Courseiva

PRINCE2F People: organizations, teams, and leadership Practice Question

Which role is responsible for delivering Work Packages and reporting progress to the Project Manager?

⚠ Common exam trap

Watch out — candidates often confuse the Project Manager's overall responsibility for the project with the delegated responsibility for delivering specific Work Packages, leading candidates to incorrectly select the Project Manager as the role that directly delivers Work Packages.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Team Manager

The Team Manager is responsible for delivering Work Packages and reporting progress to the Project Manager. In PRINCE2, the Team Manager coordinates the work of the team, ensures the Work Package is completed to specification, and provides regular progress reports to the Project Manager, who manages the overall project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Senior Supplier

    Why it's wrong here

    The Senior Supplier represents supplier interests on the project board and provides resources; it does not deliver Work Packages. It is tempting because suppliers do the actual building work, so the role sounds operational, but delivery and progress reporting against Work Packages belong to the Team Manager.

  • ✗

    Project Assurance

    Why it's wrong here

    Project Assurance monitors the project on behalf of the board, checking that plans, delegation and controls are followed; it never delivers Work Packages. It is tempting because assurance reviews progress, but its remit is independent oversight, not execution or reporting to the Project Manager.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager manages the project, authorises Work Packages and receives progress reports, but does not deliver them. It is tempting because the role owns the Work Package concept, yet the Team Manager is the one who accepts, executes and reports on each Work Package.

  • ✓

    Team Manager

    Why this is correct

    The Team Manager accepts Work Packages from the Project Manager, manages delivery of those packages, and reports progress and quality information back. This satisfies the stem's requirement for the role accountable for Work Package delivery and progress reporting within PRINCE2's organisation theme.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.