Project Management Professional PMP (PMP) — Questions 601675

892 questions total · 12pages · All types, answers revealed

Page 8

Page 9 of 12

Page 10
601
MCQmedium

In an agile project, the team's velocity has decreased over the last three sprints from 30 story points to 22. During the retrospective, the team cites increasing technical debt as the cause. What should the scrum master do FIRST?

A.Facilitate a discussion with the team to identify actions to reduce technical debt and improve velocity.
B.Ask the product owner to reduce the sprint backlog to match the lower velocity.
C.Report the velocity drop to management and escalate the technical debt issue.
D.Add more developers to the team to increase velocity.
AnswerA

The scrum master should coach the team to identify and resolve impediments, such as technical debt, to improve performance.

Why this answer

The scrum master should facilitate the team to identify root causes and create an action plan to address technical debt. This aligns with agile principles of continuous improvement and self-organization.

602
Multi-Selecteasy

You are leading an agile team that has experienced a drop in velocity over the last three sprints. The team attributes this to unclear requirements and frequent changes during the sprint. Which TWO actions would best address this?

Select 2 answers
A.Increase sprint duration from two weeks to three weeks to allow more time
B.Replace underperforming team members with new ones
C.Take over the role of product owner to ensure clarity
D.Reinforce the sprint rule that no new work can be added once the sprint has started
E.Work with the product owner to improve user story refinement and acceptance criteria before sprint planning
AnswersD, E

Stabilizing scope protects the team's focus.

Why this answer

Option A improves requirement clarity. Option B stabilizes the sprint by preventing changes. Option C is wrong because longer sprints may not help.

Option D is wrong because replacing team members is drastic. Option E is wrong because the PM should facilitate, not take over.

603
MCQmedium

A key vendor informs you that due to raw material shortages, they cannot deliver a critical component on time. This component is on the critical path. The risk register included this as a high-probability risk with a contingency plan to use an alternative supplier. What should you do FIRST?

A.Ask the project sponsor to approve the alternative supplier
B.Replan the project schedule to accommodate the delay
C.Perform a new risk analysis to assess the impact
D.Activate the contingency plan and engage the alternative supplier
AnswerD

Since the risk was identified and a contingency plan exists, the PM should implement it.

Why this answer

D is correct because the risk was already identified, assessed as high-probability, and a contingency plan (alternative supplier) was documented in the risk register. When the risk occurs, the first action is to execute the pre-approved contingency plan, not to reanalyze or seek new approvals, as the plan was already vetted during risk planning.

Exam trap

The trap here is that candidates confuse the need for a new risk analysis or approval with the fact that the contingency plan was already approved and documented, leading them to waste time on unnecessary steps instead of executing the pre-planned response.

How to eliminate wrong answers

Option A is wrong because the contingency plan was already approved during risk planning; asking the sponsor to approve again wastes time and violates the principle of pre-approved contingency responses. Option B is wrong because replanning the schedule is a fallback or corrective action if the contingency plan fails, not the first step when a pre-planned response exists. Option C is wrong because performing a new risk analysis is redundant; the risk was already analyzed and a response was prepared—reanalysis delays execution of the known solution.

604
MCQeasy

In an agile project, the team's velocity has dropped for three consecutive sprints. What should the project manager do FIRST?

A.Ask the team to work overtime to catch up
B.Add more team members to increase capacity
C.Facilitate a retrospective to identify the root causes and address them
D.Reduce the sprint scope to match the current velocity
AnswerC

The agile framework encourages inspecting and adapting; a retrospective helps the team find and fix process issues.

Why this answer

Option C is correct because the PM should investigate the root cause of the velocity drop before taking action. Option A is wrong because adding team members may not address the underlying issue and can disrupt the team. Option B is wrong because increasing overtime can lead to burnout.

Option D is wrong because reducing scope without understanding the cause may hide problems.

605
MCQmedium

A project manager is leading a team with diverse cultural backgrounds. Some members are reluctant to speak up in meetings. What is the best strategy to promote inclusive participation?

A.Schedule one-on-one meetings with only the quiet members.
B.Ask the most senior team member to represent others.
C.Use anonymous polling tools to gather opinions before decisions.
D.Implement a round-robin where everyone must speak.
AnswerC

Anonymous input encourages honest feedback.

Why this answer

Option C is correct because anonymous polling tools create a psychologically safe environment where team members from diverse cultural backgrounds can contribute without fear of judgment or loss of face. This aligns with the PMI Talent Triangle's emphasis on emotional intelligence and inclusive leadership, as it removes power dynamics and cultural barriers that inhibit verbal participation in meetings.

Exam trap

The trap here is that candidates often choose round-robin (Option D) thinking it forces equality, but the PMP exam tests the nuanced understanding that forced participation can backfire in culturally diverse teams, whereas anonymous tools foster genuine inclusion without coercion.

How to eliminate wrong answers

Option A is wrong because scheduling one-on-one meetings with only the quiet members singles them out, potentially causing embarrassment or reinforcing a perception of being 'different,' which undermines inclusive participation. Option B is wrong because asking the most senior team member to represent others violates the principle of shared voice and can suppress diverse perspectives, especially from junior or less assertive members. Option D is wrong because implementing a round-robin where everyone must speak can create anxiety and force participation, which is counterproductive for members from cultures where speaking out of turn or disagreeing publicly is considered disrespectful.

606
Multi-Selecthard

During project execution, you receive a change request from a key stakeholder to add a new deliverable. The change would require additional resources and extend the schedule by two months. The project is currently on track. Which THREE actions should you take?

Select 3 answers
A.Ask the team to start working on the new deliverable while the change request is being reviewed.
B.Add the deliverable to the project scope without formal approval to satisfy the stakeholder.
C.Document the change request and its disposition in the change log.
D.Evaluate the impact of the change on the project baselines.
E.Update the project management plan and baselines if the change is approved.
AnswersC, D, E

All change requests, whether approved or rejected, should be logged.

Why this answer

Proper change control requires evaluating the impact on the project management plan, updating the plan if approved, and ensuring all changes are documented. Communicating to stakeholders is also part of the process.

607
Multi-Selecthard

Your organization is adopting SAFe (Scaled Agile Framework) to improve alignment across multiple agile teams. As a project manager, you are responsible for ensuring that the transformation is successful. Which THREE actions should you take to support the agile transformation?

Select 3 answers
A.Ensure that value streams are identified and aligned with the organization's strategic goals
B.Implement a command-and-control management style to enforce consistency
C.Provide training on agile and SAFe principles to all team members and stakeholders
D.Reduce communication between teams to minimize distractions
E.Establish Communities of Practice to share best practices across teams
AnswersA, C, E

SAFe emphasizes value stream alignment with strategy.

Why this answer

Options A, B, and D are correct. A: Training helps everyone understand the new framework. B: Aligning value streams to strategy ensures business value.

D: Establishing Communities of Practice fosters knowledge sharing. Option C is wrong because using a command-and-control style contradicts agile principles. Option E is wrong because reducing communication hinders collaboration.

608
MCQmedium

A key vendor has informed you that they cannot deliver a critical component for another two weeks, which will delay your project. The component is on the critical path. What should you do first?

A.Ask the team to work overtime to make up for the delay
B.Penalize the vendor as per the contract
C.Immediately notify the sponsor and request a schedule extension
D.Update the risk register and review the response plan for this risk
AnswerD

The risk register should contain a response plan. The PM should implement the planned response.

Why this answer

Option D is correct because the first action when a known risk materializes is to consult the risk register and execute the pre-defined response plan. Since the vendor delay is a risk that was likely identified and documented, updating the register and reviewing the planned response ensures a structured, data-driven approach rather than a reactive one. This aligns with the PMBOK Guide's guidance on implementing risk responses as the immediate next step after risk occurrence.

Exam trap

The trap here is that candidates often jump to escalation (Option C) or punitive action (Option B) without first consulting the risk register, which is the foundational step in managing identified risks according to PMI's risk management framework.

How to eliminate wrong answers

Option A is wrong because asking the team to work overtime is a reactive, unplanned action that may not address the root cause (vendor delay) and could lead to burnout, quality issues, or cost overruns without first evaluating the risk response plan. Option B is wrong because penalizing the vendor is a contractual remedy that should be executed as part of the risk response plan, not as the first step; immediate penalties may damage the relationship and ignore other mitigation options like expedited shipping or alternative sourcing. Option C is wrong because notifying the sponsor and requesting a schedule extension is a premature escalation that bypasses the risk management process; the project manager should first assess the risk register and response plan to determine if the delay can be mitigated or accommodated within existing buffers.

609
MCQmedium

You are the project manager for a software development project using Scrum. During the daily stand-up, two senior developers get into a heated argument about the technical approach for a user story. The sprint goal is at risk. What should you do FIRST?

A.Report the conflict to the product owner and ask for a decision
B.Intervene immediately and decide the technical approach to resolve the conflict
C.Cancel the stand-up and schedule a separate meeting to resolve the issue
D.Ask the developers to resolve the conflict after the meeting and escalate if they cannot
AnswerD

Coaching the team to resolve conflicts themselves promotes self-organization and empowerment.

Why this answer

Option D is correct because the Scrum framework empowers the development team to self-organize and resolve technical disagreements. The project manager should facilitate the team's autonomy by asking the developers to resolve the conflict after the stand-up, escalating only if they cannot reach a consensus, thus protecting the sprint goal without imposing a top-down decision.

Exam trap

The trap here is that candidates often assume the project manager must immediately intervene or escalate to the product owner, confusing the role of a traditional project manager with that of a Scrum facilitator who empowers team self-management.

