Sample questions
Project Management Professional PMP practice questions
Which THREE factors are most critical when selecting a conflict resolution technique for a project team? (Choose three.)
You are the project manager for a software development project using a hybrid approach. Two senior developers have a disagreement about the technical approach for a critical featur…
You are managing a hybrid project to develop a new mobile app. During the daily stand-up, two senior developers get into a heated argument about the technical approach for integrat…
A project is running 15% over budget at its midpoint. The project manager determines that the variance is due to unexpected price increases in raw materials. The project sponsor as…
Business Environment: strategy and project benefitsmediumSee the answer and why each option is right or wrong →You are managing a construction project using a traditional approach. The sponsor asks you to skip the quality inspection phase to save two weeks and meet an aggressive deadline. W…
A project manager is forming a new project team. The team includes members from diverse cultural backgrounds and different functional areas. Which team development model should the…
A stakeholder bypasses you and gives direct instructions to a team member to add a new report. The team member has already started working on it. What should the project manager do…
Your project is in the planning phase, and you are developing the risk management plan. Which THREE tools or techniques should you use to identify risks?
You are managing a large project with multiple stakeholders. One executive stakeholder has been bypassing you and giving direct instructions to the team, causing confusion. What sh…
Your project is behind schedule, and you need to compress the schedule. The critical path has been identified. What is the BEST schedule compression technique to use if you have ad…
Your agile team has been experiencing conflicts between two senior developers over technical approaches during sprint planning. The conflicts are causing delays and affecting team…
A new regulatory requirement has been discovered mid-project. The change will affect the project scope and schedule. Which TWO actions should the project manager take FIRST? (Choos…
Your agile project has been experiencing declining velocity over the last three sprints. During the retrospective, the team identifies that they are spending too much time on unpla…
You are the project manager for a team that recently transitioned to remote work. You notice that team morale is declining and collaboration has decreased. What is the BEST action…
You are managing a project in a virtual environment. A team member from a different time zone misses an important deadline because he was not aware of the priority due to a languag…
A project manager is developing a business case for a new project. Which TWO elements are essential for a strong business case?
Business Environment: strategy and project benefitseasySee the answer and why each option is right or wrong →You are managing a project where a team member consistently misses deadlines, affecting the team's velocity. You have had informal conversations with the team member, but the behav…
You are leading a virtual team across three time zones. During a video conference, you notice that one team member from a remote location has not spoken for the entire meeting. In…
You are managing a project that is running 15% over budget at the midpoint. The variance is due to higher-than-expected material costs. The sponsor is concerned about cost overruns…
A key vendor notifies you that they cannot deliver a critical component on time due to raw material shortages. This component is on the critical path and has no float. The vendor s…
A team member has been consistently late completing tasks. When you discuss this, they mention personal issues affecting their work. What should you do FIRST?
During a project, a risk you identified in the risk register occurs. Your response plan was to mitigate by purchasing backup equipment. However, you discover the backup equipment i…
Your agile team has a high turnover rate. New members are joining frequently, and the team's performance is declining. What should you do as a servant leader?
During the closure phase of a project, the customer is satisfied with the deliverables but refuses to sign the formal acceptance document, citing minor issues that were not part of…