CCNA People: organizations, teams, and leadership Questions

75 of 335 questions · Page 2/5 · People: organizations, teams, and leadership · Answers revealed

76
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Supplier
B.Senior Responsible Owner (SRO/Executive)
C.Project Support
D.Project Manager
AnswerB

The SRO owns the Business Case and is accountable for it throughout the project.

Why this answer

The Senior Responsible Owner (SRO/Executive) is the single person ultimately accountable for the project's business justification. They own the Business Case and are responsible for ensuring it remains viable, aligned with corporate strategy, and is formally reviewed at key decision points (e.g., stage boundaries). The PRINCE2 principle of continued business justification places this accountability squarely on the Executive, not on the Project Manager or support roles.

Exam trap

PeopleCert often tests the distinction between accountability (Executive) and responsibility (Project Manager) for the Business Case, trapping candidates who confuse day-to-day maintenance with ultimate ownership.

How to eliminate wrong answers

Option A is wrong because the Senior Supplier represents the interests of those providing the project's specialist products and resources; they do not own the Business Case, though they contribute to its feasibility. Option C is wrong because Project Support provides administrative and advisory services (e.g., maintaining registers, configuration management) but has no authority to own or approve the Business Case. Option D is wrong because the Project Manager is responsible for developing, reviewing, and maintaining the Business Case on a day-to-day basis, but the ultimate accountability and ownership rests with the Executive (SRO).

77
MCQmedium

The Project Board is considering a Request for Change. Which role is authorized to approve changes within delegated limits?

A.Project Manager
B.Senior Supplier
C.Senior User
D.Change Authority
AnswerD

The Change Authority has delegated authority to approve changes.

Why this answer

The Change Authority role is specifically authorized to approve Requests for Change within delegated limits set by the Project Board. This delegation allows the Change Authority to make decisions on low-impact changes without requiring full Board approval, streamlining the change control process.

Exam trap

The trap here is that candidates often assume the Project Manager has approval authority for changes, but PRINCE2 explicitly separates the management of change control from the authority to approve changes, which is delegated to the Change Authority.

How to eliminate wrong answers

Option A is wrong because the Project Manager manages the change control process but does not have the authority to approve changes unless explicitly delegated as the Change Authority. Option B is wrong because the Senior Supplier represents the supplier's interests on the Project Board and is not automatically authorized to approve changes within delegated limits. Option C is wrong because the Senior User represents the users' interests on the Project Board and is not automatically authorized to approve changes within delegated limits.

78
MCQeasy

Which role is optional in the PRINCE2 project management team?

A.Project Manager
B.Project Board
C.Team Manager
D.Project Support
AnswerD

Project Support is optional and can be provided by the Project Manager if needed.

Why this answer

In PRINCE2, the Project Manager, Project Board, and Team Manager are all mandatory roles within the project management team. Project Support is the only optional role, as its responsibilities can be absorbed by the Project Manager or other team members, or provided by a separate office like a PMO. The PRINCE2 manual explicitly states that Project Support is not a required role, making D the correct answer.

Exam trap

The trap here is that candidates often assume all roles listed in the PRINCE2 management team are mandatory, but PRINCE2 explicitly designates Project Support as optional, testing whether you know the distinction between 'required' and 'optional' roles.

How to eliminate wrong answers

Option A is wrong because the Project Manager is a mandatory role responsible for day-to-day management and is required in every PRINCE2 project. Option B is wrong because the Project Board is a mandatory role providing overall direction and decision-making authority; without it, the project cannot be governed. Option C is wrong because the Team Manager is a mandatory role when the project is large or complex enough to require delegation of technical delivery; PRINCE2 mandates this role if the Project Manager cannot directly manage the team.

79
Multi-Selectmedium

Which TWO statements about the Project Board are true?

Select 2 answers
A.It provides direction and decisions to the Project Manager.
B.It is accountable for the success of the project.
C.It is responsible for day-to-day management of the project.
D.It meets on a regular basis (e.g., weekly).
E.It includes the Project Manager as a member.
AnswersA, B

The Project Board directs the PM and makes key decisions.

Why this answer

The Project Board is accountable for the project's success, meets exception-driven, and comprises SRO, Senior User, and Senior Supplier. It does not meet regularly; it meets when exceptions occur or at stage boundaries.

80
MCQeasy

Which role is accountable for the project's Business Case throughout the project?

A.Senior User
B.Project Manager
C.Project Assurance
D.Senior Responsible Owner (Executive)
AnswerD

The SRO is the single point of accountability for the project, including the Business Case.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and its maintenance throughout the project.

81
MCQeasy

Which role is responsible for ensuring the project provides value for money and is aligned with business strategy?

A.Senior Responsible Owner (Executive)
B.Senior Supplier
C.Project Manager
D.Senior User
AnswerA

The SRO owns the Business Case and ensures value for money.

Why this answer

The Senior Responsible Owner (Executive) is the single point of accountability for ensuring the project delivers value for money and remains aligned with the organization's business strategy. This role owns the business case, approves key stage boundaries, and has ultimate authority over project funding and continuation, directly linking project outputs to strategic objectives.

Exam trap

PeopleCert often tests the misconception that the Project Manager owns the business case or that the Senior User ensures strategic alignment, but PRINCE2 explicitly assigns business case ownership and strategic accountability to the Executive alone.

How to eliminate wrong answers

Option B (Senior Supplier) is wrong because the Senior Supplier represents the interests of those providing the project's products or services, focusing on technical feasibility and resource availability, not on business strategy or value-for-money justification. Option C (Project Manager) is wrong because the Project Manager is responsible for day-to-day management, planning, and delivery within constraints, but does not own the business case or have authority to align the project with corporate strategy. Option D (Senior User) is wrong because the Senior User represents the end-users' needs and ensures the final product meets operational requirements, but does not have accountability for strategic alignment or financial value assessment.

82
MCQeasy

Which document is the key output of the Initiating a Project process?

A.Stage Plan
B.Benefits Management Approach
C.Project Initiation Documentation
D.Project Brief
AnswerC

Correct: The PID is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the definitive output of the Initiating a Project process, as it consolidates all key planning information—such as the Business Case, project scope, and risk assessment—into a single baseline that authorizes the project to proceed. PRINCE2 mandates that the PID is created during this process to provide a firm foundation for the project and is used throughout the remaining stages.

Exam trap

PeopleCert often tests the distinction between the Project Brief (an input) and the Project Initiation Documentation (the key output), so candidates mistakenly choose the Project Brief because it is created earlier and seems foundational, but the PID is the formal authorization document produced during Initiating a Project.

