CCNA PRINCE2 Practices Questions

75 of 674 questions · Page 4/9 · PRINCE2 Practices · Answers revealed

226
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board
B.Increase the project budget and continue
C.Continue and report in the next Highlight Report
D.Close the project as the Business Case is no longer viable
AnswerA

This is the correct response to a forecast tolerance breach.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

227
MCQmedium

Which of the following is a valid threat response in PRINCE2?

A.Enhance
B.Transfer
C.Reject
D.Exploit
AnswerB

Transfer is one of the five recommended threat responses.

Why this answer

PRINCE2 defines five threat responses: Avoid, Reduce, Fallback, Transfer, Accept, and Share. 'Transfer' is a valid response to shift the risk to a third party.

228
MCQhard

Which of the following correctly describes the relationship between the Change Authority and the Project Board?

A.The Change Authority is a role within the Project Support office
B.The Project Board and Change Authority are the same
C.The Project Board delegates authority to the Change Authority to approve changes within set limits
D.The Change Authority reports to the Project Manager
AnswerC

This is correct.

Why this answer

The Change Authority is delegated by the Project Board to approve changes within defined limits. Option B is correct.

229
MCQmedium

During the Managing a Stage Boundary process, the Project Manager reviews the Business Case. What is the primary purpose of this review?

A.To update the project schedule
B.To identify new stakeholders
C.To assign team managers to the next stage
D.To confirm that the project is still viable and to update the justification
AnswerD

The Business Case is reviewed to ensure continued viability before committing to the next stage.

Why this answer

The Business Case is reviewed at each stage boundary to confirm that the project remains viable and to update the justification before proceeding to the next stage.

230
MCQeasy

Which document is used by the Project Board to monitor progress at the end of a stage?

A.Highlight Report
B.Checkpoint Report
C.Exception Report
D.End Stage Report
AnswerD

The End Stage Report is used by the Project Board to decide on stage end.

Why this answer

The End Stage Report is provided by the Project Manager to the Project Board at the end of each stage to enable review.

231
MCQmedium

A risk has been identified that offers potential upside for the project. Which response should the project team consider to maximize the probability and impact of the risk?

A.Exploit
B.Accept
C.Avoid
D.Transfer
AnswerA

Exploit aims to make the opportunity happen to maximize benefits.

Why this answer

Opportunity responses include Exploit (maximize probability/impact), Enhance (increase), Share, and Reject.

232
MCQmedium

In the risk management procedure, which step includes evaluating the probability and impact of risks?

A.Implement
B.Identify
C.Assess
D.Plan
AnswerC

Assess evaluates probability and impact.

Why this answer

The 'assess' step includes evaluating probability and impact to prioritize risks.

233
MCQhard

In the context of PRINCE2 configuration management, what is the purpose of a 'baseline'?

A.To define the quality criteria for a product
B.To schedule the delivery of products
C.To provide a basis for change control by capturing the agreed state of a product
D.To record the current version of a product
AnswerC

Correct. A baseline is the agreed reference point against which changes are assessed.

Why this answer

A baseline is a snapshot of a configuration item's state at a specific point in time. It is used to provide a fixed reference for control and management, ensuring changes are made in a controlled manner.

234
MCQeasy

In PRINCE2, what is the purpose of the 'Managing Product Delivery' process?

A.To make key decisions and provide overall direction
B.To accept, execute, and deliver work packages
C.To control the work of the stage on a day-to-day basis
D.To plan the next stage and review the Business Case
AnswerB

Correct: Managing Product Delivery focuses on work package delivery.

Why this answer

Managing Product Delivery is the process by which the team manager accepts, executes, and delivers work packages. Option A describes Controlling a Stage (which focuses on overall stage control). Option B describes Managing a Stage Boundary.

Option D describes Directing a Project.

235
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Product descriptions
B.Quality criteria
C.Investment appraisal
D.Acceptance criteria
E.Expected benefits
AnswersC, E

Investment appraisal is a component of the Business Case.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Quality criteria and product descriptions belong to the Quality theme.

236
MCQeasy

What is the purpose of the Business Case practice?

A.To define the project's scope and deliverables
B.To establish mechanisms to judge whether the project is desirable, viable, and achievable
C.To monitor and control project progress
D.To assign roles and responsibilities to the project team
AnswerB

This is the core purpose of the Business Case practice.

Why this answer

The Business Case practice in PRINCE2 provides a mechanism to judge whether the project is desirable (benefits outweigh costs), viable (achievable within constraints), and achievable (feasible with available resources). It is the central justification for initiating and continuing the project, ensuring ongoing business justification throughout the project lifecycle.

Exam trap

PeopleCert often tests the distinction between the Business Case practice (which justifies the project) and the Plans practice (which defines how the project will be executed), leading candidates to confuse scope definition with business justification.

