Courseiva
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

During a daily standup meeting, a team member mentions that they encountered a technical issue that will delay their task by two days. The project is time-sensitive. What should the scrum master do FIRST?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Remove the impediment by helping the team member find a solution or escalating if necessary

The scrum master's role is to remove impediments and help the team resolve issues. Addressing the block immediately aligns with agile principles.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Remove the impediment by helping the team member find a solution or escalating if necessary

    Why this is correct

    As a Scrum Master, the primary responsibility is to facilitate the team's progress by actively removing impediments. This involves collaborating with the team member to brainstorm potential solutions, leveraging organizational resources, or, if the issue is beyond the team's immediate control or influence, escalating it appropriately to management or relevant stakeholders. This proactive approach ensures the team can maintain focus and deliver value without unnecessary delays, embodying the servant leadership aspect of the role.

  • Ask the team member to work overtime to make up for the delay

    Why it's wrong here

    Asking a team member to work overtime is a reactive measure that fails to address the root cause of the impediment and can lead to burnout, decreased morale, and reduced quality over time. While sometimes necessary in extreme circumstances, it should never be the first response to an impediment. The Scrum Master's role is to remove obstacles and optimize the team's workflow, not to compensate for systemic issues with unsustainable practices.

  • Report the issue to the project sponsor

    Why it's wrong here

    Reporting the issue directly to the project sponsor is premature and bypasses the Scrum Master's immediate responsibility to resolve impediments at the team level first. Escalation to higher management or the sponsor should only occur after the Scrum Master has exhausted all reasonable avenues for resolution within their sphere of influence or if the impediment requires significant organizational change or resources beyond the team's capacity. Premature escalation can undermine team autonomy and the Scrum Master's problem-solving credibility.

  • Update the project schedule to reflect the two-day delay

    Why it's wrong here

    Updating the project schedule to reflect a two-day delay is a reactive administrative task that documents the impact of the impediment rather than addressing it. While schedule adjustments may eventually be necessary, the immediate priority for a Scrum Master is to mitigate or eliminate the impediment to prevent further delays and minimize its overall impact. Focusing on scheduling before problem-solving shifts attention from proactive resolution to merely recording consequences, which is not the most effective first action.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.