Step 1: Statement of Work (SOW), Step 2: Procurement Documents (e.g., RFP), Step 3: Evaluation of Proposals, Step 4: Contract Signing, Step 5: Contract Administration and Closure
Procurement follows: SOW, documents, evaluation, contract signing, and administration/closure.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Step 1: Statement of Work (SOW), Step 2: Procurement Documents (e.g., RFP), Step 3: Evaluation of Proposals, Step 4: Contract Signing, Step 5: Contract Administration and Closure
Why this is correct
This sequence accurately reflects the logical and PMP-defined flow of the procurement process. It begins with defining the project's specific needs through the Statement of Work (SOW), which then informs the creation of procurement documents to solicit vendor proposals. Subsequent evaluation ensures the selection of the most suitable vendor, leading to formal contract signing. Finally, contract administration and closure manage the vendor's performance and formally conclude the agreement.
- ✗
Step 1: Procurement Documents, Step 2: Statement of Work, Step 3: Evaluation, Step 4: Contract Signing, Step 5: Contract Administration and Closure
Why it's wrong here
This order is incorrect because the Statement of Work (SOW) is a foundational document that must be established before creating procurement documents. The SOW precisely defines the scope of work, deliverables, and requirements, providing the essential basis from which detailed procurement documents, such as Requests for Proposal (RFPs), are developed to solicit accurate and relevant bids from potential sellers. Without a clear SOW, procurement documents lack the necessary specificity.
- ✗
Step 1: Evaluation, Step 2: Statement of Work, Step 3: Procurement Documents, Step 4: Contract Signing, Step 5: Contract Administration and Closure
Why it's wrong here
This sequence is fundamentally flawed as evaluation cannot precede the definition of the Statement of Work (SOW) or the creation of procurement documents. Evaluation involves assessing vendor proposals, which are direct responses to the requirements outlined in procurement documents. These documents, in turn, are derived from the SOW. Therefore, placing evaluation first bypasses the critical steps of defining needs and soliciting offers, rendering any subsequent evaluation impossible or meaningless.
- ✗
Step 1: Statement of Work, Step 2: Contract Signing, Step 3: Procurement Documents, Step 4: Evaluation, Step 5: Contract Administration and Closure
Why it's wrong here
This order is incorrect because contract signing must occur after the thorough evaluation of proposals and before contract administration begins. Signing a contract prematurely, before evaluating vendor submissions, bypasses the critical selection process designed to identify the most qualified and cost-effective seller. This sequence risks committing the project to a vendor without proper due diligence, potentially leading to suboptimal outcomes or increased project risks.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.