How to eliminate wrong answers

Option A is wrong because the product owner is responsible for the product backlog, not for resolving technical disputes between developers; reporting the conflict to the product owner abdicates the team's self-management responsibility. Option B is wrong because the project manager should not unilaterally decide the technical approach, as this undermines the team's autonomy and may lead to suboptimal solutions; the team should own the technical decision. Option C is wrong because canceling the stand-up disrupts the daily synchronization of the entire team and delays resolution; a separate meeting can be scheduled after the stand-up without halting the event.

610
Multi-Selecthard

A project manager discovers that a key supplier is delivering materials that do not meet quality standards. The project is at risk of delays and rework. Which THREE actions should the project manager take?

Select 3 answers
A.Escalate the issue to the procurement department if the supplier does not respond
B.Work with the supplier to develop a corrective action plan
C.Immediately terminate the contract with the supplier
D.Document the quality issues in the issue log and notify relevant stakeholders
E.Accept the nonconforming materials and adjust the project plan
AnswersA, B, D

Escalation is appropriate if the supplier fails to take corrective action.

Why this answer

Options A, C, and E are correct: documenting quality issues, working with the supplier on corrective action, and escalating if necessary are appropriate steps.

611
MCQmedium

A risk that was identified and in the risk register has occurred. The risk response plan involves outsourcing a component, but the vendor is now unable to deliver on time. What should the project manager do FIRST?

A.Implement the fallback plan or contingency reserves as defined in the risk register
B.Wait to see if the vendor can resolve the issue
C.Escalate the issue to the project sponsor for guidance
D.Reassign the work to an internal team
AnswerA

The risk register should have a contingency plan for such scenarios.

Why this answer

Option A is correct because the risk has materialized and the risk response plan (outsourcing) has failed. The project manager must immediately execute the pre-defined fallback plan or use contingency reserves as documented in the risk register. This aligns with the PMBOK Guide's guidance on implementing risk responses when the primary response is no longer viable.

Exam trap

The trap here is that candidates confuse 'implement the fallback plan' with 'escalate to sponsor,' but the PMBOK Guide emphasizes that the project manager should first use the pre-defined risk responses before escalating, as escalation is reserved for risks outside the project manager's authority.

How to eliminate wrong answers

Option B is wrong because waiting passively for the vendor to resolve the issue violates the proactive risk management principle; the risk has already occurred and requires immediate action per the risk register. Option C is wrong because escalation to the sponsor is premature; the project manager should first execute the documented fallback plan or contingency reserves, which are within their authority. Option D is wrong because reassigning work to an internal team without consulting the risk register may introduce new risks (e.g., skill gaps, schedule conflicts) and bypasses the pre-planned response strategy.

612
MCQmedium

During a sprint review, the product owner expresses dissatisfaction with the feature delivered, stating it does not meet the acceptance criteria. The team disagrees, claiming it meets the definition of done. What should the project manager do first?

A.Escalate the issue to the project sponsor for a decision
B.Schedule a meeting with the product owner and the team to review the acceptance criteria and define done
C.Support the team's position and ask the product owner to accept the deliverable
D.Ask the team to redo the work to meet the product owner's expectations
AnswerB

Collaborative review clarifies expectations and promotes transparency.

Why this answer

Clarifying expectations by reviewing the acceptance criteria together resolves the misunderstanding and aligns both parties.

613
MCQhard

Your project uses a hybrid approach with a fixed-price contract. Midway through, the client requests a significant scope change that would increase project duration by two months. The project manager has assessed the impact and believes the change is beneficial. However, the sponsor is reluctant because of the schedule extension. What should the project manager do?

A.Prepare a change request with impact analysis and submit it to the CCB for approval.
B.Negotiate with the client to drop another requirement to keep the schedule.
C.Accept the change informally and adjust the schedule to accommodate it.
D.Reject the request because it will delay the project and risk penalties.
AnswerA

This follows the formal change control process, allowing informed decision-making.

Why this answer

In a hybrid project with a fixed-price contract, any scope change must follow the formal change control process. The project manager has assessed the change as beneficial, but the sponsor's reluctance requires a documented impact analysis to enable an informed decision by the Change Control Board (CCB). Submitting a formal change request ensures contractual compliance, protects against scope creep, and provides a clear audit trail, which is critical when the schedule extension affects fixed-price terms.

Exam trap

The trap here is that candidates may assume the project manager can unilaterally accept a beneficial change or negotiate directly with the client, ignoring the formal change control process required by the hybrid approach and fixed-price contract constraints.

How to eliminate wrong answers

Option B is wrong because negotiating to drop another requirement without a formal change request bypasses the CCB and risks violating the fixed-price contract's scope baseline, potentially leading to disputes or unapproved scope reduction. Option C is wrong because informally accepting the change and adjusting the schedule violates the formal change control process required in a hybrid approach, leading to undocumented scope creep and potential legal issues under the fixed-price contract. Option D is wrong because rejecting the request outright ignores the project manager's assessment that the change is beneficial and fails to follow the proper change management procedure, which could damage the client relationship and miss a valuable opportunity.

614
MCQmedium

You are managing a software development project using a hybrid approach. During a sprint review, the product owner requests a new feature that was not in the backlog. The team estimates it will take 5 additional days. What should you do first?

A.Add the feature to the product backlog and prioritize it in the next sprint planning
B.Inform the product owner that no changes can be made once the sprint has started
C.Submit a change request to the change control board and assess impact on schedule, cost, and resources
D.Ask the team to start working on the feature immediately to satisfy the stakeholder
AnswerC

PMI requires all changes to go through the Integrated Change Control process. The PM must document, assess, and obtain approval before proceeding.

Why this answer

According to PMI, any scope change must go through the change control process. The most appropriate first step is to document and assess the impact of the change.

615
MCQeasy

During a project status meeting, you notice that one team member consistently interrupts others and dismisses their ideas. This behavior is affecting team morale and collaboration. What should you do first?

A.End the meeting and schedule a team-building session
B.Speak privately with the team member after the meeting to discuss the impact of their behavior
C.Ignore the behavior as it is not affecting the project outcomes directly
D.Ask the team member to leave the meeting until they can behave professionally
AnswerB

Private feedback respects the individual and addresses the issue directly, which is the PMI-recommended approach.

Why this answer

Option B is correct because addressing interpersonal issues privately and promptly aligns with the PMP's focus on proactive conflict resolution and team management. By speaking privately with the team member, you can discuss the specific behavior's impact on morale and collaboration without public embarrassment, which is key to maintaining a respectful team environment and preventing escalation.

Exam trap

The trap here is that candidates may choose Option A (team-building) as a quick fix, mistaking a general morale-boosting activity for the specific, targeted intervention required by the PMP's emphasis on addressing the root cause of conflict first.

How to eliminate wrong answers

Option A is wrong because ending the meeting and scheduling a team-building session is an overreaction that disrupts project progress and avoids directly addressing the specific behavior. Option C is wrong because ignoring the behavior, even if it doesn't immediately affect project outcomes, can lead to long-term morale damage and reduced collaboration, which ultimately impacts project success. Option D is wrong because asking the team member to leave publicly escalates the conflict, damages trust, and violates the principle of addressing issues privately first.

616
MCQeasy

A junior team member consistently misses deadlines, affecting the project schedule. You have spoken to them twice about the issue, but performance has not improved. What should you do NEXT?

A.Reassign the tasks to another team member.
B.Meet with the team member privately to explore any obstacles or personal challenges.
C.Escalate the matter to the team member's functional manager.
D.Ignore the issue to avoid conflict.
AnswerB

A private meeting to understand root causes demonstrates servant leadership and support.

Why this answer

Option B is correct because the PM should first seek to understand the root cause of the performance issue through a private, supportive conversation. This aligns with the PMP's 'People' domain, emphasizing servant leadership and emotional intelligence. Exploring obstacles or personal challenges addresses potential underlying factors (e.g., unclear requirements, resource constraints, or personal stress) before escalating or reassigning work.

Exam trap

The trap here is that candidates often jump to reassignment (Option A) or escalation (Option C) as 'decisive' actions, failing to recognize that the PM must first use interpersonal skills to diagnose and support the team member, as per the PMP's emphasis on leading people over managing tasks.

How to eliminate wrong answers

Option A is wrong because reassigning tasks without understanding the root cause is a reactive, short-term fix that avoids addressing the team member's development and may demotivate them further. Option C is wrong because escalating to the functional manager should be a later step, after the PM has exhausted direct coaching and support; premature escalation undermines the PM's leadership and the team member's trust. Option D is wrong because ignoring the issue violates the PM's responsibility to manage the project schedule and support team performance, and it risks schedule slippage and team morale.

617
MCQhard

In an agile transformation initiative, the project manager notices that the team's velocity has dropped significantly over the last three sprints. The team cites unclear requirements and frequent interruptions from stakeholders. The project manager also notes that the product owner has been absent from sprint planning and review meetings. What should the project manager do first?

A.Schedule a meeting with the product owner and the project sponsor to discuss the importance of the product owner's role and its impact on velocity.
B.Implement a stricter definition of 'done' and enforce it during sprint reviews.
C.Add more buffer time to future sprint backlogs to compensate for the low velocity.
D.Escalate to the PMO to replace the product owner.
AnswerA

Why this answer

The root cause appears to be the product owner's absence, which leads to unclear requirements and stakeholder interference. Addressing this with the product owner and sponsor directly tackles the issue. Option A is a general fix that doesn't address the specific cause.

Option C is reactive and may not improve future sprints. Option D escalates prematurely.