How to eliminate wrong answers

Option A is wrong because a Stage Plan is produced during the Managing a Stage Boundary process, not during Initiating a Project, and it details the work for a specific management stage rather than the overall project. Option B is wrong because the Benefits Management Approach is developed as part of the Initiating a Project process but is a separate management product, not the key output; the PID is the comprehensive document that includes or references it. Option D is wrong because the Project Brief is created during the Starting Up a Project process as an input to Initiating a Project, not as an output of that process.

83
MCQmedium

Which role is responsible for providing an independent check that the project is being conducted correctly and remains aligned with the business case?

A.Project Support
B.Project Manager
C.Project Assurance
D.Team Manager
AnswerC

Project Assurance independently assures the Project Board.

Why this answer

Project Assurance provides independent oversight to the Project Board, ensuring the project stays on track.

84
MCQhard

Which PRINCE2 principle is being applied when the Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Learn from experience
B.Focus on products
C.Manage by exception
D.Manage by stages
AnswerC

Management by exception sets tolerances and requires escalation when they are forecast to be exceeded.

Why this answer

The 'manage by exception' principle is applied when the Project Manager escalates a forecast tolerance deviation to the Project Board. This principle delegates decision-making authority for day-to-day management within defined tolerances, and only escalates when those tolerances are forecast to be exceeded, ensuring the Project Board focuses on strategic oversight.

Exam trap

PeopleCert often tests the distinction between 'manage by exception' and 'manage by stages', where candidates mistakenly think escalation relates to stage boundaries rather than tolerance deviations.

How to eliminate wrong answers

Option A is wrong because 'learn from experience' focuses on capturing and applying lessons throughout the project, not on escalation of tolerance deviations. Option B is wrong because 'focus on products' emphasizes defining and delivering products with agreed quality criteria, not on escalation of tolerances. Option D is wrong because 'manage by stages' involves planning and controlling the project in stages, but the escalation of a tolerance deviation is a direct application of 'manage by exception', not stage management.

85
Multi-Selecteasy

Which TWO of the following are roles in the PRINCE2 project management team?

Select 2 answers
A.Risk Owner
B.Project Sponsor
C.Project Manager
D.Senior User
E.Steering Committee
AnswersC, D

Project Manager is a key role.

Why this answer

The PRINCE2 project management team includes the Project Manager (C) as the person responsible for day-to-day management and the Senior User (D) who represents the interests of those who will use the project's outputs. Both are defined roles in the PRINCE2 management structure, with the Project Manager reporting to the Project Board and the Senior User being a member of that board.

Exam trap

The trap here is that candidates confuse generic project governance terms like 'Steering Committee' or 'Project Sponsor' with PRINCE2's specific role names, or they incorrectly assume 'Risk Owner' is a core management team role rather than a risk practice assignment.

86
MCQeasy

Who chairs the Project Board meetings?

A.Senior User
B.Senior Supplier
C.Project Manager
D.Senior Responsible Owner (SRO/Executive)
AnswerD

The SRO chairs the Project Board.

Why this answer

In PRINCE2, the Project Board is chaired by the Executive, also known as the Senior Responsible Owner (SRO). The Executive is ultimately accountable for the project's success and ensures the business case remains viable. The Project Manager manages day-to-day activities but does not chair board meetings.

Exam trap

PeopleCert often tests the misconception that the Project Manager chairs the Project Board, because candidates confuse operational management with governance authority.

How to eliminate wrong answers

Option A is wrong because the Senior User represents the users' interests and is a member of the Project Board, but does not chair it. Option B is wrong because the Senior Supplier represents the supplier's interests and is also a board member, not the chair. Option C is wrong because the Project Manager is responsible for managing the project on a day-to-day basis and attends board meetings to report progress, but does not chair them.

87
MCQmedium

In PRINCE2, who is responsible for managing the delivery of a Work Package?

A.Senior User
B.Project Support
C.Project Manager
D.Team Manager
AnswerD

The Team Manager is responsible for producing the products within the Work Package as agreed.

Why this answer

The Team Manager is responsible for the delivery of Work Packages and reports progress to the Project Manager.

88
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Senior Supplier
B.Project Manager
C.Senior User
D.Executive (Senior Responsible Owner)
AnswerD

The Executive is accountable for the Business Case and its viability throughout the project.

Why this answer

The Executive (Senior Responsible Owner) is accountable for the Business Case and ensuring it remains viable. The Project Manager maintains it on a day-to-day basis, but the Executive holds ultimate responsibility.

89
MCQmedium

A project is in the Managing a Stage Boundary process. Which key document is produced during this process?

A.Benefits Review Plan
B.Work Package
C.Project Initiation Documentation
D.End Stage Report
AnswerD

Correct. It is the key output of Managing a Stage Boundary.

Why this answer

The End Stage Report is produced to summarize performance and request approval for the next stage.

90
MCQhard

The Project Board has delegated change control decisions to a Change Authority. What is the key benefit of this delegation?

A.It allows the Project Manager to approve all changes
B.It reduces the burden on the Project Board by handling smaller changes
C.It eliminates the need for the Configuration Management process
D.It ensures all changes are approved by the Senior Supplier
AnswerB

The Board delegates routine changes to the Change Authority.

Why this answer

Delegating change control to a Change Authority speeds up decision-making for low-impact changes without needing full Project Board involvement, while maintaining control.

91
Multi-Selectmedium

Which TWO of the following are members of the Project Board?

Select 2 answers
A.Senior User
B.Project Assurance
C.Project Manager
D.Team Manager
E.Senior Responsible Owner (SRO/Executive)
AnswersA, E

The Senior User is a Board member.

Why this answer

The Senior User (A) is a correct member of the Project Board because they represent the interests of those who will use the project's product, ensuring the product meets user requirements and provides value. The Senior Responsible Owner (E), also called the Executive, is the correct member who chairs the Project Board and is ultimately accountable for the project's success. Both roles are defined in PRINCE2 as essential for project governance and decision-making.

Exam trap

The trap here is that candidates often confuse Project Assurance as a Board member because it sounds like a governance role, but PRINCE2 explicitly defines it as a separate function that supports the Board without being a voting member.

92
MCQeasy

Which role is responsible for preparing the Highlight Report?

A.Project Support
B.Team Manager
C.Project Manager
D.Senior User
AnswerC

The Project Manager prepares the Highlight Report to inform the Project Board.

