Courseiva

CCNA PRINCE2 Practices Questions

75 of 596 questions · Page 4/8 · PRINCE2 Practices · Answers revealed

226
Multi-Selecthard

Which TWO of the following statements about the Quality Review technique are correct?

Select 2 answers
A.It is performed by the Project Board
B.It is a form of quality control
C.It assesses the viability of the Business Case
D.It is a structured review to identify defects in a product
E.It is used to test the product against its specification
AnswersB, D

Correct. Quality Review is a quality control technique.

Why this answer

The Quality Review technique is a structured review of a product against its quality criteria to identify defects. Option B is correct because it is a form of quality control, ensuring the product meets requirements. Option D is correct as it describes the technique accurately as a structured review to find defects.

Option A is incorrect because the review is conducted by subject matter experts, not the Project Board. Option C is incorrect because viability of the Business Case is assessed separately, not through Quality Review. Option E is incorrect because testing against specification is a different activity; Quality Review is a review, not a test.

227
MCQhard

What is the difference between a risk owner and a risk actionee?

A.There is no difference; the terms are interchangeable
B.The risk owner is responsible for identifying the risk, while the risk actionee implements the response
C.The risk owner is accountable for the management of the risk, while the risk actionee performs specific actions
D.The risk owner is always a member of the Project Board, while the risk actionee is a team member
AnswerC

This correctly distinguishes accountability from execution.

Why this answer

In PRINCE2, the risk owner is accountable for the overall management of a risk, including monitoring and ensuring that appropriate responses are implemented. The risk actionee, on the other hand, is responsible for performing specific actions or tasks assigned as part of the risk response plan. Option C correctly captures this distinction between accountability and execution.

Exam trap

The trap here is that candidates confuse accountability with responsibility, assuming the risk owner does all the work, when in fact PRINCE2 separates these roles to ensure clear ownership and execution.

How to eliminate wrong answers

Option A is wrong because the terms are not interchangeable; PRINCE2 explicitly differentiates between the risk owner (accountable) and the risk actionee (responsible for specific actions). Option B is wrong because the risk owner is not responsible for identifying the risk (that is the risk identifier's role), and the risk actionee does not implement the entire response but only specific assigned actions. Option D is wrong because the risk owner is not always a member of the Project Board; they can be any individual with the authority to manage the risk, while the risk actionee is not limited to team members.

228
Multi-Selectmedium

Which TWO of the following are threat responses in PRINCE2?

Select 2 answers
A.Avoid
B.Exploit
C.Reduce
D.Share
E.Reject
AnswersA, C

Avoid is a valid threat response that removes the risk by adjusting the plan.

Why this answer

In PRINCE2, threat responses (for negative risks) are: Avoid (eliminate the threat by altering the plan), Reduce (lower the probability or impact), Fallback, Transfer, and Accept. From the options, 'Avoid' (A) and 'Reduce' (C) are threat responses. 'Exploit' (B) is an opportunity response. 'Reject' (E) is not a PRINCE2 term. 'Share' (D) is an opportunity response where the opportunity is shared with a third party to increase its chances; for threats, the equivalent is 'Transfer'. Therefore, Share is not a threat response.

Exam trap

PRINCE2 defines 'Share' as a response for opportunities only. Candidates often mistakenly select it as a threat response because of the similarity to 'Transfer' (the threat counterpart). Remember that 'Share' is never used for threats in PRINCE2.

229
Multi-Selecthard

Which THREE of the following are characteristics of PRINCE2's product-based planning approach?

Select 3 answers
A.It uses a Product Breakdown Structure
B.It prioritises products based on their quality criteria
C.It creates a Product Flow Diagram
D.It creates Product Descriptions for each product
E.It starts by identifying activities and then determines products
AnswersA, C, D

Correct. Product Breakdown Structure hierarchically decomposes all products.

Why this answer

The Product Breakdown Structure (PBS) is a key characteristic of PRINCE2's product-based planning approach. It provides a hierarchical decomposition of all products to be created, ensuring that the project's outputs are clearly defined before activities are planned. This aligns with PRINCE2's principle of focusing on products rather than activities.

Exam trap

The trap here is that candidates often confuse product-based planning with activity-based planning, mistakenly thinking that activities are identified first (Option E), or they incorrectly assume that quality criteria are used for prioritization (Option B) rather than for defining acceptance standards.

230
MCQmedium

Which document describes the quality management approach for the project, including the procedures to be used for quality assurance and quality control?

A.Project Product Description
B.Quality Management Approach
C.Quality Register
D.Product Description
AnswerB

This defines the project's approach to quality, including quality assurance and quality control procedures.

Why this answer

The Quality Management Approach defines the project's approach to quality, including quality assurance and quality control procedures. Option A is incorrect because the Project Product Description describes the final product. Option C is incorrect because the Quality Register records quality review results, not the approach.

Option D is incorrect because the Product Description describes individual products.

231
Multi-Selecthard

Which THREE of the following are roles in the Project Management Team according to PRINCE2?

Select 3 answers
A.Steering Committee
B.Project Sponsor
C.Team Manager
D.Senior User
E.Project Manager
AnswersC, D, E

The Team Manager is a role within the project management team.

Why this answer

The PRINCE2 project management team includes the Executive, Senior User, Senior Supplier, Project Manager, Team Manager, Project Assurance, and Project Support. The Project Board consists of the Executive, Senior User, and Senior Supplier. 'Project Sponsor' is not a PRINCE2 role; 'Steering Committee' is not a PRINCE2 term.

