Question 703 of 892
Process — Managing Technical AspectsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is approximately 97.5%. This probability is derived from the normal distribution, where the critical path duration of 120 days serves as the mean, and the standard deviation is 5 days. Completing the project within 130 days represents a value exactly two standard deviations above the mean, since 130 minus 120 equals 10, and 10 divided by 5 equals 2. In a standard normal curve, roughly 95% of data falls within plus or minus two standard deviations, so the area to the left of the mean is 50%, and half of the 95% (which is 47.5%) lies between the mean and +2σ, giving a total of 97.5%. On the Project Management Professional PMP exam, this concept tests your ability to apply the PERT and standard deviation to calculate schedule probabilities, often appearing in earned value or risk analysis questions. A common trap is forgetting that the 95% rule covers both tails, so you must add only the upper half to the 50% baseline. Memory tip: “Two sigma up, 97.5%—just add half the bell curve’s cup.”

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project has a critical path of 120 days with a standard deviation of 5 days. The project sponsor wants to know the probability of completing the project within 130 days. Using the normal distribution, what is the approximate probability?

Question 1mediummultiple choice
Read the full NAT/PAT explanation →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

97.5%

The critical path duration is 120 days with a standard deviation of 5 days. Completing within 130 days is 2 standard deviations above the mean (130 - 120 = 10, 10/5 = 2). In a normal distribution, approximately 95% of data falls within ±2 standard deviations, so the probability of being at or below +2σ is 50% + (95%/2) = 97.5%.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 97.5%

    Why this is correct

    97.5% is the probability of completing at or below 2 standard deviations above the mean.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 95%

    Why it's wrong here

    95% is the probability within 2 standard deviations of the mean (both sides).

  • 84%

    Why it's wrong here

    84% corresponds to 1 standard deviation above the mean.

  • 68%

    Why it's wrong here

    68% is the probability within 1 standard deviation of the mean.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is confusing the probability of completing within a range (e.g., ±2σ = 95%) with the cumulative probability up to a single upper limit (+2σ = 97.5%), leading candidates to incorrectly select 95% instead of 97.5%.

Detailed technical explanation

How to think about this question

In project scheduling, the normal distribution assumption for critical path duration relies on the Central Limit Theorem, where the sum of independent activity durations approximates normality even if individual activities are not normally distributed. The standard deviation of the critical path is the square root of the sum of variances of activities on the critical path. For a 2-sigma upper tail, the exact probability from the Z-table is 97.72%, but 97.5% is the commonly used approximation for PMP exam purposes.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 97.5% — The critical path duration is 120 days with a standard deviation of 5 days. Completing within 130 days is 2 standard deviations above the mean (130 - 120 = 10, 10/5 = 2). In a normal distribution, approximately 95% of data falls within ±2 standard deviations, so the probability of being at or below +2σ is 50% + (95%/2) = 97.5%.

What should I do if I get this PMP question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.