aspect of a product's specification, and the true difference lies in whether the product is baselined (RFC) or non-conforming (Off-spec).

How to eliminate wrong answers

Option A is wrong because it incorrectly associates RFCs solely with scope changes and Off-specs solely with quality changes; in PRINCE2, RFCs can affect any baselined aspect (scope, quality, time, cost) and Off-specs are about non-conformance to any specification, not just quality. Option B is wrong because RFCs and Off-specs are distinct concepts with different triggers and actions; they are not synonyms. Option C is wrong because both RFCs and Off-specs can be raised by any project stakeholder, not exclusively by the Project Manager or Team Manager; the PRINCE2 guidance states that anyone can raise an issue, which is then logged and assessed.

180
MCQmedium

Which document is produced by the Team Manager to report progress on a Work Package?

A.Checkpoint Report
B.Exception Report
C.Highlight Report
D.End Stage Report
AnswerA

Correct. The Team Manager produces Checkpoint Reports for the Project Manager.

Why this answer

The Checkpoint Report is produced by the Team Manager and sent to the Project Manager to report progress on a Work Package.

181
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Report the overrun in the next Highlight Report
B.Raise an Exception Report to the Project Board
C.Close the project as the Business Case is no longer viable
D.Increase the stage budget and continue
AnswerB

Correct action: escalate immediately via Exception Report.

Why this answer

In PRINCE2, when a project manager forecasts that a stage will exceed its cost tolerance, they must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated limits, and exceeding them requires board-level decision-making, not just reporting or self-authorization. The Exception Report triggers an Exception Plan to recover or adjust the project.

Exam trap

PeopleCert often tests the distinction between reporting (Highlight Report) and escalation (Exception Report), trapping candidates who think a simple status update suffices when tolerances are breached.

How to eliminate wrong answers

Option A is wrong because a Highlight Report is a periodic status update, not an escalation mechanism for tolerance breaches; the Project Manager must raise an Exception Report immediately, not wait for the next Highlight Report. Option C is wrong because exceeding stage cost tolerance does not automatically invalidate the Business Case; the Project Board must assess viability and decide on corrective action, not unilaterally close the project. Option D is wrong because the Project Manager cannot increase the stage budget without authorization; tolerances are set by the Project Board, and only they can approve budget changes through an Exception Plan.

182
MCQeasy

In PRINCE2, who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (Executive)
B.Project Manager
C.Senior Supplier
D.Project Assurance
AnswerA

The SRO is accountable for the Business Case throughout the project.

Why this answer

In PRINCE2, the Executive (also known as the Senior Responsible Owner) is accountable for the Business Case and must ensure it remains viable throughout the project. The Business Case is the key document that justifies the project's initiation and continued existence, and only the Executive has the authority to approve changes to it or decide to close the project if the Business Case is no longer viable.

Exam trap

The trap here is confusing the Project Manager's responsibility for 'managing' the Business Case (updating it, tracking benefits) with the Executive's accountability for 'maintaining' it (owning it, approving changes, deciding to continue or stop).

How to eliminate wrong answers

Option B is wrong because the Project Manager is responsible for creating, updating, and managing the Business Case on a day-to-day basis, but they do not own it; they cannot approve changes or decide to stop the project based on it. Option C is wrong because the Senior Supplier is responsible for providing the project's products and ensuring supplier interests are met, but they do not own the Business Case. Option D is wrong because Project Assurance is an independent monitoring function that checks the Business Case is being managed correctly, but they are not responsible for maintaining it.

183
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (Executive)
B.Project Assurance
C.Project Manager
D.Senior User
AnswerA

The SRO/Executive is accountable for the Business Case.

Why this answer

The Senior Responsible Owner (SRO/Executive) owns the Business Case and is accountable for ensuring it remains viable. The Project Manager maintains the Business Case on behalf of the Executive.

184
MCQeasy

Which PRINCE2 principle ensures that the Project Board delegates decision-making to the Project Manager within defined tolerances?

A.Learn from Experience
B.Continued Business Justification
C.Management by Exception
D.Manage by Stages
AnswerC

This principle defines tolerance-based delegation.

Why this answer

Management by Exception means the PM is empowered within tolerances, and only escalates when tolerances are forecast to be exceeded.

185
MCQhard

Why does PRINCE2 recommend separating the role of Project Manager from Project Assurance?