232
MCQhard

Which of the following is a key difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to an agreed product, while an Off-specification identifies a product that does not meet its specification.
B.A Request for Change always has a cost and time impact, while an Off-specification never does.
C.A Request for Change is recorded in the Issue Register, while an Off-specification is recorded in the Risk Register.
D.A Request for Change does not require authorization, while an Off-specification does.
AnswerA

This correctly distinguishes the two types of issue.

Why this answer

A Request for Change (RFC) proposes a modification to an agreed product, while an Off-specification (Off-spec) identifies that a product does not meet its specification. Option B is incorrect because both may or may not have cost and time impacts; it's not a defining difference. Option C is incorrect because both RFCs and Off-specs are recorded in the Issue Register, not the Risk Register.

Option D is incorrect because both RFCs and Off-specs require appropriate authorization, typically at the level defined in the project's change authority.

233
MCQmedium

The Project Board has set a cost tolerance of +/- 10% for a stage. The Project Manager forecasts that the stage will be completed 15% under budget. What should the Project Manager do?

A.Report the underrun in the next Highlight Report
B.Reallocate the surplus to other activities without informing the Project Board
C.Continue as planned since being under budget is beneficial
D.Raise an Exception Report to the Project Board
AnswerD

When a tolerance is forecast to be exceeded (even beneficial), an Exception Report is required.

Why this answer

The cost tolerance for the stage is +/-10%, meaning the stage must be completed within 10% over or under the planned budget. A forecast of 15% under budget exceeds the -10% tolerance, constituting an exception. According to PRINCE2, when a forecast indicates that stage tolerance will be exceeded, the Project Manager must raise an Exception Report to the Project Board.

Option A is incorrect because Highlight Reports are used for regular reporting within tolerance, not for exceptions. Option B is incorrect because the Project Manager cannot reallocate surplus without authorization. Option C is incorrect because being outside tolerance requires escalation, not inaction.

234
MCQhard

A project manager discovers that a product expected to be completed in the current stage does not meet its product description quality criteria. The project manager has already used the stage's change budget to address a similar issue. What should the project manager do?

A.Update the product description to match the delivered product
B.Request additional budget from the Project Board via an Exception Report
C.Accept the product as delivered and proceed to the next stage
D.Approve the rework using the remaining risk budget
AnswerB

The change budget is exhausted, so the project manager cannot authorize rework within their delegated authority. An Exception Report is the correct mechanism to escalate to the Project Board for additional budget or guidance.

Why this answer

The change budget is exhausted, so the project manager cannot authorize rework within their delegated authority. An Exception Report is the correct mechanism to escalate to the Project Board for additional budget or guidance. Option A is wrong because product descriptions should not be changed to match a non-conforming product; quality criteria must be met.

Option C is wrong because accepting a non-conforming product without addressing the issue risks overall project quality. Option D is wrong because the risk budget is for managing risks, not for quality rework.

235
MCQeasy

Which practice describes why the project is being done and ensures continued business justification?

A.Business Case
B.Progress
C.Plans
D.Risk
AnswerA

The Business Case practice provides the business justification for the project.

Why this answer

The Business Case practice is the correct answer because it is the PRINCE2 practice that specifically defines the reasons for initiating a project and ensures that the project remains desirable, viable, and achievable throughout its lifecycle. It provides the justification for continued investment by requiring regular review and update of the business justification, which is documented in the Business Case. Without a valid Business Case, the project should be stopped.

Exam trap

PeopleCert often tests the distinction between the Business Case practice and the Plans practice, as candidates may mistakenly think that the project's justification is derived from the project plan rather than from the Business Case document.

How to eliminate wrong answers

Option B (Progress) is wrong because the Progress practice focuses on monitoring and controlling the project's performance against plans, not on defining or justifying why the project is being done. Option C (Plans) is wrong because the Plans practice deals with defining the steps to deliver the project's products, not with providing the business justification for the project itself. Option D (Risk) is wrong because the Risk practice is concerned with identifying, assessing, and controlling uncertainties that could affect the project, not with establishing or maintaining the business case.

236
MCQhard

A project has identified a risk that could impact the project's schedule. The team decides to allocate extra resources to ensure the schedule is met despite the risk. Which risk response is being applied?

A.Reduce
B.Transfer
C.Accept
D.Avoid
AnswerA

Reduce involves actions to lower the probability or impact of a threat. Allocating extra resources reduces the impact on the schedule.

Why this answer

Allocating extra resources to ensure an opportunity is realized (or a threat is mitigated) is an 'enhance' response for opportunities. However, for threats, 'reduce' involves actions to lower probability or impact. The scenario describes a threat (schedule impact), and allocating extra resources reduces the impact; thus it is 'reduce'.

The question might be ambiguous, but the correct PRINCE2 term for threat is 'reduce'.

237
Multi-Selecthard

Which THREE of the following are elements of the PRINCE2 quality practice?

Select 3 answers
A.Quality Assurance
B.Configuration Management
C.Risk Management
D.Quality Control
E.Quality Planning
AnswersA, D, E

Quality Assurance ensures processes are followed.

Why this answer

Quality Assurance (A) is correct because it is a key element of the PRINCE2 quality practice, focusing on ensuring that the project's quality management system is in place and operating effectively. It provides independent checks that the project is being managed according to defined quality processes.

Exam trap

A common mistake in the PRINCE2 exam is confusing the three elements of the quality practice (Quality Assurance, Quality Control, and Quality Planning) with other PRINCE2 practices such as Configuration Management or Risk Management.

238
MCQhard

What is the difference between Project Assurance and Project Support?

A.Project Assurance provides independent oversight, while Project Support provides administrative services
B.Project Assurance is part of the Project Manager's team, while Project Support is independent
C.Project Assurance manages quality control, while Project Support manages the Risk Register
D.Project Assurance is only required for large projects, while Project Support is always required
AnswerA

This correctly distinguishes the two roles.