Why this answer

The Highlight Report is prepared by the Project Manager and sent to the Project Board at intervals defined in the Communication Management Approach.

93
MCQmedium

The Project Board has approved an Exception Plan to recover from a budget overrun. The Project Manager updates the Project Plan. What else must the Project Manager update?

A.The Risk Register
B.The Business Case
C.The Project Brief
D.The Benefits Management Approach
AnswerB

The Business Case must be updated to reflect the changes from the Exception Plan.

Why this answer

When an Exception Plan is approved to recover from a budget overrun, the Project Plan must be updated to reflect the new cost and schedule baselines. However, the Business Case must also be updated because the exception plan changes the project's forecast costs and benefits, which directly affects the justification for the project. PRINCE2 requires that the Business Case remains viable and approved whenever a significant deviation occurs, ensuring continued alignment with organizational objectives.

Exam trap

The trap here is that candidates often think only the Project Plan needs updating when a new baseline is approved, but PRINCE2 explicitly requires the Business Case to be updated because the exception plan changes the cost-benefit justification, which is the core of the project's approval.

How to eliminate wrong answers

Option A is wrong because the Risk Register is updated when risks are identified or change, but an approved Exception Plan is a response to a deviation, not a risk itself; the Project Manager would update the Risk Register only if new risks arise from the exception plan. Option C is wrong because the Project Brief is created during the Starting Up a Project process and is not updated during the delivery stage; it contains the initial project mandate and outline Business Case, not the current baseline. Option D is wrong because the Benefits Management Approach defines how and when benefits will be measured and realized, but it is not directly updated when an Exception Plan is approved; the Business Case, which contains the cost-benefit analysis, must be updated to reflect the revised costs and benefits.

94
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior User
C.Team Manager
D.Executive (SRO)
AnswerD

The Executive is responsible for the Business Case throughout the project.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and is responsible for ensuring it remains viable.

95
MCQhard

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-Spec)?

A.An RFC affects the project scope; an Off-Spec affects the project schedule
B.An RFC is handled via the issue register; an Off-Spec is handled via the quality register
C.An RFC proposes a change to an agreed baseline; an Off-Spec identifies that a product does not meet its specification
D.An RFC is raised by the Project Board; an Off-Spec is raised by the Project Manager
AnswerC

This is the correct distinction.

Why this answer

An RFC proposes a modification to an agreed baseline; an Off-Spec is a deviation from what was specified—something that should be there is missing or incorrect. Both are issues that may require a change control decision.

96
MCQeasy

Which role is responsible for the day-to-day management of a Work Package?

A.Project Manager
B.Senior Supplier
C.Team Manager
D.Project Support
AnswerC

The Team Manager manages the delivery of Work Packages.

Why this answer

In PRINCE2, the Team Manager is responsible for the day-to-day management of a Work Package. This includes coordinating the team's work, monitoring progress against the Work Package plan, and reporting back to the Project Manager. The Team Manager acts as the direct interface between the project management team and the team members executing the work.

Exam trap

The trap here is that candidates often confuse the Project Manager's overall authority with the delegated day-to-day control of a Work Package, mistakenly thinking the Project Manager handles all operational details rather than focusing on management by exception.

How to eliminate wrong answers

Option A is wrong because the Project Manager is responsible for overall project management, not the day-to-day management of a specific Work Package; they delegate that authority to the Team Manager. Option B is wrong because the Senior Supplier represents the supplier interests on the Project Board and is not involved in the operational management of Work Packages. Option D is wrong because Project Support provides administrative and advisory services (e.g., planning tools, configuration management) but does not manage Work Packages.

97
MCQeasy

Which role is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Senior User
C.Executive (Senior Responsible Owner)
D.Project Assurance
AnswerC

The Executive is accountable for the Business Case and its maintenance throughout the project.

Why this answer

The Executive (Senior Responsible Owner) is accountable for the Business Case and its maintenance throughout the project. The Project Manager develops and maintains the Business Case on behalf of the Executive, but accountability rests with the Executive.

98
MCQeasy

Who is responsible for the day-to-day management of a project within the tolerances set by the Project Board?

A.Senior Responsible Owner
B.Team Manager
C.Project Board
D.Project Manager
AnswerD

The Project Manager manages the project within tolerances set by the Project Board.

Why this answer

The Project Manager is delegated the authority to manage the project on a day-to-day basis within agreed tolerances.

99
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is always approved; an Off-specification is always rejected
B.A Request for Change is raised by the Project Manager; an Off-specification is raised by the team
C.A Request for Change seeks to change a baseline; an Off-specification identifies a deviation from what was specified
D.They are the same thing
AnswerC

Correct distinction.

Why this answer

Option C is correct because a Request for Change (RFC) is a formal proposal to modify a baseline (e.g., a product description, project plan, or scope), while an Off-specification (Off-spec) identifies a situation where a product or component has deviated from its approved specification or baseline. In PRINCE2, an RFC seeks to change what was agreed, whereas an Off-spec reports that something is not as specified. This distinction is critical for managing baselines and controlling issues within the organization's change control procedures.

Exam trap

PeopleCert often tests the confusion between 'change' and 'deviation' by presenting options that blur the roles of who raises each issue or the outcome, leading candidates to mistakenly think they are interchangeable or have fixed approval outcomes.

How to eliminate wrong answers

Option A is wrong because neither a Request for Change nor an Off-specification is automatically approved or rejected; both are subject to the project's change control process and may be approved, rejected, or deferred based on impact assessment. Option B is wrong because both an RFC and an Off-specification can be raised by any stakeholder (e.g., project manager, team member, customer), not exclusively by the project manager or team. Option D is wrong because they are fundamentally different: an RFC proposes a change to a baseline, while an Off-spec reports a deviation from an existing specification, and they serve distinct purposes in issue management.

100
MCQhard

What is the primary purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the project's progress and approve the next Stage Plan
B.To close the project and hand over the products
C.To produce the Project Initiation Documentation
D.To ensure that Work Packages are completed on time
AnswerA

The process allows the Board to assess continued viability and approve the next stage.

Why this answer

Managing a Stage Boundary provides the Project Board with information to review the current stage's performance, update the project plan, and approve the next stage plan.

101
MCQhard

What is the difference between a Request for Change (RFC) and an Off-Specification (Off-spec)?

A.An RFC is always approved by the Change Authority, while an Off-spec is always escalated to the Project Board
B.An RFC is for a change in scope, while an Off-spec is for a quality defect
C.An RFC is raised by the Project Manager, while an Off-spec is raised by the Senior User
D.An RFC is a request to change an approved baseline, whereas an Off-spec is a deviation from what was specified
AnswerD

This is the correct distinction per PRINCE2.