A.To comply with regulatory requirements
B.To reduce the workload of the Project Manager
C.To provide an independent perspective on the project's status
D.To allow the Project Manager to focus on quality reviews
AnswerC

Independence is key to effective assurance.

Why this answer

Separating Project Manager from Project Assurance ensures objectivity and independence of assurance activities. The Project Manager is responsible for day-to-day management and cannot objectively assess their own work.

186
Multi-Selectmedium

Which TWO roles are part of the Project Board?

Select 2 answers
A.Senior User
B.Team Manager
C.Project Manager
D.Project Support
E.Executive (SRO)
AnswersA, E

The Senior User is a board role.

Why this answer

The Project Board consists of the Executive (SRO), Senior User(s), and Senior Supplier(s).

187
MCQhard

In a project, a Team Manager reports progress to the Project Manager using which report?

A.Highlight Report
B.Exception Report
C.Checkpoint Report
D.End Stage Report
AnswerC

The Team Manager produces Checkpoint Reports for the PM.

Why this answer

The Team Manager produces a Checkpoint Report to inform the Project Manager of progress against the Work Package plan.

188
Multi-Selectmedium

Which TWO of the following are characteristics of the Project Assurance role?

Select 2 answers
A.It is responsible for producing Work Packages
B.It is often performed by the Project Manager
C.It reports to the Project Board
D.It is a subset of Project Support
E.It must be independent of the Project Manager
AnswersC, E

Assurance reports to the Board, not the PM.

Why this answer

Option C is correct because the Project Assurance role is specifically tasked with monitoring and reporting on the project's adherence to PRINCE2 standards, and it reports directly to the Project Board to provide independent oversight. This ensures that the Project Board receives objective assessments of the project's progress and compliance, separate from the Project Manager's perspective.

Exam trap

PeopleCert often tests the misconception that Project Assurance is a subset of Project Support or can be performed by the Project Manager, but PRINCE2 strictly requires independence to maintain objective oversight.

189
MCQeasy

How often should the Project Board meet during a PRINCE2 project?

A.Only at the end of the project
B.Monthly
C.Weekly
D.At the end of each stage and when exceptions occur
AnswerD

The Project Board meets at stage boundaries and when an exception is raised.

Why this answer

Project Board meetings are held at key decision points (end of stages) and when exceptions occur. They are not scheduled at regular intervals but are exception-driven.

190
MCQmedium

Which role is responsible for ensuring that the project's products meet specified quality criteria?

A.Project Assurance
B.Senior User
C.Project Manager
D.Senior Supplier
AnswerB

The Senior User represents the users who will use the product and defines quality needs.

Why this answer

The Senior User is responsible for specifying the requirements and ensuring the final product meets the agreed quality criteria.

191
Multi-Selectmedium

Which THREE of the following are roles on the PRINCE2 Project Board?

Select 3 answers
A.Project Manager
B.Senior Responsible Owner (Executive)
C.Senior User
D.Senior Supplier
E.Team Manager
AnswersB, C, D

Yes, this is the chair of the Project Board.

Why this answer

The Project Board consists of the Senior Responsible Owner (Executive), Senior User, and Senior Supplier.

192
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the stage and approve the next
B.To control day-to-day activities within a stage
C.To plan the entire project in detail
D.To close the project
AnswerA

This is the correct purpose.

Why this answer

Managing a Stage Boundary allows the Project Board to review the current stage's performance, approve the next Stage Plan, and update the Business Case.

193
MCQmedium

A project is in its Initiating a Project process. The Project Manager has prepared the Project Initiation Documentation (PID). Which role is responsible for approving the PID?

A.Project Manager
B.Project Board
C.Project Assurance
D.Senior Responsible Owner
AnswerB

The Project Board collectively approves the PID to authorize the project.

Why this answer

The PID is approved by the Project Board, which includes all three roles (Executive, Senior User, Senior Supplier). The Project Manager prepares it but does not approve it.

194
MCQhard

In PRINCE2, what is the key difference between the Project Assurance role and a quality review?

A.Project Assurance is a role, while quality review is a technique
B.There is no difference; they are the same thing
C.Project Assurance is performed by the Project Manager, while quality review is performed by external auditors
D.Project Assurance focuses on the Business Case, while quality review focuses on the project plan
AnswerA

Project Assurance is a role that ensures the project remains viable; quality review is a technique to verify product quality.