Why this answer

Project Assurance provides independent oversight and is accountable to the Project Board, while Project Support provides administrative services to the Project Manager and team. Option B is incorrect because Project Assurance is independent, not part of the Project Manager's team. Option C is incorrect because Project Assurance does not manage quality control; it provides oversight, and the Risk Register is managed by the Project Manager with support from Project Support.

Option D is incorrect because both roles are required in all projects, though the level of effort may vary.

239
Multi-Selectmedium

Which TWO of the following are outputs of the Initiating a Project process?

Select 2 answers
A.Project Plan
B.Project Initiation Documentation
C.Risk Register
D.Project Brief
E.Business Case
AnswersB, E

The PID is the key output.

Why this answer

The correct outputs of the Initiating a Project process are the Project Initiation Documentation (PID) and the Business Case. The PID is a comprehensive document that consolidates key information, while the Business Case is refined and approved during this process. Option A (Project Plan) is an output of the Planning process, not Initiating a Project.

Option C (Risk Register) is created during Initiating a Project but is part of the PID, not listed as a separate key output. Option D (Project Brief) is an output of the Starting Up a Project process. Therefore, only B and E are correct.

240
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.An Off-specification is something that should be provided but is not, while a Request for Change is a proposal to change a baseline
B.A Request for Change always requires a change budget, while an Off-specification does not
C.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
D.An Off-specification is recorded in the Risk Register, while a Request for Change is in the Issue Register
AnswerA

This correctly distinguishes the two.

Why this answer

A Request for Change (RFC) is a proposal to modify a baseline, while an Off-specification (Off-spec) describes something that should be provided by the product but is not. Therefore, option A is correct.

241
Multi-Selectmedium

Which TWO statements about the Risk practice are correct?

Select 2 answers
A.The risk budget is used to fund the project's activities.
B.A risk owner must be identified for each risk.
C.Only threats are considered as risks.
D.The risk register is optional if the project is small.
E.The risk management approach defines how risks will be managed.
AnswersB, E

Each risk must have a risk owner who is responsible for managing the risk.

Why this answer

PRINCE2 requires that each risk has a named risk owner who is accountable for managing that risk and implementing the planned responses. This ensures clear accountability and proactive risk management throughout the project lifecycle.

Exam trap

PeopleCert often tests the misconception that the risk budget can be used for general project activities, but PRINCE2 strictly reserves it for funding risk responses, not operational tasks.

242
MCQeasy

What is the definition of quality in PRINCE2?

A.The lowest cost to produce
B.Customer satisfaction
C.Fit for purpose
D.Zero defects
AnswerC

Correct. PRINCE2 defines quality as fit for purpose, meaning the product meets the user's needs.

Why this answer

PRINCE2 defines quality as 'fit for purpose' — the product must meet the needs of the user. Option A is wrong because quality is not about cost efficiency but about meeting requirements. Option B is wrong because customer satisfaction is a broader concept; PRINCE2 focuses on fitness for purpose.

Option D is wrong because 'zero defects' is not the PRINCE2 definition of quality; quality is about meeting stated needs, not necessarily achieving zero defects.

243
Multi-Selectmedium

Which THREE of the following are roles in the project management team?

Select 3 answers
A.Executive
B.Risk Actionee
C.Senior User
D.Change Authority
E.Project Manager
AnswersA, C, E

The Executive is a key role on the Project Board.

Why this answer

The Executive is a defined role in the PRINCE2 project management team, responsible for overall project direction, key decision-making, and ensuring the project delivers business value. The Executive chairs the Project Board and is ultimately accountable for the project's success.

Exam trap

PRINCE2 often tests the distinction between permanent project management team roles and temporary or process-specific roles like Risk Actionee or Change Authority, leading candidates to incorrectly include them as part of the core team.

244
MCQmedium

In PRINCE2, what is the definition of quality?

A.Highest possible standard
B.Fit for purpose
C.Zero defects
D.Conformance to specification
AnswerB

The PRINCE2 definition of quality is 'fit for purpose'.

Why this answer

PRINCE2 defines quality as 'fit for purpose' — meeting agreed requirements and fulfilling its purpose.

245
MCQmedium

What is the purpose of the Risk Register?

A.To approve risk budgets
B.To report progress to stakeholders
C.To capture and track information about identified risks throughout the project
D.To record all decisions made by the Project Board
AnswerC

Correct: the Risk Register is used for recording and tracking risks.

Why this answer

The Risk Register is a PRINCE2 management product that captures and tracks all identified risks throughout the project lifecycle. It records risk descriptions, probability, impact, proximity, and responses, ensuring risks are actively managed and monitored. This aligns with the PRINCE2 principle of continued business justification by maintaining visibility of threats and opportunities.

Exam trap

The trap here is confusing the Risk Register with other registers or reports, such as the Issue Register or Highlight Report, leading candidates to select options that describe functions of those products instead.

How to eliminate wrong answers

Option A is wrong because approving risk budgets is a function of the Project Board, not the Risk Register; the register records risk data but does not authorize financial allocations. Option B is wrong because reporting progress to stakeholders is the purpose of the Highlight Report or End Stage Report, not the Risk Register, which is a detailed log for risk management. Option D is wrong because recording all decisions made by the Project Board is the role of the Decision Register or meeting minutes, while the Risk Register focuses exclusively on risk-related information.

246
MCQmedium

During the Managing Product Delivery process, the Team Manager delivers products to the Project Manager. What document authorizes the Team Manager to deliver the work?

A.Work Package
B.Project Plan
C.Stage Plan
D.Product Description
AnswerA

Correct. A Work Package authorizes the work for the Team Manager.