Why this answer

An RFC proposes a change to an approved baseline; an Off-spec is something that should be delivered but isn't or is missing.

102
MCQmedium

A project is in the Initiating a Project process. Which document is the key output of this process?

A.Stage Plan
B.Project Initiation Documentation (PID)
C.Project Brief
D.Business Case
AnswerB

The PID is the main output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project, defining the project's scope, plans, and controls.

103
MCQhard

What is the key difference between Project Assurance and Project Support?

A.Project Assurance is independent of the Project Manager; Project Support assists the Project Manager
B.Project Assurance is performed by the Project Manager; Project Support is performed by the Team Manager
C.Project Assurance reviews products; Project Support reviews processes
D.Project Assurance is optional; Project Support is mandatory
AnswerA

Assurance is independent; support is administrative.

Why this answer

Project Assurance is an independent monitoring role reporting to the Project Board, while Project Support provides administrative services to the Project Manager.

104
MCQeasy

Who is responsible for providing Project Support in PRINCE2?

A.Designated project support staff
B.Team Manager
C.Project Board
D.Project Manager
AnswerA

Project Support is provided by designated staff or a separate team.

Why this answer

In PRINCE2, Project Support is a defined role responsible for administrative and advisory services to the project management team. The correct answer is designated project support staff because the PRINCE2 manual explicitly states that Project Support can be provided by a dedicated team or individuals assigned to this function, not by the Project Manager or Team Manager who have distinct responsibilities.

Exam trap

The trap here is that candidates often assume the Project Manager handles all support tasks, but PRINCE2 explicitly separates the Project Support role to maintain objectivity and allow the Project Manager to focus on management, not administration.

How to eliminate wrong answers

Option B is wrong because the Team Manager is responsible for delivering the team's work packages and managing the team, not for providing administrative or advisory support to the project. Option C is wrong because the Project Board is accountable for overall project direction and decision-making, not for day-to-day support activities. Option D is wrong because the Project Manager is responsible for managing the project on a day-to-day basis and cannot also provide independent Project Support without a conflict of interest; PRINCE2 separates these roles to ensure objectivity and efficiency.

105
Multi-Selectmedium

Which TWO of the following are benefits of separating the Project Manager and Project Assurance roles?

Select 2 answers
A.Increases administrative efficiency
B.Reduces the number of roles required
C.Provides independent oversight of the project
D.Ensures faster decision-making
E.Avoids conflict of interest
AnswersC, E

Independence is key.

Why this answer

Option C is correct because separating the Project Manager and Project Assurance roles ensures that project assurance is performed independently of the project manager, providing objective oversight. This independence allows assurance to verify that the project is being managed correctly without bias, which is a core principle of PRINCE2's management of risk and quality.

Exam trap

PeopleCert often tests the misconception that separating roles improves efficiency or speed, when in fact PRINCE2 prioritizes control and objectivity over administrative convenience.

106
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO)
B.Project Manager
C.Project Assurance
D.Senior User
AnswerA

The SRO is accountable for the Business Case and its maintenance throughout the project.

Why this answer

The Senior Responsible Owner (SRO) is the single person accountable for the Business Case and ensuring the project delivers the expected benefits. The Project Manager maintains the project documentation but the SRO owns the Business Case.

107
MCQmedium

The Team Manager receives a Work Package and proceeds with the work. A product is found to be defective. What should the Team Manager do?

A.Correct the defect and continue with the work package
B.Record the defect and raise a Problem/Concern to the Project Manager
C.Inform the Project Board directly
D.Ignore the defect and continue as planned
AnswerB

The Team Manager should record the off-specification and escalate to the Project Manager as a problem.

Why this answer

If a product is defective, the Team Manager should first record the issue as an Off-specification and then raise a Problem/Concern to the Project Manager for resolution.

108
Multi-Selecthard

Which TWO of the following are differences between the Starting Up a Project (SU) and Initiating a Project (IP) processes?

Select 2 answers
A.SU produces the Project Brief; IP produces the Project Initiation Documentation
B.SU is optional; IP is mandatory
C.SU creates the Stage Plan for the first stage; IP creates the Project Plan
D.SU includes the appointment of the Project Board; IP includes the appointment of the Project Manager
E.SU occurs before the project is formally authorized; IP occurs after authorization
AnswersA, E

The Project Brief is output of SU; PID is output of IP.

Why this answer

SU is a pre-project process to ensure the project is viable, while IP formalizes the initiation and produces the PID. IP follows SU.

109
Multi-Selecthard

Which THREE factors should be considered when designing the project management team structure? (Choose three.)

Select 3 answers
A.The budget allocated for project assurance
B.The capabilities of the people available to the project
C.The organizational culture and environment
D.The stage of the project lifecycle
E.The scale and complexity of the project
AnswersB, C, E

Capabilities affect roles.

Why this answer

Option B is correct because the capabilities of the people available directly influence the project management team structure. PRINCE2 emphasizes that the team structure must be designed around the skills, experience, and availability of individuals to ensure roles can be effectively filled and responsibilities discharged. Without assessing capabilities, the structure may assign roles that cannot be performed, leading to project failure.

Exam trap

PeopleCert often tests the misconception that the project lifecycle stage influences the team structure design, but PRINCE2 treats the structure as a static design element defined at initiation, not dynamically adjusted per stage.

110
MCQmedium

A team manager has completed a work package and is ready to hand over the deliverables. To whom should the team manager report the completion?

A.Project Manager
B.Project Board
C.Senior Responsible Owner
D.Project Assurance
AnswerA

The Team Manager reports completion to the Project Manager.

Why this answer

The Team Manager reports to the Project Manager, who manages the work packages within a stage.

111
MCQhard

What is the main reason PRINCE2 separates the role of Project Manager from Project Assurance?

A.To reduce the workload of the Project Manager
B.To ensure that the Project Board receives independent and objective assurance
C.To comply with regulatory requirements
D.To allow the Project Manager to focus only on the Business Case
AnswerB

Independence ensures that assurance is unbiased and credible.

Why this answer

B is correct because PRINCE2's principle of 'defined roles and responsibilities' mandates that Project Assurance be independent from the Project Manager to provide objective oversight of the project's progress, risks, and compliance with the Business Case. This separation ensures that the Project Board receives unbiased information, preventing the Project Manager from having unchecked control over assurance activities. Without this independence, assurance could be compromised by the Project Manager's personal or operational biases.

