Which report is produced by the Team Manager and used by the Project Manager to update the Project Board?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Checkpoint Report
The Checkpoint Report is produced by the Team Manager and sent to the Project Manager. The Project Manager then uses it to compile the Highlight Report for the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Checkpoint Report
Why this is correct
Correct.
- ✗
Exception Report
Why it's wrong here
The Exception Report is produced by the Project Manager when tolerances are forecast to be exceeded.
- ✗
End Stage Report
Why it's wrong here
The End Stage Report is produced by the Project Manager at stage boundaries.
- ✗
Highlight Report
Why it's wrong here
The Highlight Report is produced by the Project Manager.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.