Why this answer

A Work Package is the document that authorizes the Team Manager to create one or more products. It contains details of the work to be done and constraints.

247
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To prepare an Exception Plan when tolerances are exceeded
C.To control the work of the current stage
D.To enable the Project Board to approve completion of the current stage and authorize the next stage
AnswerD

This is the key purpose: review and authorize the next stage.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve its completion, and authorize the next stage. This process ensures that the project remains viable and aligned with the business case before proceeding, making D the correct answer.

Exam trap

The trap here is that candidates confuse the purpose of Managing a Stage Boundary with the purpose of Controlling a Stage, because both involve stage-level activities, but Managing a Stage Boundary is specifically about the transition between stages, not the ongoing work within a stage.

How to eliminate wrong answers

Option A is wrong because closing the project is the purpose of the Closing a Project process, not Managing a Stage Boundary. Option B is wrong because preparing an Exception Plan is triggered when stage tolerances are forecast to be exceeded, but it is a separate activity within the Managing a Stage Boundary process; the primary purpose is not to prepare an Exception Plan but to enable stage boundary review and next-stage authorization. Option C is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, which focuses on day-to-day management, not the boundary review between stages.

248
MCQeasy

Which practice defines the project management team structure?

A.Business Case
B.Plans
C.Progress
D.Organising
AnswerD

Correct.

Why this answer

The Organising practice defines the project management team structure, including roles, responsibilities, and reporting lines. It establishes who is accountable for key decisions and how the team is organized to deliver the project. This is distinct from other practices that focus on justification, planning, or monitoring.

Exam trap

The PRINCE2 Foundation exam often tests the distinction between 'Organising' (structure and roles) and 'Plans' (scheduling and resources), leading candidates to confuse the practice that defines the team with the one that defines the work breakdown.

How to eliminate wrong answers

Option A is wrong because the Business Case practice provides the justification for the project, not the team structure. Option B is wrong because the Plans practice focuses on defining how the project will be delivered, including schedules and resources, not the organizational hierarchy. Option C is wrong because the Progress practice deals with monitoring and controlling performance against plans, not defining the team structure.

249
Multi-Selectmedium

Which TWO of the following are components of a Product Description?

Select 2 answers
A.Lessons Report
B.Acceptance methods
C.Stage boundaries
D.Risk budget
E.Quality criteria
AnswersB, E

Acceptance methods describe how the product will be verified against its quality criteria.

Why this answer

Options B and E are correct. A Product Description includes acceptance methods and quality criteria. Lessons Report, stage boundaries, and risk budget are not components of a Product Description.

250
Multi-Selecteasy

Which TWO of the following are types of tolerance that can be set in PRINCE2?

Select 2 answers
A.Change control approach
B.Quality management approach
C.Risk budget
D.Time
E.Cost
AnswersD, E

Time is one of the six PRINCE2 tolerances.

Why this answer

The six types of tolerance in PRINCE2 are Time, Cost, Quality, Scope, Risk, and Benefits. Options D and E (Time and Cost) are correct. Options A and B refer to management products (the Change Control Approach and the Quality Management Approach), which are not types of tolerance.

Option C (Risk budget) is a type of budget, not a tolerance. Therefore, the correct answers are D and E.

251
Multi-Selectmedium

Which TWO of the following are components of the Business Case?

Select 2 answers
A.Expected benefits
B.Configuration item records
C.Major risks
D.Team structure
E.Product Breakdown Structure
AnswersA, C

Expected benefits are a key component of the Business Case.

Why this answer

The Business Case in PRINCE2 captures the justification for the project, including the expected benefits (tangible and intangible) that the project aims to deliver. Benefits are a core component because they define the value that the project must provide to justify the investment. Without expected benefits, the Business Case cannot demonstrate whether the project is worthwhile.

Exam trap

PRINCE2 often tests the distinction between components of the Business Case (benefits, risks, costs) and elements of other management products (e.g., Configuration Item Records from Change Control, Team Structure from Organization, Product Breakdown Structure from Plans), leading candidates to confuse planning artifacts with justification artifacts.

252
MCQhard

In PRINCE2, what is the purpose of the Managing a Stage Boundary process?

A.To authorize the work for the next stage
B.To enable the Project Board to review the current stage, approve the next stage plan, and confirm continued business justification
C.To produce the End Project Report
D.To update the Project Plan with actual progress
AnswerB

This is the correct purpose of the Managing a Stage Boundary process.

Why this answer

The purpose is to provide the Project Board with sufficient information to review the current stage, approve the next stage plan, and confirm continued business justification.

253
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Risk
B.Action Item
C.Lessons Learned
D.Off-specification
E.Request for Change
AnswersD, E

One of the three issue types.

Why this answer

In PRINCE2, an issue is a relevant event that has occurred and requires management attention. The two recognized types of issue are 'Off-specification' (something that should be provided by the project but is not, or is provided incorrectly) and 'Request for Change' (a proposal for a change to a product's baseline). Options D and E are correct because they directly match these defined types.

Exam trap

The trap here is that candidates often confuse 'Risk' with 'Issue' because both are management products, but PRINCE2 strictly separates them: risks are uncertain future events, while issues are events that have already occurred.

254
Multi-Selectmedium

Which TWO of the following are opportunity responses in PRINCE2 risk management?

Select 2 answers
A.Exploit
B.Accept
C.Enhance
D.Transfer
E.Avoid
AnswersA, C

Exploit is an opportunity response.

Why this answer

Exploit and Enhance are opportunity responses. Avoid and Transfer are threat responses. Accept can be used for both.

255
Multi-Selectmedium

Which THREE of the following are risk responses for a threat?

