Courseiva
Process — Managing Technical AspectseasyMultiple ChoiceObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

During a sprint review, a key stakeholder expresses dissatisfaction with the product increment, stating that it does not meet their expectations. The team followed the acceptance criteria defined in the user stories. What should the project manager do NEXT?

⚠ Common exam trap

Many candidates choose Option C, thinking the product owner alone handles backlog changes, but the PM must actively facilitate the meeting to ensure the stakeholder's concerns are fully understood and addressed, not just delegated.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Schedule a meeting with the stakeholder and product owner to clarify expectations and refine the backlog

The project manager must facilitate a meeting between the stakeholder and the product owner to clarify expectations and refine the backlog. This aligns with the agile principle of continuous stakeholder engagement and ensures that acceptance criteria are updated to reflect true needs, preventing future mismatches.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Explain that the team delivered exactly what was agreed upon and the stakeholder should have raised concerns earlier

    Why it's wrong here

    This approach is confrontational and violates the PMP emphasis on collaborative stakeholder engagement. Blaming the stakeholder for not raising concerns earlier fails to acknowledge potential communication gaps or evolving needs, which are common in agile environments. A project manager should seek to understand the root cause of dissatisfaction and facilitate a solution, not deflect responsibility.

  • Schedule a meeting with the stakeholder and product owner to clarify expectations and refine the backlog

    Why this is correct

    This is the most appropriate response as it demonstrates proactive communication and collaborative problem-solving, core tenets of effective project management. By facilitating a direct meeting between the stakeholder and the Product Owner, the project manager ensures that expectations are clarified, feedback is directly incorporated, and the product backlog can be refined to reflect current needs and prevent future misalignment. This approach fosters trust and ensures value delivery.

  • Refer the stakeholder to the product owner to discuss changes for future sprints

    Why it's wrong here

    While the Product Owner is responsible for the product backlog, simply referring the stakeholder abdicates the Project Manager's responsibility for stakeholder engagement and issue resolution. The PM should actively facilitate communication, understand the nature of the dissatisfaction, and ensure a structured approach to addressing concerns, rather than delegating the entire interaction. This passive approach can lead to unresolved issues and further stakeholder disengagement.

  • Ask the team to redo the work to meet the stakeholder's unspoken needs

    Why it's wrong here

    Asking the team to redo work based on unspoken needs constitutes gold-plating, which is adding features or work beyond the agreed-upon scope and acceptance criteria. This wastes resources, extends timelines, and undermines the established definition of "done." A project manager must adhere to the agreed scope and facilitate a process to formally capture and prioritize new requirements, rather than making ad-hoc demands on the team.

About these practice questions

One of 800 original PMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.