Exam trap

The trap here is that candidates often confuse the separation of roles with workload reduction or regulatory compliance, but PRINCE2 specifically emphasizes independence and objectivity as the core reason for this structural choice.

How to eliminate wrong answers

Option A is wrong because reducing the Project Manager's workload is a secondary benefit, not the main reason; the primary purpose is to maintain objectivity in assurance. Option C is wrong because PRINCE2 is a generic methodology, not a regulatory framework, and compliance with external regulations is not the driver for this role separation. Option D is wrong because the Project Manager is responsible for day-to-day management of the project, including the Business Case, but not exclusively; the separation ensures assurance is independent, not that the Project Manager focuses solely on the Business Case.

112
MCQhard

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To reduce the workload on the Project Manager
B.To provide independent oversight and avoid conflict of interest
C.To ensure that the Project Board is kept informed of progress
D.To allow the Project Manager to focus on technical delivery
AnswerB

Independence is key to effective assurance.

Why this answer

PRINCE2 separates the Project Manager role from Project Assurance to ensure that assurance activities are independent from the day-to-day management of the project. This avoids a conflict of interest where the Project Manager might be tempted to report overly optimistic progress or hide issues to protect their own performance. The Project Assurance role provides objective oversight, verifying that the project remains aligned with business, user, and supplier interests without being influenced by the Project Manager's personal stake in delivery.

Exam trap

The trap here is that candidates confuse the separation of roles with workload reduction or task delegation, when PRINCE2 specifically mandates it to maintain objectivity and prevent the Project Manager from being the sole judge of their own work.

How to eliminate wrong answers

Option A is wrong because reducing workload is not the primary reason; PRINCE2's separation is about governance and objectivity, not workload distribution. Option C is wrong because keeping the Project Board informed is the responsibility of the Project Manager through reports and highlight reports, not a function of separating assurance from management. Option D is wrong because the Project Manager's focus is on managing the project according to the plan, not on technical delivery; technical delivery is typically delegated to team managers or specialists, and the separation of assurance does not change that focus.

113
MCQeasy

During project execution, a team member raises a concern that the project's objectives are not aligned with the organization's strategic goals. Which role is primarily responsible for ensuring alignment?

A.Senior Supplier
B.Executive
C.Senior User
D.Project Manager
AnswerB

The executive is accountable for business justification and alignment.

Why this answer

The Executive is ultimately accountable for the project's business justification and ensuring it remains aligned with the organization's strategic goals. In PRINCE2, the Executive owns the Business Case and must approve any changes that affect strategic alignment. The team member's concern about misalignment triggers the Executive's responsibility to review and, if necessary, revalidate the project's mandate.

Exam trap

The trap here is that candidates often mistake the Project Manager as the owner of all project aspects, but PRINCE2 explicitly separates management (Project Manager) from accountability (Executive) for strategic alignment.

How to eliminate wrong answers

Option A (Senior Supplier) is wrong because the Senior Supplier represents the interests of those providing the project's products and technology, not the strategic alignment with organizational goals. Option C (Senior User) is wrong because the Senior User represents the users' needs and operational benefits, not the overarching strategic fit. Option D (Project Manager) is wrong because the Project Manager manages day-to-day execution and escalates issues but does not have the authority to decide on strategic alignment; that accountability rests with the Executive.

114
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To initiate the project
B.To close the project
C.To produce a detailed plan for the next stage and request approval to proceed
D.To control the work during a stage
AnswerC

Correct.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage's detailed plan, and authorize continued project work. It produces the Stage Plan for the next stage and a request to proceed, ensuring controlled progression between stages.

Exam trap

The trap here is confusing the Managing a Stage Boundary process with the Controlling a Stage process, as both involve stage-level activities, but Managing a Stage Boundary focuses on stage-end planning and approval, not day-to-day control.

How to eliminate wrong answers

Option A is wrong because initiating the project is the purpose of the Initiating a Project process, not Managing a Stage Boundary. Option B is wrong because closing the project is the purpose of the Closing a Project process, which occurs at the end of the final stage. Option D is wrong because controlling work during a stage is the purpose of the Controlling a Stage process, which handles day-to-day management and issue resolution within a stage.

115
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager?

Select 2 answers
A.Ensure the Business Case remains viable
B.Raise Exception Reports when tolerances are forecast to be exceeded
C.Manage the project within the tolerances set by the Project Board
D.Deliver Work Packages
E.Maintain the project's configuration item records
AnswersB, C

The PM escalates via Exception Reports.

Why this answer

The Project Manager manages day-to-day project work within tolerances and escalates exceptions. Options A and C are correct. B is the responsibility of the SRO.

D is the responsibility of the Team Manager. E is performed by the SRO or Project Support.

116
MCQmedium

In PRINCE2, which role is responsible for the day-to-day management of the project within the tolerances set by the Project Board?

A.Team Manager
B.Senior Supplier
C.Project Support
D.Project Manager
AnswerD

The Project Manager manages the project day-to-day within tolerances set by the Project Board.

Why this answer

The Project Manager is delegated authority by the Project Board to manage the project on a day-to-day basis within agreed tolerances.

117
MCQeasy

Which role is responsible for providing administrative support to the project team?

A.Project Support
B.Project Manager
C.Team Manager
D.Project Assurance
AnswerA

Project Support handles administrative tasks.

Why this answer

Project Support is an optional role that provides administrative services such as document management and reporting.

118
MCQmedium

In the PRINCE2 RACI model, what does 'Accountable' mean?

A.The person who is consulted before decisions are made
B.The person who does the work
C.The person who is ultimately answerable for the correct completion of the deliverable
D.The person who is informed after decisions are made
AnswerC

This is the definition of Accountable.

Why this answer

The accountable person is ultimately answerable for the correct and thorough completion of the deliverable or task, and has 'A' in the RACI chart.

119
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Increase the stage budget using contingency reserves
B.Raise an Exception Report to the Project Board
C.Close the project as the Business Case is no longer viable
D.Continue with the current plan and report the overrun in the next Highlight Report
AnswerB

This is the correct escalation mechanism when tolerances are forecast to be exceeded.

Why this answer

According to PRINCE2's management by exception, if a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

120
MCQmedium

What is the purpose of the Change Authority role in PRINCE2?

A.To manage the project's risk register.
B.To authorize the project budget.
C.To audit the project's compliance with PRINCE2.
D.To make decisions on change requests within agreed limits.
AnswerD

The Change Authority is delegated to handle change control decisions.