How to eliminate wrong answers

Option A is wrong because defining the project's scope and deliverables is the purpose of the Product Description and Project Plan, not the Business Case practice. Option C is wrong because monitoring and controlling project progress is the role of the Progress practice, which uses tolerances and reporting. Option D is wrong because assigning roles and responsibilities is the function of the Organization practice, which defines the project management team structure.

237
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To review the current stage and plan the next stage
B.To control the work within a stage
C.To close the project
D.To produce the Project Initiation Documentation
AnswerA

Managing a Stage Boundary prepares the End Stage Report and next Stage Plan for approval.

Why this answer

The purpose is to provide the Project Board with information to review current stage, approve next stage plan, and update the Business Case.

238
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Stage Plan
B.The Business Case
C.The Project Plan
D.The Project Initiation Documentation
AnswerD

The PID is the comprehensive document that defines the project and is the key output of Initiating a Project.

Why this answer

The Project Initiation Documentation (PID) is the key output of Initiating a Project. Option D is correct.

239
Multi-Selecteasy

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Problem
B.Threat
C.Request for Change
D.Quality review
E.Off-specification
AnswersC, E

An RFC is a type of issue.

Why this answer

PRINCE2 defines three issue types: Request for Change, Off-specification, and Problem/Concern. Option B and D are correct. Option A is a risk type, not an issue.

Option C is a general term. Option E is a quality activity.

240
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Senior User
C.The Project Manager
D.The Project Board
AnswerA

The Executive is the single point of accountability for the Business Case.

Why this answer

The Executive (Senior Responsible Owner) owns the Business Case and is ultimately responsible for its maintenance. The Project Manager may assist but is not the owner.

241
MCQeasy

Which register records all identified risks and their status?

A.Issue Register
B.Lessons Log
C.Quality Register
D.Risk Register
AnswerD

The Risk Register is the correct register for risks.

Why this answer

The Risk Register is the repository for all risk management information throughout the project.

242
MCQeasy

Which PRINCE2 principle emphasizes that a project should have continued business justification?

A.Manage by Stages
B.Learn from Experience
C.Continued Business Justification
D.Focus on Products
AnswerC

This principle ensures the project remains justified.

Why this answer

Continued Business Justification is one of the seven PRINCE2 principles, ensuring the project remains viable throughout.

243
Multi-Selectmedium

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Business Case
B.Risk Register
C.Benefits Review Plan
D.Project Plan
E.Project Brief
AnswersA, B, D

The Business Case is a key component of the PID.

Why this answer

The PID includes the Business Case, Project Plan, and Risk Register. The Project Brief is a predecessor document, and the Benefits Review Plan is a separate document.

244
MCQmedium

Which risk response is appropriate for a threat with high probability and high impact that cannot be reduced?

A.Accept
B.Avoid
C.Transfer
D.Fallback
AnswerD

Fallback provides a plan to deal with the risk if it occurs, suitable when reduction is not possible.

Why this answer

Fallback is used when a response plan is implemented only if the risk occurs, often after other responses have failed or are not feasible.

245
MCQmedium

What is the first step in the PRINCE2 recommended risk management procedure?

A.Plan
B.Assess
C.Implement
D.Identify
AnswerD

Identify is the first step.

Why this answer

The risk management procedure starts with 'Identify' risks, followed by Assess, Plan, Implement, and Communicate.

246
MCQmedium

What is the PRINCE2 definition of quality?

A.Customer satisfaction
B.Fit for purpose
C.Conformance to specification
D.Zero defects
AnswerB

PRINCE2 defines quality as fit for purpose.

Why this answer

PRINCE2 defines quality as 'fit for purpose', meaning the product must meet its stated requirements and satisfy user needs.

247
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.Project Manager
B.Project Support
C.Senior User
D.Executive
AnswerA

The Project Manager maintains the Business Case under the direction of the Executive.

Why this answer

The Project Manager is responsible for maintaining the Business Case as part of day-to-day management. The Executive (SRO) owns and approves it.

248
MCQmedium

Who is responsible for providing assurance that the project is being conducted properly?

A.Project Support
B.Team Manager
C.Project Board through Project Assurance
D.Project Manager
AnswerC

The Project Board delegates assurance to independent Project Assurance roles.

Why this answer

Project Assurance is an independent role from the Project Board, responsible for monitoring compliance with standards and providing objective oversight.

249
Multi-Selecthard

Which THREE of the following are components of the Project Initiation Documentation (PID)?

Select 3 answers
A.Highlight Report
B.Business Case
C.Risk Register
D.Project Plan
E.Checkpoint Report
AnswersB, C, D

The Business Case is a key component of the PID.

Why this answer

The PID includes the Project Plan, Business Case, and Risk Register (among others).

