Which report is produced by the Team Manager and used by the Project Manager to update the Project Board?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Checkpoint Report

The Checkpoint Report is produced by the Team Manager and sent to the Project Manager. The Project Manager then uses it to compile the Highlight Report for the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Checkpoint Report

    Why this is correct

    Correct.

  • Exception Report

    Why it's wrong here

    The Exception Report is produced by the Project Manager when tolerances are forecast to be exceeded.

  • End Stage Report

    Why it's wrong here

    The End Stage Report is produced by the Project Manager at stage boundaries.

  • Highlight Report

    Why it's wrong here

    The Highlight Report is produced by the Project Manager.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.