Why this answer

Project Assurance provides ongoing independent oversight of the project, while a quality review is a specific inspection technique used to assess the quality of a product.

195
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To produce the Project Plan
B.To manage the work of the current stage
C.To enable the Project Board to review progress and approve the next stage
D.To close the project
AnswerC

Correct: The process provides a review and decision point for the Project Board.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with the information needed to review the current stage's performance, assess the updated Business Case, and approve the next Stage Plan. This process ensures that the project remains viable and aligned with business objectives before committing resources to the next stage. Option C correctly captures this review and approval purpose.

Exam trap

The trap here is confusing the purpose of Managing a Stage Boundary with Controlling a Stage (option B), as both involve stage-level activities, but only Managing a Stage Boundary focuses on the boundary review and approval of the next stage, not the day-to-day management of work.

How to eliminate wrong answers

Option A is wrong because the Project Plan is created during the Initiating a Project process, not during Managing a Stage Boundary. Option B is wrong because managing the work of the current stage is the purpose of the Controlling a Stage process, not Managing a Stage Boundary. Option D is wrong because closing the project is the purpose of the Closing a Project process, which occurs after all stages are complete.

196
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager?

Select 2 answers
A.Chairing the Project Board meetings
B.Approving Stage Plans
C.Preparing Highlight Reports for the Project Board
D.Producing the Business Case
E.Managing the project on a day-to-day basis
AnswersC, E

Correct.

Why this answer

Option C is correct because the Project Manager is responsible for preparing Highlight Reports to keep the Project Board informed of progress, achievements, and exceptions at regular intervals. Option E is correct because the Project Manager is accountable for the day-to-day management of the project, ensuring tasks are completed, risks are managed, and the project remains on track within the tolerances set by the Project Board.

Exam trap

The trap here is that candidates often confuse the Project Manager's operational responsibilities (like preparing reports and daily management) with the Project Board's governance duties (like chairing meetings and approving plans), leading them to select options that sound plausible but are actually Board-level tasks.

197
MCQhard

A Team Manager receives a Work Package from the Project Manager. During delivery, the Team Manager identifies a potential issue that may cause a delay. What should the Team Manager do first?

A.Update the Project Plan to reflect the delay
B.Take corrective action to avoid the delay
C.Inform the Project Manager via a Checkpoint Report
D.Escalate directly to the Project Board
AnswerC

The Team Manager reports progress and issues to the PM via Checkpoint Reports.

Why this answer

The Team Manager should report the issue to the Project Manager via a Checkpoint Report or exception process, as they are accountable for delivery within tolerances.

198
Multi-Selectmedium

Which THREE of the following are responsibilities of the Project Board?

Select 3 answers
A.Manage day-to-day activities
B.Provide overall direction and control
C.Produce Checkpoint Reports
D.Authorize deviations from tolerances
E.Approve Stage Plans
AnswersB, D, E

The Board directs the project.

Why this answer

The Board approves stage plans (A), authorizes tolerances (C), and makes key decisions (E). B and D are PM responsibilities.

199
MCQmedium

During the Managing a Stage Boundary process, the Project Manager updates the business case. Who is accountable for approving the updated business case?

A.Project Board
B.Senior User
C.Senior Responsible Owner
D.Project Manager
AnswerC

The SRO owns the business case and approves updates.

Why this answer

The Senior Responsible Owner (Executive) is accountable for the business case and approves updates at stage boundaries.

200
MCQeasy

Which role is responsible for managing the delivery of a Work Package?

A.Team Manager
B.Senior User
C.Project Assurance
D.Project Manager
AnswerA

The Team Manager manages the delivery of Work Packages.

Why this answer

The Team Manager is responsible for managing the delivery of a Work Package within a PRINCE2 project. This role coordinates the team members, ensures the work is completed according to the agreed specifications, and reports progress back to the Project Manager. The Team Manager acts as the direct interface between the project management team and the team members executing the work.

Exam trap

PeopleCert often tests the distinction between the Project Manager's overall responsibility and the Team Manager's delegated authority for Work Package delivery, leading candidates to incorrectly select the Project Manager as the answer.

How to eliminate wrong answers

Option B (Senior User) is wrong because the Senior User represents the interests of those who will use the project's products and is responsible for specifying the requirements and benefits, not for managing the delivery of a Work Package. Option C (Project Assurance) is wrong because Project Assurance is an independent monitoring function that checks compliance with PRINCE2 standards and project controls, not a role that manages work package delivery. Option D (Project Manager) is wrong because the Project Manager is responsible for the overall planning, monitoring, and control of the project, but delegates the day-to-day management of a Work Package to the Team Manager.