250
MCQhard

During a quality review, it is discovered that the acceptance criterion 'The system shall be compatible with Windows 10 and macOS' has been classified as 'Should' (i.e., a desirable but not essential criterion). Which action should be taken?

A.Remove the criterion from the Project Product Description.
B.Ignore the issue because the criterion is already documented.
C.Reclassify it as 'Must' to ensure delivery.
D.Seek confirmation from the customer that the classification is acceptable.
AnswerD

The customer should agree on the priority of acceptance criteria.

Why this answer

In PRINCE2, the classification of acceptance criteria (e.g., 'Must', 'Should', 'Could') is a customer decision. When a criterion classified as 'Should' is discovered during a quality review, the correct action is to seek confirmation from the customer that the classification is acceptable, as only the customer can decide whether a desirable criterion can be downgraded or reclassified. This ensures the project remains aligned with customer expectations and avoids unauthorized changes to the Project Product Description.

Exam trap

The trap here is that candidates may assume the project manager or quality review team has the authority to reclassify criteria, but PRINCE2 emphasizes that acceptance criteria are customer-defined and any change must be formally agreed with the customer.

How to eliminate wrong answers

Option A is wrong because removing the criterion from the Project Product Description without customer approval would be an unauthorized change, violating the change control process. Option B is wrong because ignoring the issue fails to address the potential misclassification, which could lead to customer dissatisfaction if the criterion is later expected to be delivered. Option C is wrong because reclassifying it as 'Must' without customer confirmation would be a unilateral decision that could increase scope and cost without agreement, breaking the principle of continued business justification.

251
MCQmedium

Which PRINCE2 principle is applied when a Project Manager escalates a forecast tolerance deviation to the Project Board?

A.Manage by stages
B.Focus on products
C.Manage by exception
D.Continued business justification
AnswerC

Correct. Escalating when tolerances are breached is management by exception.

Why this answer

Management by Exception means that deviations within tolerance are handled by the PM, but deviations forecast to exceed tolerance are escalated to the Board.

252
MCQmedium

A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

A.Close the project immediately as the Business Case is no longer viable
B.Increase the project budget to absorb the additional cost and continue with the current Stage Plan
C.Raise an Exception Report to the Project Board and await their direction before proceeding
D.Continue with the current Stage Plan and report the cost overrun in the next Highlight Report
AnswerC

This is the correct action per PRINCE2's management by exception.

Why this answer

When a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report to seek direction.

253
MCQmedium

Which document describes the quality criteria and acceptance methods for a product in PRINCE2?

A.Product Description
B.Quality Management Strategy
C.Project Product Description
D.Work Package
AnswerA

Each product has a Product Description defining its quality criteria and acceptance methods.

Why this answer

The Product Description defines the product's purpose, composition, quality criteria, and acceptance methods.

254
MCQmedium

Which role is responsible for approving the Project Plan?

A.Project Board
B.Executive
C.Senior User
D.Project Manager
AnswerA

The Project Board collectively approves the Project Plan.

Why this answer

The Project Plan is approved by the Project Board, as it sets the baseline for the project's scope, schedule, and cost.

255
MCQmedium

Which document describes the quality methods and tools to be used on the project?

A.Quality Management Approach
B.Project Plan
C.Product Description
D.Project Product Description
AnswerA

This document defines the quality methods, tools, and responsibilities for the project.

Why this answer

The Quality Management Approach defines how quality will be managed, including quality methods, tools, and responsibilities.

256
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To provide the Project Board with information to review the current stage and plan the next
B.To plan the next stage and update the Business Case
C.To control the work of a stage and manage issues
D.To authorize the project and approve the Project Initiation Documentation
AnswerA

This is the core purpose of Managing a Stage Boundary.

Why this answer

Managing a Stage Boundary provides the Project Board with sufficient information to review the current stage and plan the next stage, and to decide whether to continue the project.

257
Multi-Selectmedium

Which THREE of the following are threat responses defined in PRINCE2?

Select 3 answers
A.Enhance
B.Accept
C.Transfer
D.Avoid
E.Exploit
AnswersB, C, D

Accept is a valid threat response.

Why this answer

PRINCE2 defines six threat responses: Avoid, Reduce, Fallback, Transfer, Accept, and Share. Options A, C, and D are correct; Exploit and Enhance are opportunity responses.

258
MCQmedium

A project is in the Initiating a Project process and the Project Manager is preparing the Project Plan. Which technique is recommended by PRINCE2 for creating the Project Plan?

A.Work Breakdown Structure
B.Critical Path Analysis
C.Earned Value Management
D.Product-Based Planning
AnswerD

PRINCE2 recommends product-based planning, which starts with identifying products and dependencies.

