Courseiva
Process — Managing Technical AspectsmediumMultiple SelectObjective-mapped

PMP Process — Managing Technical Aspects Practice Question

You are managing a project that is experiencing scope creep. Several stakeholders have been requesting additional features informally. You want to bring the project under control. Which TWO actions should you take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Remind stakeholders that all changes must go through the formal change control process

To control scope creep, the PM should reinforce the change control process and ensure all requests are documented as change requests. Communicating with stakeholders about the impacts also helps.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ignore minor requests to avoid conflict

    Why it's wrong here

    Ignoring minor requests is a passive approach that fails to address the root cause of scope creep and can lead to stakeholder dissatisfaction and unmanaged expectations. This inaction does not prevent the scope from expanding informally, nor does it provide a mechanism for evaluating the impact of these requests on project baselines. A PMP must proactively manage scope, not avoid it, to maintain project control and achieve objectives.

  • Remind stakeholders that all changes must go through the formal change control process

    Why this is correct

    This is a crucial proactive step to manage scope creep by re-establishing project governance. By reminding stakeholders of the formal change control process, the project manager reinforces the established procedures for evaluating, approving, or rejecting proposed changes, thereby preventing further unauthorized additions to the project scope. This action directly supports maintaining the scope baseline and managing stakeholder expectations effectively.

  • Add the requests to the project backlog without approval

    Why it's wrong here

    Adding requests directly to the project backlog without formal approval bypasses the critical change control process, effectively condoning and institutionalizing scope creep. This action undermines the project's scope baseline and can lead to unmanaged increases in work, budget overruns, and schedule delays, as the impact of these additions has not been properly assessed or authorized. It creates an illusion of control while actually losing it.

  • Update the project management plan to reflect all informal requests

    Why it's wrong here

    Updating the Project Management Plan (PMP) to incorporate informal requests without them first undergoing the formal change control process is fundamentally incorrect and detrimental. This action legitimizes unauthorized scope changes, effectively making informal requests part of the official plan without proper impact analysis, stakeholder review, or formal approval from the Change Control Board (CCB). It compromises the integrity of the project baselines and the PMP itself.

  • Implement a change request for each informal request to formalize them

    Why this is correct

    For existing informal requests that have already surfaced, the most appropriate action is to initiate a formal change request for each one. This brings all proposed scope additions under the project's established change control process, allowing for proper evaluation of their impact on scope, schedule, cost, and quality. This approach ensures that even previously informal requests are properly reviewed, approved, or rejected, maintaining project governance and control.

About these practice questions

Courseiva writes every PMP question from scratch — 800 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMP exam.