618
MCQmedium

Your agile team has noticed that sprint velocity has dropped from 30 to 20 story points over the last three sprints. During the retrospective, team members mention unclear requirements and frequent interruptions. As the project manager, what should you do first?

A.Work with the product owner to improve user story refinement and establish a 'definition of ready' to reduce ambiguity
B.Add more team members to the next sprint to increase capacity
C.Reduce the sprint length to increase focus
D.Ask the team to commit to a lower velocity in the next sprint planning
AnswerA

Improving the readiness of stories and reducing interruptions addresses the root cause and helps restore velocity.

Why this answer

The core issue is unclear requirements and interruptions. The PM should address the root cause by improving the refinement process and protecting the team from disruptions.

619
MCQhard

A project is in execution phase, and a team member consistently misses deadlines, impacting the critical path. The project manager has had informal conversations, but the behavior continues. What should the project manager do next?

A.Reassign the team member to a less critical task
B.Initiate the formal performance management process as per organizational policy
C.Ignore the issue and hope it resolves on its own
D.Replace the team member with a new resource
AnswerB

Formal steps ensure documentation and provide a clear path for improvement or consequences.

Why this answer

Option B is correct because once informal coaching has failed to correct a performance issue that impacts the critical path, the project manager must escalate to the formal performance management process as defined in the organizational policy. This ensures due process, documentation, and alignment with HR and legal requirements, protecting both the project and the organization.

Exam trap

The trap here is that candidates often choose Option A (reassign to a less critical task) thinking it is a quick fix to protect the critical path, but the PMP exam expects the project manager to follow the organizational policy for performance issues before considering reassignment or replacement.

How to eliminate wrong answers

Option A is wrong because reassigning the team member to a less critical task merely avoids the problem without addressing the root cause of the missed deadlines; it does not correct the behavior and may shift the risk to another area. Option C is wrong because ignoring the issue will likely cause further schedule delays on the critical path, increasing project risk and potentially leading to stakeholder dissatisfaction or project failure. Option D is wrong because replacing the team member is a drastic step that should only be taken after formal performance management has been attempted and documented; skipping this step violates organizational policy and could expose the organization to legal or ethical issues.

620
MCQhard

During a project closure phase, you realize that several deliverables were completed but not formally accepted by the customer. The contract requires signed acceptance for each deliverable. What should you do first?

A.Inform the sponsor that the project is complete and request closure approval
B.Document lessons learned and then close the project
C.Archive the project records and close the project as the work is complete
D.Schedule a meeting with the customer to obtain formal acceptance of the outstanding deliverables
AnswerD

Formal acceptance is a prerequisite for project closure.

Why this answer

Option A is correct because without formal acceptance, the project cannot be closed. Option B is wrong because obtaining acceptance is the PM's responsibility. Option C is wrong because lessons learned are important but not the immediate priority.

Option D is wrong because closing without acceptance is not allowed.

621
MCQhard

A project manager is leading a virtual team distributed across three time zones. The team has been performing well, but recently two team members have missed deadlines and seem disengaged. The project manager suspects the cause is related to team member motivation. According to the PMBOK Guide, which theory suggests that people are motivated by achievement, recognition, and growth opportunities?

A.Expectancy theory
B.Herzberg's two-factor theory
C.Maslow's hierarchy of needs
D.McGregor's Theory X
AnswerB

Herzberg's motivators include achievement, recognition, and growth.

Why this answer

Herzberg's two-factor theory (also known as the motivation-hygiene theory) distinguishes between hygiene factors (e.g., salary, work conditions) and motivators (e.g., achievement, recognition, growth opportunities). The question specifically points to motivation factors, which aligns directly with Herzberg's motivators. In a virtual team context, the project manager can address disengagement by providing challenging assignments, public recognition, and professional development paths.

Exam trap

PMI often tests the distinction between Herzberg's motivators and hygiene factors, and candidates confuse 'recognition' as a hygiene factor or mistakenly apply Maslow's esteem level, which is a broader category that includes both internal and external esteem needs.

How to eliminate wrong answers

Option A is wrong because Expectancy theory (Vroom) focuses on the belief that effort leads to performance and performance leads to a valued outcome (valence), not specifically on achievement, recognition, or growth. Option C is wrong because Maslow's hierarchy of needs is a pyramid of five levels (physiological, safety, social, esteem, self-actualization) and while esteem and self-actualization overlap with the given factors, the theory is broader and not exclusively about achievement, recognition, and growth as distinct motivators. Option D is wrong because McGregor's Theory X assumes employees are inherently lazy, dislike work, and need coercion and control, which is the opposite of a motivation theory centered on positive growth and recognition.

622
Multi-Selecthard

Your agile project has experienced a significant drop in velocity for two consecutive sprints. The team is blaming unclear requirements from the product owner, while the product owner claims the team is not collaborating enough. As the scrum master, which THREE actions should you take to address the situation?

Select 3 answers
A.Add buffer time to the next sprint to account for uncertainty
B.Mandate that the team must collaborate more by pairing on all tasks
C.Coach the product owner on techniques for refining the product backlog and writing clear user stories
D.Coach the team on self-organization and effective collaboration techniques
E.Facilitate a retrospective focused on identifying root causes of the velocity drop
AnswersC, D, E

Improving backlog quality helps reduce ambiguity.

Why this answer

Options A, B, and D are correct. Facilitating a retrospective (A) allows the team to discuss issues openly. Coaching the team on self-organization (B) helps them improve collaboration.

Coaching the product owner on backlog refinement (D) addresses the requirements clarity issue. Option C is incorrect because adding buffer contradicts agile principles. Option E is incorrect because mandating collaboration is not effective and violates self-organization.

623
MCQhard

A project manager discovers that a team member has been working overtime for weeks to meet a deadline. The team member appears stressed and burnt out. The project manager is concerned about the team member's well-being and the sustainability of the project. What should the project manager do?

A.Increase the project budget to hire additional help immediately
B.Warn the team member that overtime is not sustainable and require them to stop
C.Ignore the situation as long as deadlines are met
D.Schedule a private meeting to discuss the workload, express concern, and explore options for support or reprioritization
AnswerD

Empathy and support align with servant leadership.

Why this answer

Option A is correct because servant leadership involves caring for team members' well-being. Having an empathetic conversation to understand the situation and offer support is the first step. Option B is confrontational.

Option C ignores the issue. Option D may not address the root cause.

624
MCQmedium

During a sprint planning meeting, the product owner wants to add a high-priority user story that the team believes is too large to complete in one sprint. What should the team do?

A.Accept the story and work overtime to complete it
B.Ask the product owner to attend the daily standups for this sprint only
C.Work with the product owner to break the story down into smaller, manageable pieces
D.Refuse to accept the story because it is too large
AnswerC

Agile teams collaborate to refine user stories into sprint-sized chunks.

Why this answer

Option B is correct because the team should collaborate with the product owner to break down the story. Option A is wrong because the product owner can add to the backlog but the team estimates capacity. Option C is wrong because accepting without planning leads to overcommitment.

Option D is wrong because the product owner can attend but the team needs to plan.

625
MCQhard

Your agile team has been consistently delivering in each sprint, but the product owner is concerned because the customer's needs have changed and some completed features may no longer be valuable. The project uses fixed-price contract. What should you do?

A.Work with the product owner to reprioritize the remaining backlog and submit a change request to modify the scope
B.Continue with the current sprint plan since the contract is fixed-price
C.Advise the product owner to accept the current features and add new ones in a separate project
D.Stop the project and renegotiate the contract with the customer
AnswerA

Reprioritizing within the contract framework and formalizing changes via change control aligns with PMI.

Why this answer

In a fixed-price contract, changes must go through change control to adjust scope, schedule, and cost. The PM should facilitate a discussion about reprioritizing the backlog and submit a change request if needed.

626
Multi-Selectmedium

During a project, a new regulation is enacted that requires additional compliance testing. The project is in the execution phase. Which THREE actions should the project manager take?

Select 3 answers
A.Ignore the regulation because it was not in the original project plan.
B.Update the risk register with the new regulatory requirement as a threat.
C.Communicate the impact of the new regulation to stakeholders.
D.Submit a change request to include the compliance testing in the project scope.
E.Instruct the team to start compliance testing immediately without formal approval.
AnswersB, C, D

The new regulation is a risk that should be documented and assessed.

Why this answer

The PM should update the risk register to reflect the new compliance risk, submit a change request to incorporate the testing, and communicate the impact to stakeholders. Ignoring the regulation or proceeding without change control would be incorrect.

627
Multi-Selectmedium

A new regulatory requirement has been introduced that affects your project's deliverables. The requirement must be implemented within two months. Your project is currently in the execution phase. Which THREE actions should you take?

Select 3 answers
A.Update the project management plan and baselines after approval.
B.Ask the team to implement the change without documentation to save time.
C.Ignore the requirement until the next project phase.
D.Submit a change request to incorporate the regulatory requirement.
E.Analyze the impact of the new requirement on scope, schedule, and budget.
AnswersA, D, E

Approved changes must be reflected in the project documents.

Why this answer

Since the requirement is mandatory, you must assess its impact, submit a change request to incorporate it, and update the project management plan accordingly. Ignoring or delaying is not acceptable.

628
MCQmedium

An executive stakeholder has been bypassing you and giving direct instructions to your team, causing confusion and scope creep. What should you do FIRST?

A.Instruct the team to ignore any instructions from the stakeholder
B.Meet with the stakeholder to discuss the issue and reinforce the project's communication management plan
C.Update the stakeholder engagement plan without informing the stakeholder
D.Escalate the issue to the project sponsor immediately
AnswerB

Direct, respectful communication clarifies roles and expectations.