Why this answer

PRINCE2 recommends product-based planning, which includes creating a Product Breakdown Structure (PBS) and Product Flow Diagram.

259
Multi-Selecthard

Which THREE of the following are correct statements about Project Assurance?

Select 3 answers
A.It is performed by the Project Manager
B.It can be delegated to individuals outside the project management team
C.It focuses only on financial aspects
D.It provides independent oversight of the project's progress and quality
E.It is the responsibility of the Project Board
AnswersB, D, E

Assurance can be delegated to independent people.

Why this answer

Project Assurance is independent, performed by Project Board members or delegates, and covers all aspects of the project.

260
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Executive
C.The Senior User
D.The Project Support
AnswerA

The Project Manager maintains the Business Case throughout the project.

Why this answer

In PRINCE2, the Project Manager is responsible for maintaining the Business Case throughout the project. This includes monitoring actual costs and benefits against the Business Case, updating it with any changes, and ensuring it remains viable. The Project Manager does not create the Business Case (that is the Executive's role) but is accountable for its ongoing maintenance and reporting.

Exam trap

PeopleCert often tests the distinction between 'owning' and 'maintaining' the Business Case, leading candidates to incorrectly select the Executive (who owns it) instead of the Project Manager (who maintains it).

How to eliminate wrong answers

Option B is wrong because the Executive is responsible for creating and approving the Business Case, not for its day-to-day maintenance; the Executive owns the Business Case at a strategic level but delegates maintenance to the Project Manager. Option C is wrong because the Senior User is responsible for specifying the benefits and ensuring the project delivers them, but does not maintain the Business Case document itself. Option D is wrong because Project Support provides administrative and advisory services to the Project Manager, but does not hold responsibility for maintaining the Business Case.

261
Multi-Selecthard

Which THREE of the following statements about the PRINCE2 principle 'Manage by Exception' are correct?

Select 3 answers
A.The Project Manager sets project tolerances for the Project Board
B.Tolerances are set for each management level
C.If a stage tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board
D.The Project Board sets stage tolerances for the Project Manager
E.Management by exception means that no reports are required unless a tolerance is exceeded
AnswersB, C, D

PRINCE2 defines tolerances at project, stage, and work package levels.

Why this answer

Options A, B, and D are correct. Manage by Exception means setting tolerances for each level and only escalating when they are exceeded. The Project Board sets stage tolerances for the PM.

The PM sets work package tolerances for team managers. Options C and E are false: the PM does not set project tolerances (Project Board does), and management by exception does not eliminate reporting — it defines when escalation is needed.

262
Multi-Selecthard

Which TWO of the following statements about the Quality Review technique are correct?

Select 2 answers
A.It is performed by the Project Board
B.It is a form of quality control
C.It assesses the viability of the Business Case
D.It is a structured review to identify defects in a product
E.It is used to test the product against its specification
AnswersB, D

Correct. Quality Review is a quality control technique.

Why this answer

The Quality Review technique involves a structured review of a product against its quality criteria. Option A is correct: the review identifies defects. Option D is correct: it is a form of quality control.

Option B is false: the review does not test; it is a review. Option C is false: it is not performed by the Project Board; it involves subject matter experts. Option E is false: the review is not about the Business Case; it's about products.

263
MCQhard

What is the difference between a risk owner and a risk actionee?

A.There is no difference; the terms are interchangeable
B.The risk owner is responsible for identifying the risk, while the risk actionee implements the response
C.The risk owner is accountable for the management of the risk, while the risk actionee performs specific actions
D.The risk owner is always a member of the Project Board, while the risk actionee is a team member
AnswerC

This correctly distinguishes accountability from execution.

Why this answer

In PRINCE2, the risk owner is accountable for the overall management of a risk, including monitoring and ensuring that appropriate responses are implemented. The risk actionee, on the other hand, is responsible for performing specific actions or tasks assigned as part of the risk response plan. Option C correctly captures this distinction between accountability and execution.

Exam trap

The trap here is that candidates confuse accountability with responsibility, assuming the risk owner does all the work, when in fact PRINCE2 separates these roles to ensure clear ownership and execution.

How to eliminate wrong answers

Option A is wrong because the terms are not interchangeable; PRINCE2 explicitly differentiates between the risk owner (accountable) and the risk actionee (responsible for specific actions). Option B is wrong because the risk owner is not responsible for identifying the risk (that is the risk identifier's role), and the risk actionee does not implement the entire response but only specific assigned actions. Option D is wrong because the risk owner is not always a member of the Project Board; they can be any individual with the authority to manage the risk, while the risk actionee is not limited to team members.

264
Multi-Selectmedium

Which TWO of the following are threat responses in PRINCE2?

Select 2 answers
A.Avoid
B.Exploit
C.Reduce
D.Share
E.Reject
AnswersA, C

Avoid is a threat response to eliminate the threat.