201
Multi-Selecthard

Which THREE of the following are true about Project Assurance in PRINCE2?

Select 3 answers
A.It is a mandatory role in PRINCE2
B.It can be delegated to the Project Manager
C.It is only performed at the end of each stage
D.It provides independent oversight of the project
E.It reports to the Project Board
AnswersA, D, E

Project Assurance is mandatory, though it can be performed by multiple people.

Why this answer

Option A is correct because PRINCE2 mandates the Project Assurance role to ensure that the project remains aligned with its business case, quality standards, and governance requirements. This role is separate from the Project Manager and cannot be combined with it, as it provides an independent check on the project's ongoing viability and compliance.

Exam trap

The trap here is that candidates often confuse Project Assurance with the Project Manager's responsibilities, assuming that the Project Manager can self-assure, or they mistakenly think assurance is only needed at stage boundaries, when in fact PRINCE2 requires continuous independent oversight throughout the project.

202
MCQmedium

Which report is produced by the Team Manager and used by the Project Manager to update the Project Board?

A.Checkpoint Report
B.Exception Report
C.End Stage Report
D.Highlight Report
AnswerA

Correct.

Why this answer

The Checkpoint Report is produced by the Team Manager and sent to the Project Manager. The Project Manager then uses it to compile the Highlight Report for the Project Board.

203
MCQhard

In a PRINCE2 project, the Project Manager has also been assigned the Project Assurance role. Which PRINCE2 principle is being violated?

A.Continued business justification
B.Defined roles and responsibilities
C.Focus on products
D.Manage by stages
AnswerB

PRINCE2 requires separation of Project Manager and Project Assurance to ensure independence.

Why this answer

PRINCE2 requires that Project Assurance be independent of the Project Manager to provide objective oversight. Combining the roles violates the 'defined roles and responsibilities' principle and the management of risk.

204
Matchingmedium

Match each PRINCE2 role to its responsibility.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Manages the project on a day-to-day basis.

Specifies the user requirements and ensures the project delivers benefits.

Provides the resources and expertise to produce the project's products.

Owns the business case and chairs the project board.

Monitors all aspects of the project's performance independently.

Why these pairings

These are key roles in the PRINCE2 project management team.

205
MCQmedium

A Senior Supplier is concerned that a proposed change will impact the project's technical feasibility. What should the Senior Supplier do?

A.Issue a Change Request directly to the Project Manager
B.Escalate the concern to the Project Board for a decision
C.Approve the change as it aligns with the Business Case
D.Update the Project Plan to reflect the change
AnswerB

The Senior Supplier should bring the concern to the Project Board as part of their role in representing supplier interests.

Why this answer

The Senior Supplier is a member of the Project Board and should raise their concern at the Project Board meeting or via an Exception Report if the change requires Board decision. The Senior Supplier ensures that supplier interests are represented.

206
MCQmedium

Which role is responsible for delivering Work Packages and reporting progress to the Project Manager?

A.Senior Supplier
B.Project Assurance
C.Project Manager
D.Team Manager
AnswerD

The Team Manager is responsible for delivering Work Packages and reporting to the PM.

Why this answer

The Team Manager manages the delivery of Work Packages and reports to the Project Manager. Option C is correct.

207
MCQhard

In PRINCE2, why is the Project Manager not allowed to also perform Project Assurance?

A.To ensure independence and avoid conflicts of interest
B.Because Project Assurance is not a PRINCE2 role
C.To reduce the number of roles in the project
D.Because the Project Manager is too busy
AnswerA

Correct. Independence is key to effective assurance.

Why this answer

In PRINCE2, Project Assurance is a separate role from the Project Manager to ensure objective oversight of the project's adherence to standards, plans, and business justification. The Project Manager is responsible for day-to-day management and delivery, so allowing them to also perform Project Assurance would create a conflict of interest, as they would be reviewing their own work. This independence is critical for the integrity of the assurance function, which must provide unbiased checks on the Project Manager's decisions and outputs.

Exam trap

The trap here is that candidates may think Project Assurance is optional or not a formal role (Option B), or they may assume the reason is practical (Option D), but PRINCE2 explicitly enforces role separation to prevent conflicts of interest.

