During a project, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will add two weeks to the schedule but no additional cost. The change request is approved by the change control board (CCB). What should the project manager do next?
When a change is approved by the Change Control Board (CCB), it becomes a formal part of the project's authorized scope. The schedule baseline, a critical component of the project management plan, must be formally updated to reflect this new agreement, ensuring all future progress is measured against the revised plan. Subsequently, informing all relevant stakeholders is paramount for maintaining transparency, managing expectations, and ensuring everyone operates with the most current project information, aligning with the Communication Management Plan.
Why this answer
After the CCB approves a change that increases scope, the project manager must update the schedule baseline to reflect the approved two-week delay. This ensures the project plan remains accurate and serves as the basis for performance measurement. Informing all stakeholders of the approved change is a key communication requirement per the PMBOK Guide's Manage Communications process.
Exam trap
The trap here is that candidates often confuse the order of actions after CCB approval, mistakenly thinking that communicating to the team or updating the WBS should come before updating the schedule baseline, but the baseline must be formally revised first to maintain control over the project plan.
How to eliminate wrong answers
Option B is wrong because the change request has already been approved by the CCB, so the project manager cannot unilaterally reject it; doing so would violate the established change control process. Option C is wrong because instructing the team to begin work immediately bypasses the necessary updates to the project management plan (e.g., schedule baseline, WBS) and risks misalignment with the approved change. Option D is wrong because while updating the WBS is part of the process, it is not the immediate next step; the schedule baseline must be updated first to reflect the approved two-week delay, and communication to the project team should occur after the plan is updated.