Why this answer

Avoid and Reduce are threat responses. Exploit and Share are opportunity responses, and Reject is also an opportunity response.

265
Multi-Selecthard

Which THREE of the following are characteristics of PRINCE2's product-based planning approach?

Select 3 answers
A.It uses a Product Breakdown Structure
B.It prioritises products based on their quality criteria
C.It creates a Product Flow Diagram
D.It creates Product Descriptions for each product
E.It starts by identifying activities and then determines products
AnswersA, C, D

PBS is a key technique.

Why this answer

Product-based planning focuses on defining products first, then activities. It includes Product Breakdown Structure, Product Flow Diagram, and Product Descriptions.

266
MCQmedium

Which document describes the quality management approach for the project, including the procedures to be used for quality assurance and quality control?

A.Project Product Description
B.Quality Management Approach
C.Quality Register
D.Product Description
AnswerB

This defines the project's approach to quality, including quality assurance and quality control procedures.

Why this answer

Option C is correct. The Quality Management Approach defines the project's approach to quality, including quality assurance and quality control procedures. Option A is incorrect because the Project Product Description describes the final product.

Option B is incorrect because the Product Description describes individual products. Option D is incorrect because the Quality Register records quality review results, not the approach.

267
Multi-Selecthard

Which THREE of the following are roles in the Project Management Team according to PRINCE2?

Select 3 answers
A.Steering Committee
B.Project Sponsor
C.Team Manager
D.Senior User
E.Project Manager
AnswersC, D, E

The Team Manager is a role within the project management team.

Why this answer

The PRINCE2 project management team includes the Executive, Senior User, Senior Supplier, Project Manager, Team Manager, Project Assurance, and Project Support. The Project Board consists of the Executive, Senior User, and Senior Supplier. 'Project Sponsor' is not a PRINCE2 role; 'Steering Committee' is not a PRINCE2 term.

268
MCQhard

Which of the following is a key difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to an agreed product, while an Off-specification identifies a product that does not meet its specification.
B.A Request for Change always has a cost and time impact, while an Off-specification never does.
C.A Request for Change is recorded in the Issue Register, while an Off-specification is recorded in the Risk Register.
D.A Request for Change does not require authorization, while an Off-specification does.
AnswerA

This correctly distinguishes the two types of issue.

Why this answer

Option D is correct. A Request for Change proposes a modification to an agreed product, while an Off-specification identifies that a product does not meet its specification. Option A is incorrect because both require authorization.

Option B is incorrect because both may involve cost and time impacts. Option C is incorrect because both are recorded in the Issue Register.

269
MCQmedium

The Project Board has set a cost tolerance of +/- 10% for a stage. The Project Manager forecasts that the stage will be completed 15% under budget. What should the Project Manager do?

A.Report the underrun in the next Highlight Report
B.Reallocate the surplus to other activities without informing the Project Board
C.Continue as planned since being under budget is beneficial
D.Raise an Exception Report to the Project Board
AnswerD

When a tolerance is forecast to be exceeded (even beneficial), an Exception Report is required.

Why this answer

If a forecast is within tolerance (under budget but within 10%?), actually 15% under is within the -10%? Wait: 15% under is outside the -10% tolerance. So it is an exception. The Project Manager must raise an Exception Report.

Option B is wrong because a Highlight Report is for regular reporting, not for exceptions. Option C is wrong because the PM cannot reallocate without authorization. Option D is wrong because exceeding tolerance requires escalation.

270
MCQhard

A project manager discovers that a product expected to be completed in the current stage does not meet its product description quality criteria. The project manager has already used the stage's change budget to address a similar issue. What should the project manager do?

A.Update the product description to match the delivered product
B.Request additional budget from the Project Board via an Exception Report
C.Accept the product as delivered and proceed to the next stage
D.Approve the rework using the remaining risk budget
AnswerB

When the change budget is exhausted, the project manager must escalate to the Project Board.

Why this answer

Since the change budget is exhausted, the project manager cannot approve further changes within their delegated authority. Therefore, they must escalate to the Project Board via an Exception Report.

271
MCQeasy

Which practice describes why the project is being done and ensures continued business justification?

A.Business Case
B.Progress
C.Plans
D.Risk
AnswerA

The Business Case practice provides the business justification for the project.

Why this answer

The Business Case practice is the correct answer because it is the PRINCE2 practice that specifically defines the reasons for initiating a project and ensures that the project remains desirable, viable, and achievable throughout its lifecycle. It provides the justification for continued investment by requiring regular review and update of the business justification, which is documented in the Business Case. Without a valid Business Case, the project should be stopped.