Why this answer

Option B is correct because the first step in resolving stakeholder interference is to address the issue directly with the stakeholder through a meeting, reinforcing the communication management plan. This plan defines how information flows, including who can give instructions to the team, and is a key tool in managing stakeholder expectations and preventing scope creep. By discussing the issue, you can clarify roles, re-establish agreed-upon channels, and avoid further confusion without escalating prematurely.

Exam trap

The trap here is that candidates often choose to escalate immediately (Option D) or take a confrontational approach (Option A), failing to recognize that the PM should first attempt to resolve the issue through direct communication as outlined in the communication management plan.

How to eliminate wrong answers

Option A is wrong because instructing the team to ignore the stakeholder directly violates the principle of stakeholder engagement and could damage the relationship; it also ignores the need to address the root cause through communication. Option C is wrong because updating the stakeholder engagement plan without informing the stakeholder is a passive, non-collaborative action that fails to resolve the conflict and may lead to further misalignment. Option D is wrong because escalating to the sponsor immediately bypasses the opportunity to resolve the issue at the stakeholder level, which is a more direct and less disruptive approach; escalation should be a later step if the meeting fails.

629
MCQeasy

Your project is halfway through execution, and the earned value analysis shows CPI = 0.85 and SPI = 0.90. You have used 60% of the budget. What is the most likely interpretation of these metrics?

A.The project is under budget and ahead of schedule
B.The project is over budget and behind schedule
C.The project is under budget but behind schedule
D.The project is over budget but ahead of schedule
AnswerB

CPI < 1 means cost overrun; SPI < 1 means schedule delay.

Why this answer

CPI < 1 indicates cost overrun (spending more than planned for work accomplished). SPI < 1 indicates schedule delay (accomplished less than planned). Together they suggest the project is both over budget and behind schedule.

Option A correctly states this. Option B is reversed. Options C and D are incorrect.

630
MCQeasy

During project execution, you discover that a key vendor will not be able to deliver a critical component on time, which will delay the project by two weeks. The vendor was selected based on the procurement plan. What should you do FIRST?

A.Initiate a change request to replace the vendor with a new one.
B.Immediately escalate the issue to senior management and request intervention.
C.Contact the vendor to understand the reason for the delay and explore options to expedite delivery.
D.Update the project schedule and continue working on other tasks.
AnswerC

The PM should first work with the vendor to find a solution and then communicate the impact to stakeholders.

Why this answer

The PM should communicate the delay to stakeholders as soon as possible to manage expectations and seek resolution. This is proactive and aligns with PMI's emphasis on communication.

631
MCQeasy

You are managing a software development project using a hybrid approach. During a sprint review, the customer expresses satisfaction but requests a small additional feature that was not in the original backlog. The team believes it can be completed in two days without affecting the critical path. What should you do first?

A.Submit a change request to the change control board for evaluation and approval.
B.Ask the team to implement the feature and document it as a scope change later.
C.Inform the customer that no changes are allowed after the sprint review.
D.Approve the request since it is small and won't affect the schedule.
AnswerA

All changes must go through the Integrated Change Control process to assess impact and obtain formal approval.

Why this answer

According to PMI, any change to scope must go through the change control process. Even if the change seems small, it requires formal evaluation and approval to prevent scope creep and ensure all impacts are considered.

632
Multi-Selecthard

A project manager is assigned to a troubled project. The team is divided into two factions: one supports a technical solution A, the other solution B. The conflict is causing delays. The project manager wants to resolve this using a collaborative approach. Which THREE actions should the project manager take?

Select 3 answers
A.Bring in a neutral external expert to evaluate both options
B.Make the final decision based on your own expertise to save time
C.Ask the team to focus on project objectives rather than personal preferences
D.Implement both solutions in parallel to satisfy both sides
E.Facilitate a meeting where both factions present their arguments with data and evidence
AnswersA, C, E

An impartial expert can provide an objective assessment and help break the deadlock.

Why this answer

Option A is correct because bringing in a neutral external expert aligns with the collaborative approach the project manager wants to use. The expert can objectively evaluate both technical solutions A and B based on data and evidence, helping to de-escalate the conflict without taking sides. This fosters a collaborative environment by focusing on facts rather than personal biases, which is essential for resolving the delay-causing faction dispute.

Exam trap

The trap here is that candidates may confuse 'collaborative approach' with 'consensus at any cost' and incorrectly choose Option D (implementing both solutions) as a way to satisfy both sides, but this ignores the practical constraints of project resources and the need for a single, optimal technical solution.

633
MCQeasy

Your project is using a predictive approach. A key vendor has informed you that they will be unable to deliver a critical component on time, which could delay the project by three weeks. You have identified this risk in the risk register. What should you do first?

A.Escalate the issue to the project sponsor immediately without taking any action
B.Update the risk register and continue monitoring, as the risk was expected
C.Ask the team to find a workaround without consulting the risk register
D.Implement the risk response plan that was documented in the risk register
AnswerD

PMI recommends executing the planned response when a risk occurs.

Why this answer

Option A is correct: Since the risk is in the register, a response plan exists. The PM should implement the planned response. Option B escalates prematurely, C updates without action, D ignores the issue.

634
MCQmedium

Your project team is distributed across four countries, and you notice that communication is breaking down, leading to misunderstandings and rework. The team members are not using the collaboration tools effectively. What should the project manager do FIRST?

A.Create a team charter that outlines communication norms, tool usage, and meeting schedules.
B.Replace the current collaboration tools with more user-friendly software.
C.Assign a communication lead in each location to facilitate information flow.
D.Mandate daily video calls for all team members to improve communication.
AnswerA

A team charter sets clear expectations and is a best practice for virtual teams.

Why this answer

The first step in addressing communication breakdowns is to establish clear expectations and norms. A team charter defines how the team will communicate, which tools to use, and meeting schedules, aligning the distributed team on a shared framework. This proactive approach prevents misunderstandings and rework by setting ground rules before investing in new tools or roles.

Exam trap

The trap here is that candidates often jump to a tactical solution (like replacing tools or adding roles) instead of first establishing a shared framework for communication, which is a core principle of the PMP's 'People' domain.

How to eliminate wrong answers

Option B is wrong because replacing tools without first defining how they should be used does not address the root cause of ineffective usage; the team may misuse new tools similarly. Option C is wrong because assigning communication leads adds organizational overhead and may create silos, rather than fostering direct collaboration and shared responsibility across the team. Option D is wrong because mandating daily video calls can lead to meeting fatigue and may not be practical across time zones; it imposes a rigid solution without first understanding the team's specific communication needs.

635
MCQmedium

During a project retrospective, the team identifies several obstacles that are slowing them down, including unclear requirements and lack of access to a testing environment. As a servant leader, what should you do?

A.Document the obstacles and review them at the next retrospective
B.Prioritize the obstacles and include them in the project risk register
C.Ask the team to resolve the obstacles themselves
D.Work with the team and relevant stakeholders to remove the obstacles
AnswerD

Servant leadership involves actively removing impediments.

Why this answer

Option D is correct because, as a servant leader, your primary responsibility is to remove impediments that hinder the team's progress. By working directly with the team and relevant stakeholders to address unclear requirements and lack of access to a testing environment, you enable the team to maintain velocity and focus on delivering value. This aligns with the PMI's focus on empowering teams through proactive obstacle removal rather than deferring or delegating the issue.

Exam trap

The trap here is that candidates may confuse the servant leader role with a passive facilitator (Option A) or incorrectly apply risk management (Option B), failing to recognize that immediate impediment removal is a core duty, not a deferred or delegated task.

How to eliminate wrong answers

Option A is wrong because documenting obstacles and reviewing them at the next retrospective delays resolution, which violates the servant leader's duty to remove impediments promptly and can lead to continued productivity loss. Option B is wrong because obstacles identified during a retrospective are not risks—they are current blockers—and adding them to the risk register misapplies risk management processes, which deal with uncertain future events, not known present issues. Option C is wrong because asking the team to resolve the obstacles themselves abdicates the servant leader's responsibility to facilitate and support the team, especially when the obstacles (e.g., lack of testing environment) likely require stakeholder authority or resources beyond the team's control.

636
MCQeasy

In a hybrid project, the project sponsor asks you to skip the testing phase to meet the deadline. The product is critical for an upcoming trade show. What should you do?

A.Tell the sponsor that testing is mandatory and cannot be skipped
B.Explain the risks of skipping testing and propose reducing the scope of testing to high-risk areas only
C.Skip testing as requested to meet the deadline
D.Ask the quality assurance manager to decide
AnswerB

The PM should communicate risks and collaborate with the sponsor to find a balanced solution that maintains essential quality.

Why this answer

Option B is correct because the PM should explain the risks of skipping testing and propose alternatives that balance quality and schedule. Option A is wrong because skipping testing may lead to defects and reputational damage. Option C is wrong because the PM is responsible for quality and should not simply accept the request.

Option D is wrong because it does not address the sponsor's concern.

637
MCQmedium

During a hybrid project, the product owner frequently bypasses you and gives direct instructions to the development team. The team is confused about priorities, and scope creep is occurring. What should you do FIRST?

A.Speak privately with the product owner to explain the impact on the team and request that instructions go through you
B.Tell the team to ignore instructions from the product owner
C.Escalate to the project sponsor for resolution
D.Update the team charter to include a communication protocol
AnswerA

A private conversation allows the PM to address the issue professionally and reinforce the project manager's role.

