PMP Process — Managing Technical Aspects Practice Question
Your project is 50% complete, and your earned value analysis shows: EV = $200,000, PV = $220,000, AC = $240,000. Based on this data, what is the most accurate assessment of the project's performance?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The project is over budget and behind schedule
CPI = EV/AC = 200,000/240,000 = 0.833 (over budget); SPI = EV/PV = 200,000/220,000 = 0.909 (behind schedule). The project is both over budget and behind schedule.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The project is over budget and behind schedule
Why this is correct
When the Cost Performance Index (CPI) is less than 1, it indicates that the actual cost incurred for the work performed is greater than the earned value, signifying that the project is currently over budget. Concurrently, if the Schedule Performance Index (SPI) is less than 1, it means the earned value is less than the planned value, indicating that the project has completed less work than planned by this point, thus running behind schedule. Therefore, both conditions together accurately describe a project that is over budget and behind schedule.
- ✗
The project is under budget and ahead of schedule
Why it's wrong here
This option is incorrect because both CPI and SPI being less than 1 directly contradict the claims of being under budget and ahead of schedule. A CPI value below 1 explicitly means the project is spending more than planned for the work accomplished, leading to an over-budget status. Similarly, an SPI value below 1 signifies that less work has been completed than scheduled, placing the project behind schedule, not ahead. Thus, the stated conditions are the opposite of what CPI < 1 and SPI < 1 imply.
- ✗
The project is over budget but ahead of schedule
Why it's wrong here
While a CPI less than 1 correctly indicates that the project is over budget, the assertion that it is 'ahead of schedule' is fundamentally incorrect when the Schedule Performance Index (SPI) is also less than 1. An SPI value below 1 specifically means that the project has not achieved the amount of work planned by the current date, signifying a behind-schedule status. Therefore, despite being over budget, the project cannot be simultaneously ahead of schedule under these earned value conditions.
- ✗
The project is under budget but behind schedule
Why it's wrong here
This option incorrectly states the budget status while accurately reflecting the schedule status. A Cost Performance Index (CPI) less than 1 unequivocally means that the project is spending more money than planned for the work completed, which translates to being over budget, not under budget. Although an SPI less than 1 correctly indicates the project is behind schedule, the misrepresentation of the budget status makes this entire statement false. The financial performance is clearly unfavorable based on the CPI.
Go deeper
Related to this question
About these practice questions
This PMP question is part of Courseiva's 800-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.