How to eliminate wrong answers

Option B is wrong because Project Assurance is explicitly defined as a PRINCE2 role, responsible for monitoring compliance and providing independent oversight. Option C is wrong because PRINCE2 does not reduce roles to simplify; it mandates distinct roles (e.g., Project Manager, Project Assurance, Senior User) to ensure separation of duties and accountability. Option D is wrong because the reason is not about the Project Manager's workload or time constraints; it is a governance principle to maintain objectivity and avoid self-review.

208
MCQeasy

Which role is responsible for project assurance activities in a PRINCE2 project?

A.Project Manager
B.Senior Supplier
C.Project Assurance
D.Team Manager
AnswerC

Project Assurance is the role responsible for independent assurance.

Why this answer

Project Assurance is the correct answer because in PRINCE2, Project Assurance is a distinct role responsible for monitoring and reporting on the project's adherence to the management and technical standards, independent of the Project Manager. It ensures that the project remains aligned with the business case, quality requirements, and stakeholder expectations, acting as the 'eyes and ears' of the Project Board.

Exam trap

The trap here is that candidates often confuse the Project Manager's responsibility for managing the project with the independent oversight role of Project Assurance, leading them to incorrectly select the Project Manager as the answer.

How to eliminate wrong answers

Option A is wrong because the Project Manager is responsible for day-to-day management and execution, not for independent assurance; they are the subject of assurance checks. Option B is wrong because the Senior Supplier is a member of the Project Board who provides supplier-side input and decision-making, but does not perform the ongoing, independent monitoring of project assurance activities. Option D is wrong because the Team Manager is responsible for delivering the work within a work package, not for project-level assurance, which is a higher-level oversight function.

209
MCQhard

In a PRINCE2 project, the project board is concerned that the project manager is not effectively communicating with key stakeholders. The project manager recently presented a detailed risk report to the board, but several board members were unaware of the critical risks identified. Which communication management activity should the project manager have performed to ensure the board was properly informed?

A.Included the critical risks in the project plan
B.Prepared a highlight report instead of a detailed risk report
C.Updated the risk register and sent it to the board
D.Agreed on the communication management strategy with the board
AnswerD

The strategy defines how and when to communicate risks to each stakeholder.

Why this answer

The correct answer is D because the PRINCE2 communication management strategy defines how, when, and to whom information should be communicated. The project manager should have agreed on this strategy with the board upfront, ensuring that critical risks are reported in a format and frequency that meets the board's needs. Without this agreement, the board was not properly informed despite the detailed risk report being presented.

Exam trap

The trap here is that candidates often confuse operational reporting tasks (like updating the risk register or preparing a highlight report) with the strategic management activity of agreeing on the communication management strategy, which is the foundational step to ensure stakeholders receive the right information in the right way.

How to eliminate wrong answers

Option A is wrong because including critical risks in the project plan is not a communication management activity; the project plan focuses on schedule, cost, and scope, not on defining stakeholder communication needs. Option B is wrong because a highlight report is a summary for the board, but the core issue is the lack of agreement on communication methods, not the type of report used. Option C is wrong because updating the risk register and sending it to the board is an operational task, not a strategic communication management activity; it does not address the need for the board to agree on how and when risks should be communicated.

210
Multi-Selecthard

Which THREE of the following are responsibilities of the Senior Supplier role on the Project Board?

Select 3 answers
A.Manage the team on a day-to-day basis
B.Ensure that the supplier's products meet quality requirements
C.Provide resources and expertise to deliver the project's products
D.Contribute to the Business Case from a supplier perspective
E.Approve the Stage Plans
AnswersB, C, D

Quality of supplier deliverables is a key responsibility.

Why this answer

The Senior Supplier role on the Project Board is responsible for ensuring that the supplier's products meet the agreed quality requirements. This includes providing the necessary resources and expertise to deliver the project's products, and contributing to the Business Case from a supplier perspective, particularly regarding the feasibility and cost of the supplier's work.

Exam trap

The trap here is that candidates often confuse the day-to-day management responsibilities of the Project Manager with the strategic oversight responsibilities of the Senior Supplier on the Project Board, leading them to incorrectly select Option A.

211
MCQhard

Which role can delegate change control decisions to a Change Authority?

A.Project Manager
B.Project Board
C.Executive
D.Senior User
AnswerB

Correct: The Project Board can set up a Change Authority to approve changes within defined tolerances.

