Question 693 of 892
Process — Managing Technical AspectshardMultiple SelectObjective-mapped

Quick Answer

The correct actions are to provide a high-level release plan, educate the steering committee on agile principles, and use a rolling-wave planning approach for the Gantt chart. This reconciles phase-gate governance with agile by translating the product backlog’s iterative delivery into a timeline view that satisfies organizational review requirements without forcing detailed task-level commitments. On the PMP exam, this scenario tests your understanding of hybrid project governance, where you must balance agile flexibility with traditional stage gates—a common trap is assuming you must abandon agile for waterfall when governance demands a fixed schedule. Instead, remember that a release plan acts as the bridge: it shows milestones and high-level phases, not every sprint task. Memory tip: “Release plan, not task plan” to keep the gate open without losing agility.

PMP Process — Managing Technical Aspects Practice Question

This PMP practice question tests your understanding of process — managing technical aspects. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

In a hybrid project, the team uses Scrum but the organization requires detailed phase-gate reviews. During the gate review, the steering committee asks for a Gantt chart showing all tasks until project completion. The Scrum team only maintains a product backlog and sprint backlogs. Which THREE actions should you take?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Create a high-level milestone schedule for the remaining phases

Option A is correct because a high-level schedule can satisfy governance without detailed tasks. Option B is correct because educating on agile practices helps alignment. Option C is correct because the release plan provides a timeline view. Option D is wrong because switching to waterfall is not necessary. Option E is wrong because a detailed Gantt is not required for agile.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Convert the project to a pure waterfall approach to meet governance requirements

    Why it's wrong here

    Changing methodology is a major process change and not required.

  • Ask the team to create a detailed Gantt chart for all future sprints

    Why it's wrong here

    Detailed Gantt charts are not typical for agile and would be counterproductive.

  • Create a high-level milestone schedule for the remaining phases

    Why this is correct

    A milestone schedule provides necessary oversight without detailed tasking.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Provide a release plan with expected feature delivery dates by sprint

    Why this is correct

    A release plan shows when features will be delivered, satisfying the need for a timeline.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Educate the steering committee on agile principles and the value of iterative delivery

    Why this is correct

    Stakeholder education helps align expectations with the hybrid approach.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.

Detailed technical explanation

How to think about this question

This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.
  • Use explanations to understand the rule behind the answer.

TExam Day Tips

  • Underline the problem statement mentally.
  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PMP exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

Related practice questions

Related PMP practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PMP practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PMP question test?

Process — Managing Technical Aspects — This question tests Process — Managing Technical Aspects — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Create a high-level milestone schedule for the remaining phases — Option A is correct because a high-level schedule can satisfy governance without detailed tasks. Option B is correct because educating on agile practices helps alignment. Option C is correct because the release plan provides a timeline view. Option D is wrong because switching to waterfall is not necessary. Option E is wrong because a detailed Gantt is not required for agile.

What should I do if I get this PMP question wrong?

Identify which PMP exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on PMP

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In a hybrid project, the development team is self-organizing but a senior developer consistently misses sprint commitments. The product owner is frustrated. What should the project manager do first?

medium
  • A.Inform the product owner that the team self-manages and the issue will resolve itself
  • B.Reassign the developer to less critical tasks
  • C.Escalate the issue to the functional manager
  • D.Have a private conversation with the developer to understand challenges and offer support

Why D: Option A is correct because the PM should first understand the developer's challenges through a private conversation. Option B is wrong because escalation should be a last resort. Option C is wrong because reassignment may not address the root cause. Option D is wrong because the PM should assess the situation before reporting to stakeholders.

Last reviewed: Jun 21, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.