Why this answer

Option A is correct because the first step in resolving a conflict between the product owner and the development team is to have a private, respectful conversation with the product owner. This allows you to explain the negative impact of bypassing you—such as team confusion, priority misalignment, and scope creep—and request that all instructions be routed through you to maintain the agreed-upon workflow and protect the team's focus.

Exam trap

The trap here is that candidates often choose to escalate (Option C) immediately, forgetting that the PM should first attempt to resolve the conflict directly with the stakeholder before involving higher authorities.

How to eliminate wrong answers

Option B is wrong because telling the team to ignore the product owner outright escalates the conflict, undermines the product owner's authority, and violates the principle of servant leadership; it does not address the root cause of the communication breakdown. Option C is wrong because escalating to the sponsor is premature; you should first attempt to resolve the issue directly with the product owner, as the sponsor is a higher authority and should only be involved after direct negotiation fails. Option D is wrong because updating the team charter to include a communication protocol is a corrective action that should come after the initial conversation; it is not the first step and does not immediately address the existing confusion and scope creep.

638
MCQmedium

A team member has been consistently missing deadlines for the past three sprints. Their work quality is also declining. You have had informal conversations with them, but the problem persists. What is the BEST next step for the project manager?

A.Escalate the issue to human resources to initiate a replacement process
B.Schedule a private meeting to discuss the performance issues, identify underlying causes, and agree on an improvement plan
C.Reassign the team member to less critical tasks to minimize impact
D.Ignore the issue for now and hope the team member improves on their own
AnswerB

A formal performance discussion with a plan is appropriate to address declining performance.

Why this answer

Option B is correct because the PMBOK Guide emphasizes addressing performance issues through direct, collaborative communication. A private meeting allows the project manager to explore root causes (e.g., skill gaps, personal challenges, or unclear requirements) and co-create a performance improvement plan, which aligns with the 'Manage Team' process and the principle of servant leadership.

Exam trap

The trap here is that candidates may choose Option A (escalation) or Option C (reassignment) because they seem like decisive actions, but the PMP exam prioritizes collaborative problem-solving and coaching over immediate escalation or task shuffling.

How to eliminate wrong answers

Option A is wrong because escalating to HR for replacement is premature without first attempting to resolve the issue through coaching and a formal improvement plan; it bypasses the project manager's responsibility to manage the team. Option C is wrong because reassigning to less critical tasks avoids addressing the root cause and may demotivate the team member, failing to develop their skills or resolve the underlying problem. Option D is wrong because ignoring the issue violates the project manager's duty to proactively manage team performance and risks further degradation of deliverables and team morale.

639
MCQmedium

Your project is using a predictive approach to build a mobile app. During testing, the team discovers a critical security vulnerability that was not identified during planning. Fixing it will require two additional weeks and $50,000, which is within the contingency reserve. What should you do NEXT?

A.Document the vulnerability in the issue log and proceed without fixing it.
B.Submit a change request to use the contingency reserve for the fix.
C.Inform the sponsor and ask for approval to use the contingency reserve.
D.Use the contingency reserve to fix the vulnerability immediately.
AnswerB

Following the change control process ensures proper governance.

Why this answer

Option B is correct because the contingency reserve is intended for such risks; using it requires a change request. Option A is incorrect because the contingency reserve should be used through formal process. Option C is incorrect as approval is needed.

Option D is incorrect; the PM cannot authorize use of contingency reserves without following the plan.

640
MCQhard

You are managing a pharmaceutical research project that is subject to strict regulatory compliance. Mid-project, a new regulation requires additional testing that will add 4 weeks to the schedule and $50,000 in costs. The sponsor is anxious about the delay. What should you do FIRST?

A.Submit a change request with the impact analysis to the change control board for approval
B.Instruct the team to begin the additional testing immediately to ensure compliance
C.Inform the sponsor that the project will be delayed and request more budget
D.Update the risk register and issue log to reflect the new regulation
AnswerA

All changes must go through integrated change control; the PM documents the impact and seeks approval.

Why this answer

Option C is correct because the change control process must be followed for any scope change. The PM should assess the impact and submit a change request for formal approval.

641
MCQmedium

You are managing a project to deploy a new customer relationship management (CRM) system. During user acceptance testing, the quality assurance team identifies several critical defects that must be fixed before go-live. The project is already behind schedule. What should the project manager do NEXT?

A.Prioritize fixing the critical defects and update the project schedule and stakeholders on the new timeline
B.Escalate the issue to the project sponsor for a decision on whether to delay
C.Proceed with go-live and fix defects in a later release
D.Ask the team to work overtime to fix defects without changing the go-live date
AnswerA

Critical defects must be resolved; the PM should plan accordingly and communicate the impact.

Why this answer

Option B is correct because quality is a constraint; fixing critical defects is necessary. The PM should reassess the schedule and communicate impacts to stakeholders.

642
MCQeasy

During a sprint retrospective, the team identifies that the daily standup meetings are running too long and are not focused. They want to improve the effectiveness of the standups. What should the scrum master do?

A.Cancel standup meetings and replace them with written status reports
B.Shorten the standup to 5 minutes and enforce strict time limits
C.Ask the team to propose improvements and agree on a new format for the standup
D.Escalate the issue to the project sponsor for guidance
AnswerC

The scrum master facilitates the team's self-organization and continuous improvement.

Why this answer

The scrum master should facilitate the team in finding a solution that works for them. Coaching the team to keep the standup time-boxed and focused aligns with agile principles.

643
MCQmedium

You are managing a software development project using a hybrid approach. During a sprint review, the customer is delighted with the progress but requests a new feature that would require significant rework of the current sprint's deliverable. The feature is not in the backlog. What should you do FIRST?

A.Submit a change request, assess the impact on schedule and cost, and seek approval from the change control board
B.Add the feature to the product backlog and prioritize it for the next sprint
C.Inform the customer that no changes can be made at this stage
D.Work with the team to incorporate the feature immediately to maintain customer satisfaction
AnswerA

This follows the Integrated Change Control process, which is the correct PMI approach.

Why this answer

Per PMI, any change to scope must go through the formal change control process. The project manager must assess the impact and obtain approval before proceeding. Ignoring the request or implementing it without approval violates the change management plan.

644
Multi-Selecthard

You are managing a hybrid project with a co-located core team and remote subject matter experts. Two senior developers argue daily about the technical approach for a critical module. The conflict is delaying sprint planning and affecting team morale. Which TWO actions should you take first?

Select 2 answers
A.Reassign one developer to a different module to reduce interaction
B.Facilitate a private meeting between the two developers to understand their perspectives and guide them toward a resolution
C.Ignore the conflict and hope it resolves on its own
D.Escalate the issue to the project sponsor for a decision
E.Review and reinforce the team charter with the team, emphasizing agreed-upon behavioral norms
AnswersB, E

Direct conflict resolution is a core PM responsibility and aligns with servant leadership.

Why this answer

Option A is correct because addressing the conflict directly is essential. Option D is correct because a team charter establishes ground rules for behavior. Option B is wrong because reassigning the senior developers may not address root cause.

Option C is wrong as it avoids the issue. Option E is wrong because escalating without resolution attempts is premature. (Note: correct answers are A and D)

645
MCQmedium

During a project, an executive stakeholder bypasses the project manager and directly instructs a team member to add a new feature. The team member is already overloaded. What should the project manager do FIRST?

A.Instruct the team member to follow the executive's order to maintain good relations.
B.Escalate the issue to the sponsor and request intervention.
C.Speak with the executive stakeholder privately to explain the change control process and the impact of the request.
D.Update the issue log and continue with the original plan.
AnswerC

The PM should address the issue directly with the stakeholder, reinforcing the need to follow formal processes.

Why this answer

Option C is correct because the project manager must first address the unauthorized change directly with the executive stakeholder, explaining the formal change control process and the impact on scope, schedule, and resources. This aligns with the PMBOK Guide's principle of managing stakeholder expectations and protecting the project from uncontrolled scope creep, which is a key technical aspect of project integration management.

Exam trap

The trap here is that candidates may choose Option B (escalation) because they think the executive's authority requires immediate higher-level intervention, but the PMP exam emphasizes that the project manager should first attempt to resolve the issue directly with the stakeholder using communication and process explanation before escalating.

How to eliminate wrong answers

Option A is wrong because instructing the team member to follow the executive's order bypasses the change control process, violates the project manager's authority, and risks schedule and budget overruns due to unapproved work. Option B is wrong because escalating to the sponsor should be a later step if the stakeholder refuses to follow the process; it is not the first action and may be seen as premature escalation without attempting direct resolution. Option D is wrong because updating the issue log and continuing with the original plan ignores the unauthorized instruction, leaving the team member conflicted and the project exposed to undisclosed scope changes and resource overload.

646
MCQmedium

In an agile project, the team has been working on the same product backlog for several sprints. During sprint planning, the product owner introduces a new high-priority user story that will require the team to reprioritize existing work. What is the BEST approach?

A.Reject the new story because the sprint has already started
B.Put the new story in the product backlog for a future sprint
C.Add the new story to the sprint backlog and ask the team to work overtime to complete everything
D.Discuss the new story with the team and the product owner, and if accepted, remove a lower-priority story of equivalent size
AnswerD

This respects the team's capacity and allows for reprioritization within the sprint.

Why this answer

In agile, the product owner can change priorities, but the team should assess the impact on the sprint goal and capacity. The best approach is to discuss the new story and its priority, and then adjust the sprint backlog accordingly, possibly removing lower-priority items.