Why this answer

In PRINCE2, the Project Board is responsible for overall project governance and can delegate its change control authority to a Change Authority. This delegation is formalized in the Project Initiation Documentation (PID) and allows the Change Authority to approve or reject change requests within predefined limits, such as cost or time thresholds, without needing to escalate every decision back to the Board.

Exam trap

The trap here is that candidates often confuse the Project Board with its individual members (Executive or Senior User) and mistakenly think one person can delegate change authority, but PRINCE2 requires collective Board approval for such delegation.

How to eliminate wrong answers

Option A is wrong because the Project Manager manages day-to-day activities and can recommend changes but does not have the authority to delegate change control decisions; that authority rests with the Project Board. Option C is wrong because the Executive is a single role on the Project Board, not the collective decision-making body; delegation of change control is a Board-level decision, not an individual one. Option D is wrong because the Senior User represents user interests on the Project Board but, like the Executive, cannot unilaterally delegate change authority; only the full Project Board can do so.

212
MCQeasy

Which role manages the day-to-day execution of a Work Package?

A.Project Support
B.Team Manager
C.Senior User
D.Project Manager
AnswerB

The Team Manager manages the day-to-day execution of a Work Package.

Why this answer

The Team Manager is the role responsible for the day-to-day management of a Work Package within a PRINCE2 project. They report to the Project Manager and ensure that the work is completed according to the agreed tolerances, quality criteria, and schedule. This is defined in the PRINCE2 manual under the 'Organizing' theme, where the Team Manager is specifically tasked with coordinating the team's work and reporting progress.

Exam trap

The trap here is that candidates often confuse the Project Manager's overall responsibility with the Team Manager's specific duty to manage the day-to-day execution of a Work Package, leading them to incorrectly select the Project Manager.

How to eliminate wrong answers

Option A is wrong because Project Support provides administrative and advisory services to the project, such as maintaining files and providing tools, but does not manage the execution of a Work Package. Option C is wrong because the Senior User represents the interests of those who will use the project's products and specifies requirements, but does not manage day-to-day Work Package execution. Option D is wrong because the Project Manager delegates the management of Work Packages to the Team Manager and focuses on overall project planning and control, not the daily execution of individual Work Packages.

213
MCQmedium

A Team Manager receives a Work Package from the Project Manager. To whom should the Team Manager report progress?

A.Project Board
B.Senior User
C.Project Assurance
D.Project Manager
AnswerD

The Team Manager reports to the Project Manager.

Why this answer

In PRINCE2, the Team Manager is responsible for delivering the Work Package and reports progress directly to the Project Manager, who is the single point of accountability for the project. The Project Manager uses this information to update the Project Plan and report to the Project Board. This ensures a clear line of control and avoids bypassing the management layer.

Exam trap

The trap here is that candidates confuse the reporting line with oversight roles, assuming that Project Assurance or the Board needs direct progress updates, when PRINCE2 explicitly mandates that the Team Manager reports only to the Project Manager to preserve the single point of control.

How to eliminate wrong answers

Option A is wrong because the Project Board is the ultimate decision-making body and does not receive direct progress reports from the Team Manager; the Project Manager reports to the Board. Option B is wrong because the Senior User represents user interests and is not involved in day-to-day progress reporting from the Team Manager. Option C is wrong because Project Assurance is an independent oversight function that reviews compliance and quality, not a recipient of routine progress reports from the Team Manager.

214
Multi-Selecthard

Which TWO of the following statements about the Change Authority role are correct?

Select 2 answers
A.The Change Authority is mandatory in all projects
B.The Change Authority is an optional role
C.The Change Authority can be delegated by the Project Board
D.The Change Authority is always the Project Manager
E.The Change Authority must include the Senior User
AnswersB, C

Correct.

Why this answer

Option B is correct because the Change Authority role is optional in PRINCE2. It is only established if the Project Board decides to delegate authority for making change decisions within defined limits, rather than handling all change requests themselves.

Exam trap

The trap here is that candidates often assume the Change Authority is mandatory or always the Project Manager, confusing it with the Change Control approach or the Project Manager's responsibilities, when PRINCE2 explicitly makes it an optional delegation by the Project Board.