Select 3 answers
A.Reduce
B.Avoid
C.Exploit
D.Transfer
E.Enhance
AnswersA, B, D

Reduce is a threat response.

Why this answer

The five threat responses are: avoid, reduce, transfer, accept, share. Fallback is not a separate response; it is part of a plan.

256
Multi-Selectmedium

Which TWO of the following are components of the Project Initiation Documentation (PID)?

Select 2 answers
A.Project Brief
B.Business Case
C.Project Plan
D.Checkpoint Report
E.Project Product Description
AnswersB, C

The Business Case is a core component of the PID.

Why this answer

The Business Case is a core component of the Project Initiation Documentation (PID) because it provides the justification for the project, including costs, benefits, and risks. The Project Plan is also a component of the PID as it defines how and when the project objectives will be achieved, including timescales and resource requirements. Both are mandatory elements that form the foundation of the PID in PRINCE2.

Exam trap

The trap here is that candidates often confuse the Project Brief as a component of the PID, but it is actually a predecessor document that is superseded by the PID during the Initiating a Project process.

257
MCQeasy

In the Organising practice, which role is responsible for providing assurance that the project is being conducted correctly?

A.Team Manager
B.Project Assurance
C.Project Support
D.Project Manager
AnswerB

Project Assurance is independent and provides objective oversight.

Why this answer

Project Assurance is independent of the Project Manager and provides assurance to the Project Board.

258
MCQmedium

Which report does the Project Manager produce regularly to inform the Project Board of progress within a stage?

A.Highlight Report
B.End Stage Report
C.Checkpoint Report
D.Exception Report
AnswerA

The Highlight Report is sent from the Project Manager to the Project Board.

Why this answer

The Highlight Report is produced by the Project Manager at intervals defined in the Communication Management Approach to update the Project Board on progress.

259
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Executive
B.The Project Manager
C.The Project Assurance
D.The Senior User
AnswerB

The Project Manager maintains the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because they manage day-to-day activities, track progress against the Business Case, and escalate any deviations to the Executive. PRINCE2 assigns this operational responsibility to the Project Manager to ensure continuous alignment with the project's justification.

Exam trap

A common mistake in PRINCE2 is to confuse accountability with responsibility. Although the Executive is accountable for the Business Case, the Project Manager is responsible for its day-to-day maintenance. Candidates often select the Executive because they think ownership implies maintenance, but PRINCE2 assigns the operational maintenance role to the Project Manager.

How to eliminate wrong answers

Option A is wrong because the Executive owns the Business Case and is accountable for its approval and viability, but the day-to-day maintenance and monitoring of the Business Case is delegated to the Project Manager. Option C is wrong because Project Assurance provides independent oversight and checks that the Business Case remains valid, but does not maintain it. Option D is wrong because the Senior User specifies the benefits and is responsible for realizing them, but does not maintain the Business Case document itself.

260
MCQhard

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Revise the Project Plan to reduce costs in later stages
B.Issue a Highlight Report noting the overrun
C.Raise an Exception Report to the Project Board
D.Request additional funds from the Executive informally
AnswerC

Correct action when tolerance is forecast to be exceeded.

Why this answer

In PRINCE2, when a project is forecast to exceed its cost tolerance, the Project Manager must escalate the issue to the Project Board by raising an Exception Report. This is because tolerances are delegated authority limits, and exceeding them requires the Project Board to decide on corrective action, such as approving a revised plan or adjusting tolerances. Option C is correct as it directly follows the PRINCE2 principle of management by exception.

Exam trap

The trap here is that candidates confuse a Highlight Report (for routine within-tolerance reporting) with an Exception Report (for escalation when tolerances are forecast to be exceeded), leading them to choose Option B instead of C.

How to eliminate wrong answers

Option A is wrong because revising the Project Plan unilaterally to reduce costs in later stages violates the management by exception principle; the Project Manager cannot change the plan without Project Board approval once tolerances are forecast to be exceeded. Option B is wrong because a Highlight Report is a regular progress report for within-tolerance status, not an escalation mechanism for forecast overruns; issuing one would fail to trigger the required exception process. Option D is wrong because informally requesting additional funds from the Executive bypasses the formal Exception Report process and the Project Board's collective decision-making authority, undermining governance.

261
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Continue with the current plan and adjust the budget in the next stage
B.Close the project immediately
C.Issue an Exception Report to the Project Board
D.Reduce the scope to stay within budget without informing the Board
AnswerC

An Exception Report is the correct mechanism to escalate the forecast deviation.

Why this answer

Management by exception dictates that when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report. Continuing without escalation is not allowed.

262
MCQeasy

Which practice describes the project management team structure and defines roles and responsibilities?

A.Plans
B.Business Case
C.Organising
D.Progress
AnswerC

Correct. Organising defines the team structure and responsibilities.

Why this answer

The Organising practice defines the project management team structure, roles, and responsibilities, including the four levels of management (corporate/programme management, project board, project manager, and team manager) and the three project interests (business, user, supplier). It establishes clear accountability and authority within the PRINCE2 project management team.

Exam trap

The trap here is that candidates often confuse the Organising practice with the Plans practice, mistakenly thinking that defining the team structure is part of planning, when in PRINCE2 it is a separate practice focused specifically on roles and responsibilities.

How to eliminate wrong answers

Option A is wrong because the Plans practice focuses on defining the steps to deliver the project's products, including the sequence, dependencies, and resources, not the team structure or roles. Option B is wrong because the Business Case practice justifies the project's viability and tracks benefits, costs, and risks, not the organizational hierarchy. Option D is wrong because the Progress practice controls the ongoing comparison of actual achievements against planned targets through tolerances and reporting, not the definition of roles and responsibilities.

