Back to Project Management Professional PMP

PMI exam questions

Project Management Professional PMP practice test

Practise RAM questions covering identification, installation, speeds, dual-channel, and troubleshooting for the PMP exam.

892
practice questions
4
topics covered
PMP
exam code
PMI
vendor

Study modes

Three ways to study

Start with the Study Sheet to learn the material, switch to Practice Tests for active recall, then take a Mock Exam to simulate the real thing.

Study Sheet

All 892 questions with correct answers and explanations already visible. Read at your own pace — no time pressure.

Start reading →

Practice Test

Answer first, then see feedback and explanation. Tracks your score per session. Best for active recall and identifying weak areas.

Mock Exam

Full timed simulation with countdown. Answers hidden until the end. Includes all question types just like the real exam.

Start mock exam →

Study Sheet

All 892 PMP questions with answers

Every question in the bank, paginated 75 per page. Correct answers and full explanations are revealed upfront — ideal for first-pass learning and pre-exam review.

12 pages · 75 questions per page · 892 total

Related practice questions

Study PMP by topic

Topic pages go deep on individual concepts — each one covers a specific exam topic with questions, explanations, and study notes.

Courseiva uses original exam-style practice questions created for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps. Learn the difference →

Sample questions

Project Management Professional PMP practice questions

Start practice test

A project manager is leading a digital transformation initiative. Midway through the project, a new regulation is introduced that affects the product's compliance requirements. The project sponsor is concerned about potential scope creep and delays. What should the project manager do first?

Order the steps for closing a project or phase.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Sequence the steps for performing a qualitative risk analysis.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Arrange the steps for controlling project changes.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Order the steps for performing project quality assurance.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Order the steps for creating a Work Breakdown Structure (WBS).

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Order the steps for developing a project schedule.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5
Question 8mediummultiple choice
Read the full NAT/PAT explanation →

A project has a critical path of 120 days with a standard deviation of 5 days. The project sponsor wants to know the probability of completing the project within 130 days. Using the normal distribution, what is the approximate probability?

A project manager is using earned value management. At month 6 of a 12-month project, the EV is $50,000, PV is $60,000, and AC is $55,000. What is the cost performance index (CPI)?

Which TWO are inputs to the Control Schedule process? (Choose two.)

Which THREE are tools and techniques used in the Plan Risk Management process? (Choose three.)

A project manager is reviewing the schedule performance index (SPI) and cost performance index (CPI). The current values are SPI = 0.85 and CPI = 1.10. What is the most likely conclusion about the project?

During project execution, a key stakeholder requests a change that will increase the scope. The project manager follows the formal change control process. What is the first step the project manager should take?

Refer to the exhibit. The project's S3 bucket policy allows read access only from the internal IP range (10.0.0.0/8) and denies access if not using HTTPS. A developer reports that they can access the bucket from a machine with IP 10.0.0.5 using HTTPS. However, they cannot access it from a machine with IP 10.0.0.6 using HTTP. What is the most likely reason?

Exhibit

Refer to the exhibit.
```
{
  "Version": "2012-10-17",
  "Statement": [
    {
      "Effect": "Allow",
      "Action": ["s3:GetObject"],
      "Resource": "arn:aws:s3:::my-bucket/*",
      "Condition": {
        "IpAddress": {
          "aws:SourceIp": "10.0.0.0/8"
        }
      }
    },
    {
      "Effect": "Deny",
      "Action": "s3:*",
      "Resource": "arn:aws:s3:::my-bucket/*",
      "Condition": {
        "Bool": {
          "aws:SecureTransport": "false"
        }
      }
    }
  ]
}
```

Which TWO are key components of a project management plan? (Choose two.)

A project team is developing a new software feature. During a sprint review, the product owner requests a change that would increase the scope significantly. The team has already committed to the current sprint backlog. What is the BEST course of action for the project manager?

A project manager notices that the project's cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.1. What is the MOST likely cause of this situation?

A project is in the planning phase. The team has identified 50 risks. The project manager wants to prioritize risks for further analysis. Which tool or technique is BEST suited for this?

Which THREE of the following are common causes of project change requests?

A project is in the planning phase. The project manager wants to ensure that all stakeholders have a common understanding of the project scope. Which document should be used as the primary reference?

During a project, the team identifies a risk that could cause a major delay. The probability is high and the impact is high. The project manager decides to hire an external expert to manage the risk. Which risk response strategy is being used?

A project manager is managing a construction project and notices that the actual cost for concrete work is consistently 15% above budget. The earned value (EV) is $100,000, and the actual cost (AC) is $115,000. The project manager wants to estimate the cost at completion (EAC) if this trend continues. Which formula should the project manager use?

Question 23mediummultiple choice
Read the full NAT/PAT explanation →

A project manager is developing the project schedule and wants to determine the critical path. The activity network diagram shows multiple paths. Which technique should the project manager use?

A project team is in the performing stage of development. The project manager is leaving for a two-week vacation. What is the best way to ensure the team remains productive?

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

Exam question guide

How to use these PMP questions

Use these questions as active recall, not passive reading. Try the question first, review the answer choices, then open the explanation and connect the result back to the exam topic.

Quick answer

RAM tests your ability to identify, install, and troubleshoot memory types, speeds, and configurations for PCs.

Identifying DDR3 vs DDR4 vs DDR5 physical and electrical differences

Matching RAM speed (MHz) to motherboard and CPU support

Calculating total memory capacity from module size and slots

Troubleshooting common RAM errors like beep codes and blue screens

These PMP practice questions are part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style PMP questions with detailed explanations, topic-based practice, mock exams, readiness tracking, and study analytics.