647
Multi-Selectmedium

A project manager is defining the benefits management plan for a new product launch. The company's strategy includes expanding into emerging markets. Which TWO elements must be included in the benefits management plan to align with the company's strategy?

Select 2 answers
A.The business case justifying the project
B.Timeline for realizing benefits
C.Target benefits (e.g., market share increase)
D.The project's strategic objectives
E.The project scope statement
AnswersB, C

The timeline for realizing benefits is a required element of the benefits management plan.

Why this answer

The benefits management plan must include a timeline for realizing benefits (Option B) to ensure that the expected value from the product launch in emerging markets is achieved within a defined period, aligning with the company's strategic expansion. Target benefits such as market share increase (Option C) are also required to quantify the specific outcomes that support the strategy, providing measurable criteria for success.

Exam trap

The trap here is that candidates confuse the benefits management plan with the business case or project charter, mistakenly including strategic objectives or scope elements that are not part of the benefits realization process.

648
Matchingmedium

Match each project management process group to its primary purpose.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Define a new project or phase

Establish scope, objectives, and course of action

Complete work defined in the project management plan

Track, review, and regulate progress and performance

Finalize all activities to formally close the project

Why these pairings

These are the five process groups as defined in the PMBOK Guide.

649
MCQhard

You are the project manager for a large construction project. An executive stakeholder has been bypassing you and directly giving instructions to the site supervisor to add extra features. The supervisor complied, and now the project is experiencing scope creep. The changes have not been formally approved. What should the project manager do first?

A.Schedule a meeting with the executive stakeholder to explain the impact of the unauthorized changes and request that all change requests go through the formal process.
B.Update the project management plan to include the new features and adjust the budget and schedule accordingly.
C.Direct the site supervisor to stop all work and revert the changes.
D.Issue a change order retroactively to document the changes.
AnswerA

Communicating and reinforcing the process is the correct first step.

Why this answer

The PM should address the root cause by communicating with the executive stakeholder and reinforcing the change control process. Option B is correct because it addresses the behavior directly and professionally.

650
MCQmedium

During a project status meeting, a stakeholder requests a change that would improve the product but significantly impact the critical path. The project manager has not yet evaluated the change. What should the project manager do?

A.Document the change request, assess the impact, and submit it to the change control board for approval
B.Accept the change to satisfy the stakeholder and update the project plan immediately
C.Reject the change because it impacts the critical path and would delay the project
D.Inform the stakeholder that the change will be considered after the current phase is complete
AnswerA

This follows the proper change management process.

Why this answer

The correct answer is A because the PMBOK Guide mandates that all change requests must be formally documented and assessed for impact on constraints like the critical path before any decision is made. Submitting the evaluated change to the Change Control Board (CCB) ensures proper governance and prevents unauthorized scope creep, even if the stakeholder is influential.

Exam trap

The trap here is that candidates may assume a change impacting the critical path should be automatically rejected, but the PMP exam emphasizes that all changes must be formally evaluated through the change control process before any decision is made.

How to eliminate wrong answers

Option B is wrong because accepting a change without evaluation violates the formal change control process and can lead to uncontrolled scope creep, budget overruns, and schedule delays. Option C is wrong because rejecting a change solely because it impacts the critical path ignores the project manager's duty to objectively assess the change's value and potential trade-offs (e.g., fast-tracking or crashing). Option D is wrong because deferring the change without documentation or assessment is not a valid process; all change requests must be captured and processed through the defined change control system, regardless of timing.

651
MCQmedium

You are a project manager overseeing a 12-month ERP implementation. During sprint 6 of 20, the product owner informs you that a key stakeholder wants to add a new reporting module that was not in the original scope. The team estimates this would add 3 weeks to the schedule. What should you do FIRST?

A.Add the requirement to the product backlog and let the team address it in a future sprint without formal approval
B.Ask the team to begin work on the module immediately to accommodate the stakeholder
C.Inform the stakeholder that no changes can be made once the project has started
D.Submit a change request through the Integrated Change Control process and assess the impact on scope, schedule, and cost
AnswerD

PMI requires all scope changes to go through Integrated Change Control. The PM must document, assess impact, and obtain approval before proceeding.

Why this answer

Option C is correct because PMI requires all scope changes to go through the Integrated Change Control process. The PM must evaluate the impact and obtain approval before any work begins. Option A is wrong because implementing the change without approval bypasses change control.

Option B is wrong because refusing outright without assessing impact is not the correct approach. Option D is wrong because telling the team to start work immediately violates the change control process.

652
MCQmedium

A project manager is leading a hybrid project where the team uses Scrum for development but has a fixed end date for regulatory compliance. Halfway through, a key vendor informs you that they will be unable to deliver a critical component on time. What should the project manager do FIRST?

A.Adjust the sprint backlog to deprioritize features dependent on the component
B.Analyze the schedule to determine the impact on the critical path and identify possible mitigation options
C.Escalate the issue immediately to the project sponsor and request additional budget
D.Initiate legal proceedings against the vendor for breach of contract
AnswerB

Impact analysis allows the PM to make informed decisions and propose alternatives.

Why this answer

In a hybrid project with a fixed regulatory deadline, the first step when a vendor fails to deliver a critical component is to analyze the schedule impact on the critical path and identify mitigation options. This aligns with the PMI approach of assessing the situation before escalating or making changes, ensuring the project manager maintains control and explores all feasible alternatives to meet the compliance date.

Exam trap

The trap here is that candidates often jump to escalation or immediate backlog adjustments without first analyzing the schedule impact, confusing the need for quick action with the correct first step of assessing the situation.

How to eliminate wrong answers

Option A is wrong because adjusting the sprint backlog to deprioritize features dependent on the component assumes the impact is limited to those features, but it may affect the critical path and regulatory compliance, and this action should be taken only after analyzing the schedule impact. Option C is wrong because escalating immediately to the sponsor and requesting additional budget bypasses the necessary analysis of schedule impact and mitigation options, which is premature and may not be needed if alternative solutions exist. Option D is wrong because initiating legal proceedings for breach of contract is a reactive, adversarial step that should be considered only after exhausting other options and understanding the full impact, as it can damage the vendor relationship and delay resolution.

653
Multi-Selecthard

Your project is in the execution phase when a key risk event from the risk register occurs: a critical team member resigns unexpectedly. You need to minimize the impact on the project. Which THREE actions should you take?

Select 3 answers
A.Inform the sponsor and ask for a project extension
B.Implement the planned risk response from the risk register
C.Arrange for knowledge transfer from the departing member before they leave
D.Reassign the departing member's tasks to other team members and adjust the schedule
E.Immediately hire a replacement with the same skills
AnswersB, C, D

The risk was identified, so a response plan should be executed.

Why this answer

Option B is correct because the risk register contains a pre-planned risk response for this identified risk event. Implementing that response is the most efficient and effective way to minimize impact, as it was designed and approved during risk planning. This aligns with the PMBOK Guide's guidance on executing risk responses during the execution phase.

Exam trap

The trap here is that candidates often confuse a reactive, ad-hoc response (like immediately hiring a replacement) with the proper, planned risk response, failing to recognize that the risk register already contains the approved action to take.

654
MCQmedium

During a daily standup, a developer mentions she is blocked because two senior engineers are in a heated argument about the technical approach for a critical feature. The disagreement has been ongoing for two days and is affecting the team's velocity. As the Scrum Master, what should you do?

A.Facilitate a meeting between the two engineers to help them reach a consensus, and involve other team members if needed
B.Decide on the technical approach yourself and assign tasks accordingly to unblock the team
C.Advise the developer to wait until the disagreement is resolved before proceeding
D.Escalate the issue to the project sponsor to resolve the technical disagreement
AnswerA

Facilitating conflict resolution is a key Scrum Master responsibility.

Why this answer

Option C is correct: The Scrum Master facilitates conflict resolution but does not impose a solution. Option A escalates without resolution attempt, B imposes a solution, D ignores the issue temporarily.

655
MCQeasy

You are managing a project where a team member consistently misses deadlines. This has caused frustration among other team members and is affecting the project schedule. What should you do FIRST?

A.Reassign the team member's tasks to other team members
B.Speak with the team member privately to understand the root cause and offer support
C.Remove the team member from the project and request a replacement
D.Document the issue in the issue log and escalate to the functional manager
AnswerB

Addressing performance issues through direct communication and support is the recommended first step.

Why this answer

The PM should first have a private conversation with the team member to understand the reasons behind the missed deadlines. This aligns with PMI's emphasis on addressing performance issues through communication and understanding before taking formal action.

656
MCQhard

Your hybrid project uses a fixed-price contract with a vendor. The vendor notifies you that they cannot deliver a critical component on time due to a labor shortage. What should you do FIRST?

A.Escalate to the project sponsor for a decision
B.Immediately find a replacement vendor
C.Accept the delay and adjust the project schedule
D.Review the procurement contract to understand terms, penalties, and remedies
AnswerD

The contract defines the rights and obligations; review it first before taking action.

Why this answer

The contract is the governing document; the PM should review it to understand remedies and obligations.

657
MCQmedium

During a construction project, you discover that a critical supplier will not be able to deliver steel beams on time due to a labor strike. This risk was identified and listed in the risk register with a planned response of 'accept.' However, the delay will cause a 2-week slip in the critical path. What should you do?

A.Activate the fallback plan to mitigate the delay by fast-tracking subsequent activities
B.Do nothing since the risk was accepted, and proceed with the current plan
C.Escalate the issue to the project sponsor immediately to request additional resources
D.Inform stakeholders of the delay and implement the risk response plan of acceptance while monitoring for secondary risks
AnswerD

The correct action is to implement the planned response (accept) and communicate. The PM should also update the schedule and monitor secondary risks.