263
MCQmedium

Which of the following best describes the purpose of the Directing a Project process?

A.To enable the Project Board to make key decisions and exercise overall control
B.To coordinate the work of the team
C.To produce the Project Plan
D.To manage the day-to-day activities of the project
AnswerA

Correct purpose.

Why this answer

The Directing a Project process is designed to enable the Project Board to make key decisions and exercise overall control over the project. It covers the board's responsibilities from project initiation through closure, including authorizing stages, reviewing progress, and providing strategic direction.

Exam trap

PeopleCert often tests the distinction between the Project Board's strategic oversight (Directing a Project) and the Project Manager's operational management (Controlling a Stage), leading candidates to confuse the two.

How to eliminate wrong answers

Option B is wrong because coordinating the work of the team is the purpose of the Managing Product Delivery process, not Directing a Project. Option C is wrong because producing the Project Plan is an activity within the Initiating a Project process, not a purpose of Directing a Project. Option D is wrong because managing day-to-day activities is the responsibility of the Project Manager via the Controlling a Stage process, not the Directing a Project process.

264
MCQmedium

Which document is the key output of the Initiating a Project process?

A.The Project Plan
B.The Business Case
C.The Project Brief
D.The Project Initiation Documentation
AnswerD

The PID is the key output of Initiating a Project.

Why this answer

The Initiating a Project process is responsible for establishing a solid foundation for the project, and its key output is the Project Initiation Documentation (PID). The PID consolidates all essential information—including the Project Plan, Business Case, and Project Brief—into a single, approved document that defines the project's scope, objectives, and controls. This document is the baseline against which project progress is measured and is formally approved by the Project Board before the project proceeds.

Exam trap

PRINCE2 Foundation exams often test the distinction between the Project Brief (created in Starting Up a Project) and the Project Initiation Documentation (created in Initiating a Project), trapping candidates who confuse the input with the output.

How to eliminate wrong answers

Option A is wrong because the Project Plan is a component within the PID, not the key output of the Initiating a Project process; the process produces the PID, which contains the Project Plan. Option B is wrong because the Business Case is developed during the Starting Up a Project process and is refined during Initiating a Project, but it is not the key output—it is a part of the PID. Option C is wrong because the Project Brief is created during the Starting Up a Project process and is used as input to the Initiating a Project process; the PID is the output that supersedes and expands upon the Project Brief.

265
MCQmedium

Which role is responsible for providing assurance that the project is being managed correctly in terms of business, user, and supplier interests?

A.Project Support
B.Project Manager
C.Team Manager
D.Project Assurance
AnswerD

Project Assurance provides independent oversight of the project's management.

Why this answer

Project Assurance is an independent role that provides assurance to the Project Board on all three interests (business, user, supplier). Option A is incorrect because Project Support provides administrative support, not independent assurance. Option B is incorrect because the Project Manager is responsible for day-to-day management, not independent assurance.

Option C is incorrect because the Team Manager is responsible for delivering work packages, not providing assurance across interests.

266
Multi-Selecthard

Which TWO of the following are opportunity responses in PRINCE2?

Select 2 answers
A.Share
B.Transfer
C.Reduce
D.Enhance
E.Avoid
AnswersA, D

Share is an opportunity response to allocate ownership to a third party best able to realize it.

Why this answer

In PRINCE2, opportunity responses are specific actions to address opportunities (positive risks). 'Share' (Option A) is correct because it involves partnering with another party to exploit an opportunity, sharing the potential benefits. 'Enhance' (Option D) is correct because it means proactively increasing the probability and/or impact of an opportunity to maximize its potential benefits.

Exam trap

PeopleCert often tests the confusion between threat and opportunity responses, where candidates mistakenly apply threat responses like 'Transfer' or 'Reduce' to opportunities, not realizing that PRINCE2 has a distinct set of responses for positive risks.

267
Multi-Selectmedium

Which TWO of the following are correct statements about tolerance in PRINCE2?

Select 2 answers
A.The Project Board sets stage tolerances for the Project Manager
B.If a stage tolerance is exceeded, the Project Manager must escalate
C.Tolerances apply only to time and cost
D.The Project Manager can never change tolerances without Board approval
E.Tolerances are set only at project level
AnswersA, B

The Board delegates authority via stage tolerances.

Why this answer

In PRINCE2, the Project Board sets stage tolerances for the Project Manager as part of the 'Manage by Stages' principle. This allows the Project Manager to manage the stage within defined tolerances without needing to escalate every minor deviation, ensuring delegated authority is clear and controlled.

Exam trap

A common misconception is that tolerances apply only to time and cost, but PRINCE2 explicitly includes scope, quality, risk, and benefits as additional tolerance dimensions.

268
MCQeasy

Who is responsible for maintaining the Business Case throughout the project?

A.The Project Manager
B.The Project Assurance
C.The Executive
D.The Senior Supplier
AnswerA

The Project Manager is responsible for maintaining the Business Case throughout the project.

Why this answer

The Project Manager is responsible for maintaining the Business Case throughout the project because PRINCE2 assigns the day-to-day management of the Business Case to the Project Manager, who must ensure it remains viable and aligned with project progress. The Project Manager updates the Business Case with actual costs, benefits, and risks, and presents it to the Project Board for approval at key decision points. This is defined in PRINCE2's Business Case management process, where the Project Manager owns the document's maintenance, not its approval.

Exam trap

PeopleCert often tests the distinction between ownership (Executive) and maintenance (Project Manager), causing candidates to incorrectly select the Executive because they confuse ultimate accountability with operational responsibility.