215
MCQhard

In PRINCE2, what is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.An RFC is raised by the Project Board; an Off-spec is raised by the Project Manager
B.There is no difference; they are interchangeable terms
C.An RFC is a request to modify a product, while an Off-spec is a product that does not meet its specification
D.An RFC is always approved by the Change Authority; an Off-spec is always rejected
AnswerC

This is the core distinction: proactive vs. non-conformance.

Why this answer

Option C is correct because in PRINCE2, a Request for Change (RFC) is a formal proposal to modify a product, its specification, or the project's baseline, while an Off-Specification (Off-spec) is a product that has been completed but does not meet its agreed specification. The key distinction is that an RFC seeks to change what is required, whereas an Off-spec identifies a deviation from what was required.

Exam trap

The trap here is that candidates confuse the raising authority or approval outcome with the core definition, leading them to choose options that describe procedural roles rather than the fundamental difference in what each term represents.

How to eliminate wrong answers

Option A is wrong because both RFCs and Off-specs can be raised by any project stakeholder, not exclusively by the Project Board or Project Manager; the Project Board may approve them, but raising is not restricted. Option B is wrong because RFC and Off-spec are distinct concepts with different definitions and purposes in PRINCE2; they are not interchangeable. Option D is wrong because an Off-spec is not always rejected; it may be accepted as a concession if the deviation is deemed acceptable, and an RFC is not always approved by the Change Authority—it can be rejected or deferred.

216
MCQeasy

Who is responsible for managing the delivery of a Work Package?

A.Project Manager
B.Senior User
C.Team Manager
D.Project Support
AnswerC

The Team Manager manages Work Package delivery.

Why this answer

The Team Manager is responsible for the delivery of one or more Work Packages and reports progress to the Project Manager.

217
MCQmedium

Which of the following is NOT a role in the PRINCE2 project management team?

A.Project Sponsor
B.Change Authority
C.Team Manager
D.Project Manager
AnswerA

PRINCE2 uses the term SRO, not Sponsor.

Why this answer

The PRINCE2 project management team structure includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and optionally the Change Authority. The Project Sponsor is not a defined role in PRINCE2; instead, the Executive role fulfills the sponsorship responsibilities. Therefore, option A is correct as the role that does NOT exist in the PRINCE2 framework.

Exam trap

The trap here is that candidates often confuse the generic term 'Project Sponsor' with the PRINCE2-specific 'Executive' role, leading them to incorrectly select a wrong option like Change Authority or Team Manager.

How to eliminate wrong answers

Option A is correct because 'Project Sponsor' is not a PRINCE2 role; the Executive is the equivalent. Option B is wrong because Change Authority is a valid PRINCE2 role, responsible for authorizing change requests within delegated limits. Option C is wrong because Team Manager is a valid PRINCE2 role, responsible for delivering the work packages assigned by the Project Manager.

Option D is wrong because Project Manager is a core PRINCE2 role, managing the day-to-day project activities and reporting to the Project Board.

218
MCQhard

What is the difference between Project Assurance and a quality review?

A.Both are the same
B.Project Assurance is a role; a quality review is a technique
C.Project Assurance is performed by the Project Manager
D.Quality review is a role; Project Assurance is a technique
AnswerB

Project Assurance is a role; quality review is a technique for reviewing products.

Why this answer

Project Assurance is ongoing and independent; a quality review is a specific technique to review products.

219
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project immediately
B.Raise an Exception Report to the Project Board
C.Increase the budget and continue with the current plan
D.Report the overrun in the next Highlight Report
AnswerB

Correct action per management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. This is management by exception.

220
MCQmedium

Which role is responsible for providing independent assurance to the Project Board that the project is on track?

A.Senior User
B.Project Support
C.Project Assurance
D.Project Manager
AnswerC

Project Assurance is an independent role that reports to the Project Board.

Why this answer

Project Assurance is independent of the Project Manager and provides assurance to the Project Board that the project is being managed correctly and remains viable.

221
MCQeasy

Which role is accountable for the project's Business Case throughout the project?

A.Project Manager
B.Senior User
C.Project Assurance
D.Executive (SRO)
AnswerD

The Executive is accountable for the Business Case.

Why this answer

The Executive (Senior Responsible Owner) is accountable for the Business Case and its maintenance throughout the project.

222
Multi-Selectmedium

Which TWO of the following statements about the Change Authority role are correct?