Exam trap

PeopleCert often tests the distinction between the Business Case practice and the Plans practice, as candidates may mistakenly think that the project's justification is derived from the project plan rather than from the Business Case document.

How to eliminate wrong answers

Option B (Progress) is wrong because the Progress practice focuses on monitoring and controlling the project's performance against plans, not on defining or justifying why the project is being done. Option C (Plans) is wrong because the Plans practice deals with defining the steps to deliver the project's products, not with providing the business justification for the project itself. Option D (Risk) is wrong because the Risk practice is concerned with identifying, assessing, and controlling uncertainties that could affect the project, not with establishing or maintaining the business case.

272
MCQhard

A project has identified a risk that could impact the project's schedule. The team decides to allocate extra resources to ensure the schedule is met despite the risk. Which risk response is being applied?

A.Reduce
B.Transfer
C.Accept
D.Avoid
AnswerA

Reduce involves actions to lower the probability or impact of a threat. Allocating extra resources reduces the impact on the schedule.

Why this answer

Allocating extra resources to ensure an opportunity is realized (or a threat is mitigated) is an 'enhance' response for opportunities. However, for threats, 'reduce' involves actions to lower probability or impact. The scenario describes a threat (schedule impact), and allocating extra resources reduces the impact; thus it is 'reduce'.

The question might be ambiguous, but the correct PRINCE2 term for threat is 'reduce'.

273
Multi-Selecthard

Which THREE of the following are elements of the PRINCE2 quality practice?

Select 3 answers
A.Quality Assurance
B.Configuration Management
C.Risk Management
D.Quality Control
E.Quality Planning
AnswersA, D, E

Quality Assurance ensures processes are followed.

Why this answer

The quality practice includes Quality Planning, Quality Control, and Quality Assurance. Configuration Management is part of the Change practice.

274
MCQhard

What is the difference between Project Assurance and Project Support?

A.Project Assurance provides independent oversight, while Project Support provides administrative services
B.Project Assurance is part of the Project Manager's team, while Project Support is independent
C.Project Assurance manages quality control, while Project Support manages the Risk Register
D.Project Assurance is only required for large projects, while Project Support is always required
AnswerA

This correctly distinguishes the two roles.

Why this answer

Option B is correct. Project Assurance provides independent oversight and is accountable to the Project Board, while Project Support provides administrative services to the Project Manager and team. Option A is wrong because Project Assurance is not part of the Project Manager's team.

Option C is wrong because both roles can exist in any project. Option D is wrong because Project Support is not responsible for quality control.

275
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Project Plan
B.Project Initiation Documentation
C.Risk Register
D.Project Brief
E.Business Case
AnswersB, E

The PID is the key output.

Why this answer

The PID and Business Case are refined and approved during Initiating a Project. The Project Brief is from Starting Up a Project, and the Risk Register is created during this process but not listed as a key output; it's part of the PID. However, the question asks for outputs, and both PID and Business Case are key outputs.

276
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.An Off-specification is something that should be provided but is not, while a Request for Change is a proposal to change a baseline
B.A Request for Change always requires a change budget, while an Off-specification does not
C.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
D.An Off-specification is recorded in the Risk Register, while a Request for Change is in the Issue Register
AnswerA

This correctly distinguishes the two.

Why this answer

A Request for Change is a proposed modification to a baseline, while an Off-specification is a failure to meet a requirement. Option B is correct.

277
Multi-Selectmedium

Which TWO statements about the Risk practice are correct?

Select 2 answers
A.The risk budget is used to fund the project's activities.
B.A risk owner must be identified for each risk.
C.Only threats are considered as risks.
D.The risk register is optional if the project is small.
E.The risk management approach defines how risks will be managed.
AnswersB, E

Each risk must have a risk owner who is responsible for managing the risk.

Why this answer

Option B is correct because PRINCE2 requires that each risk has a named risk owner who is accountable for managing that risk and implementing the planned responses. This ensures clear accountability and proactive risk management throughout the project lifecycle.

Exam trap

PeopleCert often tests the misconception that the risk budget can be used for general project activities, but PRINCE2 strictly reserves it for funding risk responses, not operational tasks.

278
MCQmedium

Which role is responsible for securing project funding and for the Business Case?

A.Executive
B.Project Manager
C.Senior User
D.Senior Supplier
AnswerA

The Executive is the single point of accountability for the Business Case.

Why this answer

The Executive (also known as Senior Responsible Owner) is accountable for the Business Case and securing funding.

279
MCQeasy

What is the definition of quality in PRINCE2?

A.The lowest cost to produce
B.Customer satisfaction
C.Fit for purpose
D.Zero defects
AnswerC

This is the correct definition: the product must be suitable for its intended use.

Why this answer

Option C is correct. PRINCE2 defines quality as 'fit for purpose' — the product must meet the needs of the user. Option A is wrong because zero defects is not the PRINCE2 definition.