How to eliminate wrong answers

Option B is wrong because Project Assurance is an independent oversight role that reviews and verifies the Business Case's integrity, but does not maintain or update it. Option C is wrong because the Executive is the ultimate owner of the Business Case and is responsible for its approval and justification, but the day-to-day maintenance is delegated to the Project Manager. Option D is wrong because the Senior Supplier provides supplier-side expertise and resources, but has no direct responsibility for maintaining the Business Case, which is a management product owned by the Project Manager.

269
MCQmedium

In the Progress practice, what is 'management by exception'?

A.The Project Manager must report all decisions to the Project Board
B.Management is only involved when tolerances are forecast to be exceeded
C.The Project Board manages the project on a daily basis
D.All deviations from the plan must be approved by the Project Board
AnswerB

This is the definition of management by exception.

Why this answer

Management by exception is a core PRINCE2 principle where the Project Board only gets involved when forecasts indicate that tolerances (e.g., time, cost, quality) will be exceeded. This allows the Project Manager to manage day-to-day within agreed tolerances, escalating only exceptions. Option B correctly captures this delegation of authority.

Exam trap

The trap here is confusing 'management by exception' with 'micro-management' or 'full reporting'—candidates often think the Board must approve all deviations, but PRINCE2 specifically limits Board involvement to tolerance breaches only.

How to eliminate wrong answers

Option A is wrong because the Project Manager does not report all decisions to the Project Board; only exceptions (forecast tolerance breaches) are escalated. Option C is wrong because the Project Board does not manage the project daily; that is the Project Manager's role within tolerances. Option D is wrong because not all deviations require Board approval; only those that exceed tolerances (exceptions) need approval.

270
MCQeasy

Which role is accountable for the project's success and chairs the Project Board?

A.Senior User
B.Executive
C.Project Manager
D.Senior Supplier
AnswerB

The Executive chairs the Project Board and is accountable for the project.

Why this answer

The Executive is the single individual accountable for the project's success and chairs the Project Board in PRINCE2. This role provides the business justification, secures funding, and makes key strategic decisions, ensuring the project remains viable and aligned with organizational objectives.

Exam trap

The trap here is confusing accountability with responsibility, leading candidates to pick the Project Manager (who is responsible for delivery) instead of the Executive (who is accountable for success and chairs the Board).

How to eliminate wrong answers

Option A is wrong because the Senior User represents the interests of those who will use the project's outputs, but they are not accountable for overall project success nor do they chair the Project Board. Option C is wrong because the Project Manager is responsible for day-to-day management and delivery within constraints set by the Board, but accountability and chairing authority rest with the Executive. Option D is wrong because the Senior Supplier represents the interests of those providing the project's products and resources, but they do not hold ultimate accountability or chair the Board.

271
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To close the project
B.To plan the next stage and provide information for the Project Board to decide on continuation
C.To initiate the project
D.To manage the work of the current stage
AnswerB

Correct.

Why this answer

The purpose is to provide the Project Board with information to approve the next stage and review the current stage's performance.

272
MCQeasy

What is the purpose of the Managing a Stage Boundary process?

A.To control the work of the current stage
B.To close the project
C.To initiate the project
D.To plan the next stage and provide an End Stage Report to the Project Board
AnswerD

The process produces an End Stage Report and a next Stage Plan for approval.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and decide whether to continue the project. It produces an End Stage Report summarizing the current stage's results and a Stage Plan for the next stage, enabling informed governance decisions.

Exam trap

PeopleCert often tests the confusion between 'controlling a stage' and 'managing a stage boundary'—candidates mistakenly think the boundary process handles day-to-day stage control, but it is specifically about stage-end review and next-stage planning.

How to eliminate wrong answers

Option A is wrong because controlling the work of the current stage is the purpose of the Controlling a Stage process, not Managing a Stage Boundary. Option B is wrong because closing the project is the purpose of the Closing a Project process, which occurs after the final stage. Option C is wrong because initiating the project is the purpose of the Initiating a Project process, which sets up the project management foundation before any delivery stages begin.

273
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change always requires a change budget; an Off-specification does not
B.A Request for Change proposes a modification to baselined products; an Off-specification identifies a failure to meet a specification
C.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
D.A Request for Change is recorded in the Risk Register; an Off-specification is recorded in the Issue Register
AnswerB

This is the correct distinction: RFC proposes a change, Off-specification identifies a deviation.

Why this answer

In PRINCE2, a Request for Change (RFC) is a formal proposal to modify a baselined product, while an Off-specification (Off-spec) is a notification that a product does not meet its agreed specification. The key distinction is that an RFC seeks to change the specification itself, whereas an Off-spec reports a failure to conform to the existing specification. Option B correctly captures this fundamental difference.

Exam trap

The trap here is that candidates confuse the source of the issue (who raises it) or the register it belongs to, when the core distinction is the nature of the problem—proposing a change versus reporting a failure to meet a specification.

How to eliminate wrong answers

Option A is wrong because a Request for Change does not always require a change budget; it may be funded from the project's contingency budget or change budget only if approved, and an Off-specification can also require a change budget if a corrective action is needed. Option C is wrong because both a Request for Change and an Off-specification can be raised by any project stakeholder, not exclusively by the Project Board or Project Manager; the Project Board approves RFCs, but they are often raised by team members or the Project Manager. Option D is wrong because both a Request for Change and an Off-specification are recorded in the Issue Register, not the Risk Register; the Risk Register is for threats and opportunities, not issues.

274
MCQmedium

What is the purpose of the Plans practice?

A.To define the project's quality criteria
B.To manage changes to project baselines
C.To define the roles and responsibilities of the project team
D.To facilitate communication and control by defining the means of delivering the products
AnswerD

This is the purpose of the Plans practice.