Why this answer

Option B is correct because the risk has occurred, and the PM must implement the planned response (accept), but also communicate the impact to stakeholders. Option A is wrong because accepting does not mean doing nothing; you still need to communicate. Option C is wrong because the risk was accepted, so escalating is not appropriate.

Option D is wrong because the risk was accepted, so activating a fallback plan is not necessary unless the response plan included one.

658
MCQmedium

In a hybrid project, the product owner wants to add a high-priority feature to the current sprint, but the team has already committed to the sprint backlog. The product owner insists it is critical for the upcoming release. What should the project manager do?

A.Escalate the request to the steering committee to force the change
B.Allow the team to swap the new feature for an equivalent amount of existing work
C.Ask the team to add the feature to the current sprint and work overtime
D.Explain to the product owner that the current sprint is committed and the feature can be added to the product backlog for the next sprint
AnswerD

Protecting the sprint commitment is key to agile; the feature can be prioritized for the next sprint.

Why this answer

In a hybrid project, the sprint backlog is a commitment made by the team for the current iteration. The project manager should protect the team from scope changes mid-sprint to maintain velocity and predictability. Option D is correct because it respects the sprint commitment and follows the agile principle of not changing the sprint backlog once it is set; the new feature is deferred to the product backlog for prioritization in the next sprint.

Exam trap

The trap here is that candidates may think swapping work (Option B) is a valid compromise, but the PMP exam emphasizes that the sprint backlog is a commitment and should not be altered mid-sprint, even by swapping equivalent work, because it disrupts the team's plan and can introduce unaccounted dependencies or risks.

How to eliminate wrong answers

Option A is wrong because escalating to the steering committee bypasses the product owner's authority and the team's self-management, and it is not a standard agile practice for handling mid-sprint changes. Option B is wrong because swapping work mid-sprint violates the sprint commitment and can disrupt the team's focus, flow, and any dependencies already established; it is not a recommended practice in hybrid or agile frameworks. Option C is wrong because asking the team to work overtime to add the feature is unsustainable, violates the principle of sustainable pace, and can lead to burnout and reduced quality; it is not a valid project management approach.

659
MCQhard

A project is using a predictive approach. The project manager discovers that a team member has been gold-plating by adding extra features to a deliverable without authorization. What should the project manager do FIRST?

A.Meet with the team member to discuss the issue and explain that only approved scope should be worked on.
B.Praise the team member for going above and beyond to satisfy the customer.
C.Submit a change request to formally approve the extra features.
D.Ignore it because it might improve customer satisfaction.
AnswerA

The PM should address the behavior directly, educating the team member on the importance of scope control.

Why this answer

Gold-plating is a violation of scope management. The PM must address the issue directly with the team member, explain why it's problematic, and reinforce the need to follow the defined scope. Corrective action may include removing the extra features.

660
Multi-Selecthard

A project manager is managing a project that is part of a program. The program manager asks the PM to provide benefits realization metrics. The project is currently in execution. Which THREE documents should the PM consult to determine the appropriate metrics?

Select 3 answers
A.Business case
B.Risk register
C.Project schedule
D.Benefits management plan
E.Project charter
AnswersA, D, E

The business case outlines the expected benefits and justification.

Why this answer

Option A, B, D are correct because the business case defines expected benefits, the benefits management plan defines metrics, and the project charter includes high-level benefits. Option C is not typically for metrics, E is for schedule.

661
MCQmedium

Your project is in the planning phase, and you need to develop the schedule. You have identified the activities and their dependencies. The team estimates that the project will take 12 months. However, the sponsor requires completion in 10 months. The project has a fixed deadline. What should you do FIRST?

A.Inform the sponsor that the deadline is unrealistic and request a 12-month schedule.
B.Reduce the project scope without formal change control to shorten the schedule.
C.Apply crashing or fast tracking to the critical path to try to meet the 10-month deadline.
D.Add more resources to all activities to reduce duration.
AnswerC

After analyzing the schedule, the PM should apply compression techniques if feasible, and then communicate the impacts to the sponsor.

Why this answer

Before applying schedule compression, the PM should first analyze the schedule to determine if compression is feasible and what the trade-offs are. The PM should then communicate with the sponsor about options and impacts. Option A is too quick to accept; Option D fails to explore options.

662
MCQmedium

Refer to the exhibit. A project team is using Terraform to provision infrastructure. The apply failed with the shown error. What is the MOST likely cause?

A.The instance type is not supported in the region.
B.The AWS region does not have a default VPC, or the VPC ID is not specified.
C.The AWS credentials are invalid.
D.The AMI ID specified is incorrect.
AnswerB

The error message indicates the default VPC is missing, and no VPC ID was provided.

Why this answer

The error message indicates that the subnet's VPC does not have an internet gateway attached, which is required for instances launched in a public subnet to communicate with the internet. Option B is correct because the default VPC typically has an internet gateway, but if it's missing or the VPC ID is not specified, Terraform cannot associate the subnet with a valid VPC, causing the apply to fail.

Exam trap

The trap here is that candidates often assume the error is about invalid credentials or AMI ID, but the specific subnet/VPC error message points directly to a missing internet gateway or VPC configuration issue.

How to eliminate wrong answers

Option A is wrong because the error message does not mention instance type or region support; it specifically references subnet and VPC configuration. Option C is wrong because invalid AWS credentials would produce an authentication error (e.g., 'AuthFailure' or 'UnauthorizedOperation'), not a VPC/subnet-related error. Option D is wrong because an incorrect AMI ID would result in an error like 'InvalidAMIID.NotFound' or 'InvalidAMIID.Malformed', not a subnet/VPC issue.

663
Multi-Selectmedium

You are the project manager for a large infrastructure project. The project is in the execution phase when a key vendor notifies you that they will be unable to deliver a critical component on time due to a supply chain disruption. Which TWO actions should you take?

Select 2 answers
A.Ignore the issue because the vendor will likely resolve it
B.Assess the impact on the project schedule and budget
C.Ask the team to work overtime to compensate for the delay
D.Immediately terminate the contract with the vendor and hire a new one
E.Evaluate alternative vendors or solutions to mitigate the delay
AnswersB, E

Understanding the impact is the first step in determining the appropriate response.

Why this answer

The correct actions are to assess the impact on the project schedule and budget, and to evaluate alternative vendors or solutions to mitigate the delay. Both are proactive steps aligned with PMI's risk management practices.

664
MCQmedium

A project is in the planning phase. The project manager wants to ensure that all stakeholders have a common understanding of the project scope. Which document should be used as the primary reference?

A.Project charter
B.Work breakdown structure
C.Schedule management plan
D.Project scope statement
AnswerD

It provides a detailed description of the project scope.

Why this answer

The project scope statement is the primary reference for ensuring all stakeholders have a common understanding of the project scope because it formally documents the project's boundaries, deliverables, acceptance criteria, and constraints. Unlike the project charter, which authorizes the project at a high level, the scope statement provides the detailed scope description needed during planning to align stakeholder expectations.

Exam trap

The trap here is that candidates confuse the project charter (which authorizes the project) with the project scope statement (which defines the detailed scope), leading them to select the charter when the question specifically asks for a common understanding of scope during planning.

How to eliminate wrong answers

Option A is wrong because the project charter is a high-level document that authorizes the project and names the project manager, but it does not contain the detailed scope description necessary for stakeholder alignment on scope specifics. Option B is wrong because the work breakdown structure (WBS) is a decomposition of the total scope into manageable work packages, but it is derived from the scope statement and does not itself define scope boundaries or acceptance criteria. Option C is wrong because the schedule management plan focuses on how the project schedule will be developed, monitored, and controlled, not on defining or communicating the project scope.

665
MCQmedium

You are managing a software development project using a hybrid approach. Midway through the project, the product owner requests a new feature that requires changing the scope and schedule. The team is currently working on a critical path activity. What should you do first?

A.Tell the product owner the request cannot be considered because the project is already underway
B.Add the new feature to the sprint backlog without formal approval
C.Submit a change request and evaluate the impact on scope, schedule, cost, and quality
D.Ask the team to start working on the feature immediately to save time
AnswerC

Following the change control process ensures all impacts are assessed and approved before changes are implemented.

Why this answer

Option B is correct because PMI requires all scope changes to go through the Integrated Change Control process to assess impact on scope, schedule, cost, and quality before approval. Option A is wrong because it bypasses change control. Option C is wrong because the team should not begin work without formal approval.

Option D is wrong because ignoring the request is not proactive.

666
MCQhard

You are the project manager for a large infrastructure project funded by a government grant that requires the project to deliver specific social benefits within three years. The project is currently in its second year, and a recent audit reveals that the project is on track to exceed its budget by 20% due to unexpected material cost increases. The grant terms stipulate that any cost overrun must be absorbed by the organization, not the grant. Additionally, the project benefits are measured based on the number of beneficiaries served, which is currently 70% of the target. The project sponsor is concerned that cutting costs may reduce the number of beneficiaries and jeopardize the grant conditions. The project team has identified two options: (1) reduce the scope of the project to stay within budget, which would lower the beneficiary count to 60% of target; or (2) request additional funding from the organization, but the CFO is reluctant because the project's return on investment is already marginal. What should the project manager do?

A.Conduct a benefits analysis to determine the minimum viable beneficiary count and then propose a revised plan that optimizes cost and benefits.
B.Escalate the issue to the steering committee for a decision.
C.Implement option 1 to control costs and then inform the sponsor of the reduced benefits.
D.Request additional funding from the CFO, emphasizing the risk of non-compliance.
AnswerA

This approach balances cost and benefits while respecting grant constraints.