Option B is wrong because quality is not about cost efficiency. Option D is wrong because customer satisfaction is a broader concept.

280
Multi-Selectmedium

Which THREE of the following are roles in the project management team?

Select 3 answers
A.Executive
B.Risk Actionee
C.Senior User
D.Change Authority
E.Project Manager
AnswersA, C, E

The Executive is a key role on the Project Board.

Why this answer

The project management team includes the Project Board (Executive, Senior User, Senior Supplier), Project Manager, Team Manager, and Project Assurance. Project Support is also a role but not part of the management team? Actually Project Support is a role. The three correct ones are Executive, Senior User, and Project Manager.

281
MCQmedium

In PRINCE2, what is the definition of quality?

A.Highest possible standard
B.Fit for purpose
C.Zero defects
D.Conformance to specification
AnswerB

The PRINCE2 definition of quality is 'fit for purpose'.

Why this answer

PRINCE2 defines quality as 'fit for purpose' — meeting agreed requirements and fulfilling its purpose.

282
MCQmedium

What is the purpose of the Risk Register?

A.To approve risk budgets
B.To report progress to stakeholders
C.To capture and track information about identified risks throughout the project
D.To record all decisions made by the Project Board
AnswerC

Correct: the Risk Register is used for recording and tracking risks.

Why this answer

The Risk Register records identified risks, their analysis, and planned responses.

283
MCQmedium

During the Managing Product Delivery process, the Team Manager delivers products to the Project Manager. What document authorizes the Team Manager to deliver the work?

A.Work Package
B.Project Plan
C.Stage Plan
D.Product Description
AnswerA

Correct. A Work Package authorizes the work for the Team Manager.

Why this answer

A Work Package is the document that authorizes the Team Manager to create one or more products. It contains details of the work to be done and constraints.

284
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To prepare an Exception Plan when tolerances are exceeded
C.To control the work of the current stage
D.To enable the Project Board to approve completion of the current stage and authorize the next stage
AnswerD

This is the key purpose: review and authorize the next stage.

Why this answer

This process provides the Project Board with information to decide whether to continue with the next stage, based on review of the current stage's performance and updated plans.

285
MCQeasy

Which practice defines the project management team structure?

A.Business Case
B.Plans
C.Progress
D.Organising
AnswerD

Correct.

Why this answer

The Organising practice defines the roles and responsibilities within the project management team.

286
Multi-Selectmedium

Which TWO of the following are components of a Product Description?

Select 2 answers
A.Lessons Report
B.Acceptance methods
C.Stage boundaries
D.Risk budget
E.Quality criteria
AnswersB, E

Acceptance methods describe how the product will be verified against its quality criteria.

Why this answer

Options B and D are correct. A Product Description includes quality criteria (B) and acceptance methods (D). The risk budget and stage boundaries are not part of a Product Description.

287
Multi-Selectmedium

Which TWO of the following are types of issues in PRINCE2?

Select 2 answers
A.Off-specification
B.Request for Change
C.Constraint
D.Opportunity
E.Risk
AnswersA, B

Why this answer

Issue types are: Request for Change, Off-specification, and Problem/Concern. Risk is not an issue; it is a separate practice.

288
Multi-Selectmedium

Which TWO of the following are valid tolerances in PRINCE2?

Select 2 answers
A.Benefit
B.Time
C.Resource
D.Cost
E.Budget
AnswersB, D

Time is one of the six tolerances.

Why this answer

In PRINCE2, tolerances are the permissible deviations from a plan without needing to escalate to the next management level. The six standard tolerances are Time, Cost, Quality, Scope, Risk, and Benefit. Time (B) and Cost (D) are explicitly defined as tolerances for managing stage and project plans.

Exam trap

The trap here is that candidates confuse 'Resource' (a management lever) with a formal tolerance, or think 'Budget' is the official term when PRINCE2 specifically uses 'Cost'.

289
Multi-Selecteasy

Which TWO of the following are types of tolerance that can be set in PRINCE2?

Select 2 answers
A.Change control approach
B.Quality management approach
C.Risk budget
D.Time
E.Cost
AnswersD, E

Time is one of the six PRINCE2 tolerances.

Why this answer

Options A and B are correct. The six tolerances in PRINCE2 are time, cost, quality, scope, risk, and benefits. Options C, D, and E are not standard PRINCE2 tolerances; they are management approaches or budgets.

290
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Expected benefits
B.Configuration item records
C.Major risks
D.Team structure
E.Product Breakdown Structure
AnswersA, C

Expected benefits are a key component of the Business Case.

Why this answer

The Business Case includes reasons, options, expected benefits, dis-benefits, timescale, costs, investment appraisal, and major risks. Expected benefits and major risks are two of these components.

