You are managing a project using a hybrid approach. The project has a fixed-price contract with a customer. Midway through, the customer requests a significant scope change that would increase the contract value. The change request is approved by the CCB. What must the project manager do NEXT?
After a change request receives formal approval, the project manager's immediate and crucial responsibility is to integrate that approved change into the project management plan and its subsidiary baselines, such as scope, schedule, and cost. This ensures all project documentation accurately reflects the revised project direction. Following this essential update, communicating the approved change and its implications to all relevant stakeholders is vital for maintaining transparency, aligning expectations, and ensuring everyone operates from the most current and authoritative project information.
Why this answer
After a change is approved by the CCB, the project manager must first update the project management plan and baselines (scope, schedule, cost) to reflect the approved change, then communicate the change to all relevant stakeholders. This ensures that the project's performance measurement baselines are aligned with the new scope and cost, and that all stakeholders are aware of the updated plan before work begins. In a hybrid approach with a fixed-price contract, updating the contract is a separate procurement process that occurs after the baselines are updated and communicated.
Exam trap
The trap here is that candidates confuse the order of actions after CCB approval, often jumping to 'update the contract' (Option C) or 'start work immediately' (Option B), forgetting that the project management plan and baselines must be formally updated and communicated first to maintain control over the project's performance measurement.
How to eliminate wrong answers
Option A is wrong because informing the team and updating work packages is a subsequent step; the baselines and plan must be updated first to provide the official reference for the new work packages. Option B is wrong because proceeding immediately without updating baselines and communicating violates the integrated change control process and risks misalignment of scope, cost, and schedule. Option C is wrong because updating the contract is a procurement activity that typically follows the update of the project management plan and baselines, and starting work before the plan is updated and communicated is premature.