Select 2 answers
A.The Change Authority is appointed by the Project Manager
B.The Change Authority helps to reduce the burden on the Project Board
C.The Change Authority is always a single person
D.The Change Authority is a mandatory role in PRINCE2
E.The Change Authority can authorize changes within agreed limits
AnswersB, E

By handling changes within limits, the Board is less burdened.

Why this answer

The Change Authority is an optional role that can be set up to make decisions on change requests within agreed limits, thereby relieving the Project Board from reviewing every change.

223
MCQmedium

Which document is the key output of the Initiating a Project process?

A.Business Case
B.Project Initiation Documentation (PID)
C.Project Plan
D.Stage Plan
AnswerB

Correct. The PID is the formal documentation of the project.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process because it consolidates all essential information needed to justify and manage the project, including the Business Case, Project Plan, and controls. It serves as the foundation for decision-making by the Project Board and is formally approved at the end of the initiation stage.

Exam trap

The trap here is that candidates often confuse the Business Case as the key output because it is the most prominent justification document, but PRINCE2 explicitly defines the PID as the consolidated output that includes the Business Case and all other baseline management products.

How to eliminate wrong answers

Option A is wrong because the Business Case is a component of the PID, not the key output itself; it is developed and refined during the Initiating a Project process but is not the single document that captures the entire project baseline. Option C is wrong because the Project Plan is one of the management products within the PID, but the PID is the overarching document that includes the Project Plan along with other critical elements like risk management and quality controls. Option D is wrong because a Stage Plan is produced during the Managing a Stage Boundary process, not during Initiating a Project; it details work for a specific stage, whereas the PID covers the whole project.

224
MCQhard

Which of the following best describes the relationship between the Senior Responsible Owner (SRO) and the Project Sponsor in PRINCE2?

A.The Project Sponsor is the Project Manager
B.The SRO is the same as the Project Sponsor; PRINCE2 uses the term Executive
C.The Project Sponsor is a separate role that reports to the SRO
D.The Project Sponsor is the Senior User
AnswerB

Correct. The Executive is the SRO and acts as the project sponsor.

Why this answer

In PRINCE2, the Senior Responsible Owner (SRO) is the same role as the Project Sponsor, but PRINCE2 uses the term 'Executive' for this role. The Executive is the single point of accountability for the project's success, representing the business interests and owning the business case. Option B correctly identifies this equivalence, which is a fundamental concept in PRINCE2's organizational structure.

Exam trap

The trap here is that candidates often confuse the PRINCE2 Executive with the Project Sponsor from other frameworks (like PMP or Agile), assuming they are different roles or that the Project Sponsor reports to the SRO, when in fact PRINCE2 explicitly uses 'Executive' as the single accountable role equivalent to the SRO.

How to eliminate wrong answers

Option A is wrong because the Project Sponsor (Executive) is not the Project Manager; the Project Manager is a separate role responsible for day-to-day management, while the Executive provides strategic direction and accountability. Option C is wrong because the Project Sponsor (Executive) is not a separate role reporting to the SRO; in PRINCE2, the Executive is the SRO, and there is no hierarchical reporting between them. Option D is wrong because the Project Sponsor (Executive) is not the Senior User; the Senior User represents the users' needs and is a distinct role on the project board, not synonymous with the Executive.

225
MCQeasy

Who chairs the Project Board?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Executive
AnswerD

Correct.

Why this answer

The Executive chairs the Project Board in PRINCE2. This is because the Executive is the ultimate decision-maker, accountable for the project's business justification and overall success. The Project Board is chaired by the Executive, not the Project Manager, Senior Supplier, or Senior User, as the Executive represents the business interests and has the authority to approve key decisions.

Exam trap

The trap here is that candidates often assume the Project Manager chairs the Project Board due to their visible leadership role, but PRINCE2 explicitly assigns the chair to the Executive to maintain separation of management and governance.

How to eliminate wrong answers

Option A is wrong because the Project Manager manages the project on a day-to-day basis and reports to the Project Board, but does not chair it; the Project Manager is a member of the project management team, not the board. Option B is wrong because the Senior Supplier represents the supplier's interests and provides resources, but does not chair the board; the chair role is held by the Executive, who balances business, user, and supplier views. Option C is wrong because the Senior User represents the users' needs and benefits, but does not chair the board; the Executive chairs to ensure business justification drives decisions.

← PreviousPage 3 of 5 · 335 questions totalNext →

Ready to test yourself?

Try a timed practice session using only People: organizations, teams, and leadership questions.