Why this answer

The Change Authority is an optional role that is delegated by the Project Board to make decisions on change requests within defined limits, to streamline the change control process.

121
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board and await their direction
B.Increase the project budget and continue with the current plan
C.Continue with the current plan and report the overrun in the next Highlight Report
D.Close the project immediately as the Business Case is no longer viable
AnswerA

This is the correct escalation procedure per PRINCE2's management by exception principle.

Why this answer

In PRINCE2, when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is a formal mechanism to request a decision on corrective action, as the Project Manager does not have authority to change tolerances or budgets. The Project Board then evaluates the situation and provides direction, ensuring governance and control over the project's viability.

Exam trap

PeopleCert often tests the misconception that the Project Manager can adjust budgets or plans within their own authority, but PRINCE2 strictly requires escalation to the Project Board when tolerances are forecast to be exceeded, not after the fact or via routine reports.

How to eliminate wrong answers

Option B is wrong because the Project Manager cannot unilaterally increase the budget; only the Project Board can authorize changes to tolerances or budgets, and doing so without escalation violates PRINCE2's management by exception principle. Option C is wrong because continuing with the current plan while knowing the cost tolerance will be exceeded is a failure to escalate; Highlight Reports are for routine status updates, not for reporting forecast breaches of tolerance. Option D is wrong because closing the project immediately is premature; the Business Case may still be viable if the Project Board approves a revised tolerance or plan, and only the Project Board can authorize premature closure.

122
Multi-Selectmedium

Which TWO of the following are true about the Senior Responsible Owner (Executive) role?

Select 2 answers
A.Can be shared between two people
B.Accountable for the project's success
C.Is a member of the project team, not the Project Board
D.Owns the Business Case
E.Responsible for day-to-day management
AnswersB, D

The SRO has ultimate accountability.

Why this answer

The SRO is accountable for the project and owns the Business Case. Options A and C are correct. Option B is false; the SRO does not manage day-to-day.

Option D is false; the SRO is a single role. Option E is false; the SRO is a board member.

123
Multi-Selectmedium

Which THREE of the following are defined roles in PRINCE2?

Select 3 answers
A.Technical Lead
B.Team Manager
C.Project Manager
D.Senior User
E.Project Sponsor
AnswersB, C, D

Correct.

Why this answer

Option B (Team Manager) is correct because PRINCE2 defines the Team Manager role as the person responsible for the team's work and for delivering the products within the team plan. This role is distinct from the Project Manager and is formally defined in the PRINCE2 management structure.

Exam trap

PeopleCert often tests the distinction between PRINCE2's defined roles and common industry job titles, so candidates mistakenly select 'Technical Lead' or 'Project Sponsor' because they are familiar from other frameworks, but PRINCE2 does not include them.

124
Multi-Selecthard

Which THREE of the following are responsibilities of the Project Board in PRINCE2?

Select 3 answers
A.Authorizing the start of each stage
B.Approving the Stage Plans
C.Authorizing work packages
D.Providing overall direction and guidance
E.Day-to-day management of the project
AnswersA, B, D

The Board authorizes stage boundaries.

Why this answer

The Project Board provides overall direction, approves stage plans, and authorizes stage boundaries. Day-to-day management and work package authorization are PM responsibilities.

125
MCQmedium

A project is being executed in a stage. The Team Manager reports that a Work Package is likely to exceed its tolerances. What should the Project Manager do first?

A.Assess the situation and consider corrective actions within the stage tolerance
B.Immediately raise an Exception Report to the Project Board
C.Inform the Project Board at the next Highlight Report
D.Request the Team Manager to continue and monitor the situation
AnswerA

The Project Manager first tries to resolve within their delegated authority.

Why this answer

According to PRINCE2, when a Team Manager reports that a Work Package is likely to exceed its tolerances, the Project Manager must first assess the situation and consider corrective actions within the stage tolerance. This is because the Project Manager has delegated authority to manage the stage within the agreed stage tolerances, and only if the forecast exceeds those tolerances should an Exception Report be raised to the Project Board. The correct first step is always to evaluate whether the issue can be resolved within the existing tolerance limits before escalating.

Exam trap

PeopleCert often tests the misconception that any forecast deviation requires immediate escalation to the Project Board, when in fact the Project Manager must first assess whether the issue can be resolved within the existing stage tolerance.

How to eliminate wrong answers

Option B is wrong because immediately raising an Exception Report is premature; the Project Manager must first determine if the deviation can be managed within the stage tolerance. Option C is wrong because waiting for the next Highlight Report would delay necessary action and violates the principle of management by exception, which requires timely escalation when tolerances are forecast to be exceeded. Option D is wrong because simply asking the Team Manager to continue monitoring without assessment abdicates the Project Manager's responsibility to proactively manage deviations and take corrective action.

126
MCQhard

What is the difference between Project Assurance and quality review?

A.There is no difference; they are synonymous terms
B.Project Assurance only occurs at the end of a stage, while quality review occurs continuously
C.Project Assurance is a role that provides independent oversight, while a quality review is a technique used to assess product quality
D.Project Assurance is performed by the Project Manager, while quality review is performed by the Team Manager
AnswerC

This correctly distinguishes the ongoing assurance role from the specific review technique.

Why this answer

Project Assurance is an independent role that provides ongoing assurance to the Project Board, while a quality review is a specific technique for reviewing products. Option B is correct.

127
MCQmedium

Why does PRINCE2 separate the Project Manager role from Project Assurance?

A.To ensure independent oversight and avoid conflicts of interest
B.To allow the Project Manager to focus on team management
C.To comply with corporate governance regulations
D.To reduce the workload of the Project Manager
AnswerA

Correct. Independence is key.

Why this answer

PRINCE2 separates the Project Manager role from Project Assurance to ensure independent oversight and avoid conflicts of interest. The Project Manager is responsible for day-to-day management and decision-making, while Project Assurance provides an objective check that the project remains aligned with business, user, and supplier interests. This separation prevents the Project Manager from being the sole judge of their own work, which could compromise governance and control.

Exam trap

The trap here is that candidates often confuse role separation with workload management or team focus, but PRINCE2 specifically mandates independence to prevent the Project Manager from having unchecked authority over project governance.