291
MCQhard

In PRINCE2, what is the purpose of the Managing a Stage Boundary process?

A.To authorize the work for the next stage
B.To enable the Project Board to review the current stage, approve the next stage plan, and confirm continued business justification
C.To produce the End Project Report
D.To update the Project Plan with actual progress
AnswerB

This is the correct purpose of the Managing a Stage Boundary process.

Why this answer

The purpose is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

292
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Risk
B.Action Item
C.Lessons Learned
D.Off-specification
E.Request for Change
AnswersD, E

One of the three issue types.

Why this answer

The three issue types are Request for Change, Off-specification, and Problem/Concern.

293
Multi-Selectmedium

Which TWO of the following are opportunity responses in PRINCE2 risk management?

Select 2 answers
A.Exploit
B.Accept
C.Enhance
D.Transfer
E.Avoid
AnswersA, C

Exploit is an opportunity response.

Why this answer

Exploit and Enhance are opportunity responses. Avoid and Transfer are threat responses. Accept can be used for both.

294
MCQmedium

What is the purpose of the Product Breakdown Structure (PBS)?

A.To assign responsibilities to team members
B.To define quality criteria for each product
C.To identify the products to be produced and their relationships
D.To sequence activities in the Project Plan
AnswerC

The PBS provides an exhaustive list of all products in a hierarchical structure.

Why this answer

The PBS is a hierarchical diagram that identifies all products to be produced, decomposing the project product into its constituent parts.

295
MCQmedium

In PRINCE2, which plan is produced by the Project Manager to provide the Team Manager with details of the work to be done?

A.Exception Plan
B.Stage Plan
C.Team Plan
D.Project Plan
AnswerC

The Team Plan details the work to be done by a team.

Why this answer

Option C is correct because in PRINCE2, the Team Plan is produced by the Project Manager (or sometimes the Team Manager) to provide the Team Manager with detailed information about the work to be done at the team level. It is derived from the Stage Plan and focuses on the specific activities, resources, and timelines for a team's work package, ensuring alignment with the overall project objectives.

Exam trap

The trap here is that candidates often confuse the Team Plan with the Stage Plan, thinking the Stage Plan provides team-level details, but PRINCE2 explicitly separates these plans by audience and purpose, with the Team Plan being the only one specifically designed for the Team Manager's work instructions.

How to eliminate wrong answers

Option A is wrong because an Exception Plan is produced when a stage is forecast to exceed its tolerances, not to provide work details to a Team Manager. Option B is wrong because a Stage Plan is produced by the Project Manager for the Project Board to manage a stage, not to give detailed work instructions to a Team Manager. Option D is wrong because a Project Plan is the top-level plan covering the entire project, created by the Project Manager for the Project Board, and is too high-level for team-level work details.

296
Multi-Selectmedium

Which THREE of the following are risk responses for a threat?

Select 3 answers
A.Reduce
B.Avoid
C.Exploit
D.Transfer
E.Enhance
AnswersA, B, D

Reduce is a threat response.

Why this answer

The five threat responses are: avoid, reduce, transfer, accept, share. Fallback is not a separate response; it is part of a plan.

297
Multi-Selectmedium

Which TWO of the following are components of the Project Initiation Documentation (PID)?

Select 2 answers
A.Project Brief
B.Business Case
C.Project Plan
D.Checkpoint Report
E.Project Product Description
AnswersB, C

The Business Case is a core component of the PID.

Why this answer

The PID includes the Business Case, Project Plan, Project Approach, and other baselines. The Project Brief is an input to the PID, and the Project Product Description is a supporting document but not a core component of the PID itself. Correct: Business Case and Project Plan.

298
MCQeasy

In the Organising practice, which role is responsible for providing assurance that the project is being conducted correctly?

A.Team Manager
B.Project Assurance
C.Project Support
D.Project Manager
AnswerB

Project Assurance is independent and provides objective oversight.

Why this answer

Project Assurance is independent of the Project Manager and provides assurance to the Project Board.

299
MCQmedium

Which report does the Project Manager produce regularly to inform the Project Board of progress within a stage?

A.Highlight Report
B.End Stage Report
C.Checkpoint Report
D.Exception Report
AnswerA

The Highlight Report is sent from the Project Manager to the Project Board.

Why this answer

The Highlight Report is produced by the Project Manager at intervals defined in the Communication Management Approach to update the Project Board on progress.

300
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Project Manager
C.The Project Assurance
D.The Senior User
AnswerB

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager maintains the Business Case on behalf of the Executive. While the Executive owns it, the Project Manager is responsible for its day-to-day maintenance.

← PreviousPage 4 of 9 · 674 questions totalNext →

Ready to test yourself?

Try a timed practice session using only PRINCE2 Practices questions.