Why this answer

Option A is correct because it aligns with the PMP's focus on benefits realization management. The project manager should first analyze the minimum beneficiary count required to satisfy grant conditions, then optimize the project plan to balance cost and benefits. This approach ensures data-driven decision-making before escalating or implementing scope changes, directly addressing the sponsor's concern about jeopardizing grant conditions.

Exam trap

The trap here is that candidates may choose to escalate (B) or unilaterally cut scope (C) without first performing the necessary analysis, failing to demonstrate proactive benefits management and stakeholder engagement as required by the PMP exam.

How to eliminate wrong answers

Option B is wrong because escalating to the steering committee without first conducting a benefits analysis abdicates the project manager's responsibility to analyze trade-offs and provide a recommended course of action. Option C is wrong because unilaterally implementing scope reduction without analyzing the minimum viable beneficiary count risks violating grant conditions and ignores the need for stakeholder buy-in. Option D is wrong because requesting additional funding without first exploring optimization options fails to demonstrate due diligence to the CFO and may be rejected due to the marginal ROI, leaving the project without a viable path forward.

667
MCQmedium

Your agile team's velocity has dropped for the third consecutive sprint. The team members report feeling burned out and demotivated due to excessive overtime. What should the project manager do first?

A.Increase the team size by adding new members to distribute the workload
B.Hold a retrospective focused on identifying the causes of overtime and discuss ways to improve sustainable pace
C.Reduce the scope of the next sprint to give the team a break
D.Inform the product owner that the team cannot commit to any new features until morale improves
AnswerB

The retrospective is the appropriate agile ceremony to address team issues and find solutions collaboratively.

Why this answer

Option B is correct because the first step when facing burnout and overtime is to hold a retrospective to identify root causes and discuss sustainable pace improvements. This aligns with the agile principle of continuous improvement and the PMP People domain focus on team motivation and well-being. Addressing the underlying issues before taking corrective actions ensures long-term productivity rather than temporary fixes.

Exam trap

PMI often tests the misconception that the immediate response to a velocity drop is to add resources or reduce scope, rather than first diagnosing the root cause through a team-led retrospective.

How to eliminate wrong answers

Option A is wrong because adding new members to an agile team often reduces velocity temporarily due to onboarding overhead and communication complexity, as per Brooks' Law, and does not address the root cause of burnout. Option C is wrong because reducing scope without understanding the causes of overtime may provide short-term relief but fails to prevent recurrence and does not involve the team in finding a sustainable solution. Option D is wrong because unilaterally informing the product owner without team input or data from a retrospective violates the collaborative and transparent nature of agile, and may damage stakeholder trust.

668
MCQmedium

Your agile project has seen a consistent drop in velocity over the last three sprints. The team is demotivated and blaming external dependencies. Retrospectives have not yielded actionable improvements. What should the project manager do FIRST?

A.Remove the team's external dependencies by negotiating with stakeholders.
B.Replace the scrum master with a more experienced one.
C.Facilitate a root cause analysis with the team to identify underlying issues and create an action plan.
D.Increase the sprint duration to give the team more time.
AnswerC

This is the proactive, collaborative approach to address the problem systematically.

Why this answer

Option C is correct because the first step when facing a consistent drop in velocity and team demotivation is to facilitate a root cause analysis with the team. This aligns with the PMP's focus on servant leadership and empowering the team to identify and solve their own problems, rather than imposing external solutions. The retrospective has failed to produce actionable improvements, so a deeper, facilitated analysis is needed to uncover the true underlying issues, which may include but are not limited to external dependencies.

Exam trap

The trap here is that candidates assume the obvious symptom (external dependencies) is the root cause and jump to negotiating them away (Option A), rather than first facilitating a team-led investigation to uncover all contributing factors.

How to eliminate wrong answers

Option A is wrong because removing external dependencies by negotiating with stakeholders is a potential solution, but it is not the first step; the project manager must first understand the root cause of the velocity drop, as the dependencies may not be the only or primary issue. Option B is wrong because replacing the scrum master assumes the scrum master is the problem, which is a blame-oriented approach that violates the agile principle of self-organizing teams and does not address the systemic issues causing demotivation. Option D is wrong because increasing sprint duration is a process change that treats the symptom (low velocity) without addressing the root cause, and it may reduce team accountability and feedback frequency, worsening the problem over time.

669
MCQmedium

A project is running 15% over budget at its midpoint. The project manager determines that the variance is due to unexpected price increases in raw materials. The project sponsor asks the project manager to reduce the project scope to bring costs back in line. What should the project manager do first?

A.Submit a change request to reduce scope and assess the impact on the project.
B.Instruct the team to reduce scope immediately.
C.Update the risk register and continue as planned.
D.Ask the sponsor for additional budget.
AnswerA

Why this answer

The correct answer is to submit a change request to formally propose the scope reduction. This follows the change control process. Option A is reactive and may affect quality.

Option B is speculative without analysis. Option D is not the first step.

670
Multi-Selecteasy

A risk event that was identified in the risk register has occurred. The risk response plan involves implementing a contingency plan. Which TWO actions should you take?

Select 2 answers
A.Submit a change request to initiate the contingency plan
B.Develop a new risk response plan from scratch
C.Update the risk register with the actual outcome and actions taken
D.Wait to see if the risk impact materializes further before acting
E.Implement the contingency plan as defined in the risk register
AnswersC, E

Lessons learned and updates are essential.

Why this answer

Option A is correct: implementing the contingency plan is the planned response. Option D is correct: updating the risk register documents the event. Option B is wrong because developing a new plan is unnecessary if one exists.

Option C is wrong because a change request is not needed for contingency plans. Option E is wrong because waiting is not proactive.

671
MCQhard

Your project is a large infrastructure build. You have completed the planning phase, but the sponsor has put pressure on you to start construction before all approvals are obtained. The schedule is tight, and any delay could result in penalties. What should the project manager do?

A.Begin construction on non-critical activities while waiting for approvals
B.Explain the risks to the sponsor and refuse to start until approvals are obtained
C.Document the sponsor's request and begin work
D.Proceed as requested by the sponsor
AnswerB

The PM should communicate risks and adhere to proper process.

Why this answer

Option D is correct. The PM must not proceed without proper approvals due to compliance and risk. Proceeding could lead to legal issues.

Option A is wrong because it bypasses approvals. Option B is wrong because the PM should not ignore the sponsor. Option C is wrong because documentation alone does not mitigate the risk.

672
MCQeasy

During a daily standup, a developer mentions she is blocked by a dependency from another team. The issue was not previously identified. As the project manager, what is the BEST action?

A.Remove the dependency by reassigning the work to a different developer.
B.Ask the developer to find a workaround and report back tomorrow.
C.Tell the developer to escalate the issue to the other team's manager directly.
D.Add the blocker to the issue log and work with the other team to resolve it.
AnswerD

Issues should be logged and managed proactively.

Why this answer

The PM should ensure the issue is documented and addressed. Option A is correct because the issue log is the proper tool. Option B delays; Option C is not the PM's role; Option D bypasses documentation.

673
MCQmedium

You are the project manager for a software development project using a hybrid approach. During a sprint review, the product owner requests a change that would add a new feature to the current release. The team estimates it will take two additional sprints. What should you do first?

A.Ask the team to start working on the new feature immediately to meet the stakeholder's needs
B.Submit a change request through the Integrated Change Control process to assess the impact on scope, schedule, cost, and quality
C.Explain that no changes can be made after the sprint review to maintain the schedule
D.Add the feature to the backlog and prioritize it for the next release without further analysis
AnswerB

PMI mandates that all changes be evaluated through formal change control before implementation.

Why this answer

Option D is correct because PMI requires all changes to go through Integrated Change Control to evaluate impact on scope, schedule, cost, and quality before approval. Option A bypasses formal control. Option B rejects without analysis.

Option C ignores governance.

674
Multi-Selectmedium

Your project is experiencing scope creep due to informal change requests from stakeholders. Which TWO actions should you take to address this?

Select 2 answers
A.Review the change management plan with stakeholders and remind them of the formal change control process
B.Document all requests in the issue log and assess them for potential change requests
C.Tell the project team to reject any work not approved by you
D.Ignore informal requests until a formal change request is submitted
E.Ask the project sponsor to intervene and stop stakeholders from making requests
AnswersA, B

Reinforcing the process educates stakeholders.

Why this answer

Options B and D are correct. Option B reinforces the change control process. Option D ensures documentation.

Option A is wrong because the PM should communicate with stakeholders, not just the team. Option C is wrong because the sponsor is not the first point of contact. Option E is wrong because ignoring requests is not proactive.

675
Multi-Selectmedium

You are a project manager for a software development project using Scrum. The product owner has been pressuring the team to increase velocity and deliver more features per sprint. The team feels overwhelmed and quality has started to suffer. Which TWO actions should the project manager take to address this situation?

Select 2 answers
A.Involve the team in sprint planning to ensure they commit to a realistic amount of work.
B.Ask the team to work overtime to meet the product owner's expectations.
C.Encourage the team to reduce testing to save time.
D.Add more team members to the project to increase capacity.
E.Facilitate a meeting between the product owner and the team to discuss velocity and sustainable pace.
AnswersA, E

Self-organization and realistic commitments are key agile principles.

Why this answer

The correct actions are to facilitate a discussion between the product owner and the team about sustainable pace and to involve the team in estimating and planning. These empower the team and ensure realistic commitments.

Page 8

Page 9 of 12

Page 10