How to eliminate wrong answers

Option B is wrong because PRINCE2 does not separate roles to allow the Project Manager to focus on team management; team management is a separate responsibility often delegated to Team Managers, and the separation is about independent oversight, not workload focus. Option C is wrong because while PRINCE2 supports corporate governance, the separation is a structural principle of the method itself, not a direct compliance requirement with external regulations. Option D is wrong because reducing the Project Manager's workload is not the primary reason; the separation is about ensuring objective assurance, not simply offloading tasks.

128
MCQhard

What is the main purpose of separating the Project Manager role from the Project Assurance role in PRINCE2?

A.To allow the Project Manager to focus on team management
B.To reduce the workload of the Project Manager
C.To ensure independent oversight of the project
D.To provide administrative support to the Project Board
AnswerC

Independence is key; Project Assurance provides objective checks and balances.

Why this answer

Project Assurance provides independent oversight to the Project Board, ensuring the project is on track without being influenced by the Project Manager's day-to-day perspective.

129
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Manager in PRINCE2?

Select 2 answers
A.Approve the Project Plan
B.Manage day-to-day project activities within tolerances
C.Provide independent assurance to the Project Board
D.Chair the Project Board meetings
E.Prepare the Stage Plan for the next stage
AnswersB, E

Correct: The Project Manager manages the project within agreed tolerances.

Why this answer

Option B is correct because the Project Manager is responsible for managing the day-to-day activities of the project within the tolerances set by the Project Board. This includes monitoring progress, resolving issues, and escalating deviations that exceed tolerances. PRINCE2 defines this as a core duty to ensure the project remains on track without requiring constant Board intervention.

Exam trap

The trap here is confusing the Project Manager's operational duties with the Project Board's strategic or assurance responsibilities, especially regarding plan approval and independent oversight.

130
Multi-Selecthard

Which THREE of the following are defined as PRINCE2 project management team roles?

Select 3 answers
A.Quality Manager
B.Project Manager
C.Risk Manager
D.Project Support
E.Project Assurance
AnswersB, D, E

A core role in the management team.

Why this answer

PRINCE2 defines specific roles: Project Manager, Team Manager, Project Assurance, Project Support, and the Project Board (Executive, Senior User, Senior Supplier). 'Risk Manager' and 'Quality Manager' are not standard roles in PRINCE2; their responsibilities are typically covered by Project Assurance or delegated within the team.

131
MCQeasy

Which role ensures that the project's products meet the needs of the users?

A.Senior User
B.Project Assurance
C.Senior Supplier
D.Project Manager
AnswerA

The Senior User ensures that the products meet user requirements.

Why this answer

The Senior User represents the users and ensures that the products meet their needs. The PM manages delivery but the Senior User defines requirements.

132
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.Both are the same
B.An Off-spec is to change something; an RFC is a product not meeting specification
C.Both are handled only by the Project Board
D.An RFC is to change something; an Off-spec is a product not meeting specification
AnswerD

Correct distinction.

Why this answer

An RFC proposes a change to agreed baselines; an Off-spec is a product that does not meet its specification.

133
MCQeasy

In PRINCE2, who is accountable for the project's success and the realization of benefits?

A.Senior Responsible Owner (SRO)
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The SRO is the single point of accountability for the project and its benefits.

Why this answer

The Senior Responsible Owner (SRO) is the single person accountable for the project's success and the realization of benefits.

134
MCQmedium

During the Initiating a Project process, which document is created that defines how the project will be controlled and governed?

A.Project Initiation Documentation (PID)
B.Project Brief
C.Project Plan
D.Business Case
AnswerA

The PID is the comprehensive document that defines how the project will be controlled.

Why this answer

The Project Initiation Documentation (PID) is the key output of the Initiating a Project process. It provides the foundation for project governance and control.

135
Multi-Selectmedium

Which THREE of the following are roles on the Project Board?

Select 3 answers
A.Project Manager
B.Senior User
C.Senior Supplier
D.Project Assurance
E.Senior Responsible Owner (Executive)
AnswersB, C, E

The Senior User represents users on the Board.

Why this answer

The PRINCE2 Project Board is the decision-making body responsible for overall project governance. It comprises three roles: the Executive (Senior Responsible Owner), the Senior User, and the Senior Supplier. The Senior User represents the interests of those who will use the project's outputs and is essential for defining requirements and benefits.

Exam trap

The trap here is that candidates often confuse the Project Manager (a management role) with a Project Board role, or mistakenly think Project Assurance is a board role rather than a separate oversight function.

136
MCQmedium

In a PRINCE2 project, the Project Manager submits an Exception Report. What is the most likely trigger for this report?

A.The Project Manager needs to request additional resources within the current stage tolerance
B.A team member reports a minor delay that can be accommodated within tolerance
C.The project is forecast to exceed the stage cost tolerance
D.The Senior User requests a change that does not affect the Business Case
AnswerC

A forecast tolerance breach triggers an Exception Report to the Project Board.

Why this answer

In PRINCE2, an Exception Report is triggered when a forecast indicates that a stage will exceed its agreed tolerance (e.g., cost or time). Option C is correct because exceeding stage cost tolerance is a formal deviation that requires escalation to the Project Board via an Exception Report, as the Project Manager cannot authorize changes beyond tolerance.

Exam trap

The trap here is confusing an Exception Report (triggered by tolerance breach) with an Issue Report or Change Request (triggered by problems or changes within tolerance).

How to eliminate wrong answers

Option A is wrong because requesting additional resources within the current stage tolerance does not require an Exception Report; the Project Manager can handle this within delegated authority. Option B is wrong because a minor delay accommodated within tolerance is managed within the stage plan and does not trigger an Exception Report. Option D is wrong because a change requested by the Senior User that does not affect the Business Case is typically handled via a Change Request or Issue Report, not an Exception Report, as it does not breach tolerance.

137
MCQmedium

Which document describes the user's needs and expectations for the project's products?

A.Stage Plan
B.Project Brief
C.Project Product Description
D.Business Case
AnswerC

This describes the final product, including user expectations and acceptance criteria.

Why this answer

The Project Product Description defines the overall product and its expectations, including user needs, but the User Requirements document captures detailed user needs. However, in PRINCE2, the Project Product Description is the key document for defining what the user expects.

138
MCQhard

What is the key difference between Project Assurance and a quality review?

A.There is no difference; they are synonymous
B.Project Assurance is a one-time activity, while quality reviews are continuous
C.Project Assurance is performed by the Project Manager, while a quality review is performed by the team
D.Project Assurance focuses on the project's compliance with PRINCE2, while a quality review focuses on product quality
AnswerD

Project Assurance checks adherence to standards and processes; quality review checks product fitness for purpose.

Why this answer

Project Assurance is an independent oversight role ensuring the project stays on track, while a quality review is a specific technique to assess the quality of products.

139
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO/Executive)
B.Project Assurance
C.Project Manager
D.Senior User
AnswerA

The SRO is accountable for the Business Case throughout the project.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and must ensure it remains viable. The Project Manager develops and maintains it on behalf of the SRO.

140
MCQeasy

What is the primary purpose of the Project Support role in PRINCE2?

A.To provide independent assurance to the Project Board
B.To approve Work Packages
C.To provide administrative support, such as maintaining files and tools
D.To manage the day-to-day activities of the project
AnswerC

Project Support handles the administrative aspects of the project.

Why this answer

Project Support provides administrative and support services to the project team. It is an optional role.

141
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Assurance role?

Select 2 answers
A.To manage the project team on a daily basis
B.To allocate Work Packages to teams
C.To monitor project compliance with PRINCE2 processes
D.To administer project documentation
E.To provide independent advice to the Project Board on project status
AnswersC, E

Assurance ensures the project follows processes correctly.

Why this answer

Project Assurance independently monitors compliance with standards and assesses risks and issues, reporting to the Project Board. It does not manage day-to-day or provide admin support.

142
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Senior Responsible Owner (SRO)
B.Project Manager
C.Senior User
D.Project Support
AnswerA

The SRO is responsible for the Business Case and its ongoing viability.

Why this answer

The Senior Responsible Owner (SRO/Executive) is accountable for the Business Case and ensuring it remains viable. Option A is correct.

143
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Write Work Packages
B.Perform Project Assurance
C.Manage the project on a day-to-day basis
D.Provide resources and authorize funds
E.Authorize stage plans and major deviations
AnswersD, E

The Project Board ensures resources are available.

Why this answer

Option D is correct because the Project Board is responsible for providing resources and authorizing funds for the project. This is a key duty of the board, as they own the business case and must ensure the project remains viable by approving the necessary budget and resource allocation.

Exam trap

The trap here is confusing the Project Board's strategic oversight responsibilities (like authorizing stage plans and providing resources) with the Project Manager's tactical duties (like writing Work Packages or day-to-day management), leading candidates to select options A or C instead of the correct pair D and E.

144
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Continue and report in the next Highlight Report
B.Close the project as the Business Case is no longer viable
C.Raise an Exception Report to the Project Board
D.Increase the stage budget to absorb the overrun
AnswerC

Management by exception requires immediate escalation.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report immediately.

145
MCQmedium

A project is forecast to exceed its cost tolerance for the current stage. What should the Project Manager do?

A.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
B.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
C.Close the project immediately as the Business Case is no longer viable
D.Raise an Exception Report to the Project Board and await their direction before proceeding
AnswerD

Correct. The PM must escalate immediately via an Exception Report.

Why this answer

In PRINCE2, when a stage is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because the Project Manager does not have authority to exceed the agreed tolerance; the Project Board must decide whether to approve a revised plan or take other corrective action. Option D correctly follows the PRINCE2 exception management process.

Exam trap

The trap here is that candidates may think the Project Manager can adjust the budget or delay reporting, but PRINCE2 strictly requires immediate escalation via an Exception Report when tolerances are forecast to be exceeded.

How to eliminate wrong answers

Option A is wrong because the Project Manager cannot unilaterally increase the project budget; only the Project Board can authorize a budget change, and doing so without approval violates the delegated authority and tolerance levels. Option B is wrong because the Project Manager must report the forecast overrun immediately via an Exception Report, not wait for the next Highlight Report, as this would delay necessary corrective action and breach the management by exception principle. Option C is wrong because the Business Case may still be viable; the Project Board should assess the situation and decide whether to continue, amend, or close the project, not the Project Manager unilaterally.

146
MCQmedium

In PRINCE2, the Project Board should meet at which frequency?

A.Weekly
B.Monthly
C.Exception-driven (triggered by management by exception)
D.Daily
AnswerC

Correct: the Board meets when exceptions occur or for stage boundaries.

Why this answer

The Project Board meets on an exception-driven basis, i.e., when decisions are needed due to deviations or at stage boundaries, not on a fixed schedule.

147
Multi-Selectmedium

Which TWO of the following are responsibilities of the Senior Responsible Owner (SRO)?

Select 2 answers
A.Managing the day-to-day activities of the project
B.Ensuring the project delivers the expected benefits
C.Maintaining the Business Case
D.Preparing the Project Plan
E.Approving the Work Packages
AnswersB, C

Benefits realization is a key accountability of the SRO.

Why this answer

The SRO owns the Business Case and is accountable for the project's success and benefits realization. They also chair the Project Board.

148
MCQmedium

During the Managing a Stage Boundary process, the Project Manager creates the Stage Plan for the next stage. Who approves this Stage Plan?

A.Project Manager
B.Senior Responsible Owner
C.Senior Supplier
D.Project Board
AnswerD

The Project Board approves the Stage Plan before the next stage can begin.

Why this answer

The Project Board approves the Stage Plan for the next stage, allowing the project to proceed. This is part of the exception-driven decision-making.

149
MCQeasy

Who is responsible for defining the project's tolerance levels?

A.Senior User
B.Project Manager
C.Team Manager
D.Project Board
AnswerD

The Board sets tolerances as part of project governance.

Why this answer

The Project Board sets project-level tolerances (e.g., time, cost, quality) in the PID, providing boundaries within which the Project Manager operates.

150
Multi-Selectmedium

Which TWO of the following statements correctly describe the relationship between the Project Manager and Project Assurance?

Select 2 answers
A.Project Assurance reports to the Project Manager
B.Project Assurance is independent of the Project Manager
C.Project Assurance provides an independent view of the project's health
D.The Project Manager can assign Project Assurance tasks to themselves if resources are limited
E.The Project Manager can delegate Project Assurance duties to a Team Manager
AnswersB, C

Independence is a key principle.

Why this answer

Option B is correct because PRINCE2 mandates that Project Assurance is independent of the Project Manager to ensure objective oversight. Option C is correct because Project Assurance's primary role is to provide an independent view of the project's health, checking compliance with standards and business justification.

Exam trap

The trap here is that candidates confuse Project Assurance with quality control or project support roles, assuming the Project Manager can control or delegate assurance tasks, when in fact PRINCE2 strictly separates assurance from management to maintain objectivity.

← PreviousPage 2 of 5 · 335 questions totalNext →

Ready to test yourself?

Try a timed practice session using only People: organizations, teams, and leadership questions.