Why this answer

The Plans practice defines the means of delivering the products by establishing a structured approach to planning, including the creation of project and stage plans. This facilitates communication and control by providing a clear roadmap for stakeholders and enabling progress tracking against baselines. It is not about defining quality criteria, managing changes, or assigning roles, which are covered by other PRINCE2 practices.

Exam trap

The trap here is that candidates often confuse the Plans practice with the Quality practice, mistakenly thinking that plans define quality criteria, when in fact plans focus on the sequence and means of product delivery, not the quality standards.

How to eliminate wrong answers

Option A is wrong because defining the project's quality criteria is the purpose of the Quality practice, not the Plans practice. Option B is wrong because managing changes to project baselines is the purpose of the Change practice, which handles issue and change control. Option C is wrong because defining the roles and responsibilities of the project team is the purpose of the Organization practice, which establishes the project management team structure.

275
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Request for Change
B.Off-specification
C.Risk
D.Opportunity
E.Change budget
AnswersA, B

A Request for Change is a type of issue.

Why this answer

In PRINCE2, an issue is a relevant event that has occurred and requires management attention. The two defined types of issue are a Request for Change (RFC), which is a proposal for a change to a product's specification or baseline, and an Off-specification, which is something that should be provided by the project but is not (e.g., a missing feature or a product that does not meet its specification). Both are formally captured and managed through the Issue and Change Control practice.

Exam trap

In PRINCE2, candidates often confuse issues (events that have already occurred) with risks (uncertain future events). This leads to selecting 'Risk' or 'Opportunity' as types of issues, when the correct types are Request for Change and Off-specification, which are managed under the Issue and Change Control practice.

276
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To enable the Project Board to review the current stage and approve the next stage plan
B.To accept Work Packages and deliver products
C.To provide overall direction and control to the project
D.To prepare the End Project Report and close the project
AnswerA

Managing a Stage Boundary prepares the information for the Project Board to decide on stage boundaries.

Why this answer

The Managing a Stage Boundary process is designed to provide the Project Board with sufficient information to review the current stage's performance, approve the next stage plan, and update the project plan and Business Case accordingly. Option A accurately describes this purpose. Option B describes the purpose of Managing Product Delivery, which handles the acceptance and delivery of work packages.

Option C describes the purpose of Directing a Project, which provides overall direction and control. Option D describes the purpose of Closing a Project, which finalizes the project.

277
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Close the project as the Business Case is no longer viable.
B.Increase the project budget using the change budget.
C.Raise an Exception Report and await Project Board direction.
D.Continue with the plan and report the overrun in the next Highlight Report.
AnswerC

The Project Manager must escalate via an Exception Report.

Why this answer

C is correct because when a project forecasts exceeding its cost tolerance, the Project Manager must escalate the issue to the Project Board via an Exception Report. This is a PRINCE2 management by exception principle: tolerances are delegated limits, and exceeding them requires board-level decision-making, not unilateral action by the Project Manager.

Exam trap

The trap here is that candidates confuse the Project Manager's authority to manage within tolerances with the ability to handle breaches, leading them to choose 'continue and report later' (D) or 'use change budget' (B), when PRINCE2 mandates immediate escalation via an Exception Report.

How to eliminate wrong answers

Option A is wrong because closing the project is a Project Board decision, not the Project Manager's, and exceeding cost tolerance does not automatically invalidate the Business Case—the board may approve a revised plan. Option B is wrong because the change budget is for authorized changes, not for covering forecast overruns; using it without board approval violates PRINCE2's change control approach. Option D is wrong because continuing the plan and reporting in the next Highlight Report ignores the escalation requirement; an Exception Report is mandatory when a tolerance is forecast to be breached.

278
Drag & Dropmedium

Drag and drop the steps to create a PRINCE2 project plan into the correct order.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4

Why this order

Planning steps: design the plan, define products, identify activities, estimate, and schedule/document.

279
MCQeasy

Which process authorizes a work package?

A.Managing Product Delivery
B.Controlling a Stage
C.Starting Up a Project
D.Initiating a Project
AnswerB

The PM authorizes work packages during CS.

Why this answer

In PRINCE2, the 'Controlling a Stage' process is responsible for authorizing work packages to be executed by the team. This process ensures that each work package is formally assigned, with clear acceptance criteria, reporting arrangements, and any constraints, before the team proceeds with delivery.

Exam trap

The trap here is confusing the process that assigns work (Controlling a Stage) with the process that executes the work (Managing Product Delivery), leading candidates to incorrectly select the delivery process as the authorizing one.

How to eliminate wrong answers

Option A is wrong because 'Managing Product Delivery' is the process that accepts and executes work packages, not authorizes them; it focuses on the team's delivery work. Option C is wrong because 'Starting Up a Project' is a pre-project process that creates the project mandate and appoints the executive/manager, but does not authorize work packages. Option D is wrong because 'Initiating a Project' produces the Project Initiation Documentation and plans, but work package authorization occurs later during stage execution under 'Controlling a Stage'.

280
MCQmedium

What is the purpose of the Quality Review technique?

A.To approve the Project Plan
B.To establish the project's acceptance criteria
C.To assign risk owners to identified risks
D.To assess whether a product meets its quality criteria and identify errors
AnswerD

This is the purpose of the Quality Review technique.

Why this answer

The Quality Review technique is used to assess whether a product meets its quality criteria and to identify errors.

281
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change proposes a modification to a baseline, whereas an Off-specification identifies a failure to meet a baseline
B.There is no difference; they are the same thing
C.A Request for Change is raised by the Project Board, while an Off-specification is raised by the Project Manager
D.An Off-specification requires a change budget, while a Request for Change does not
AnswerA

Correct distinction.

Why this answer

A Request for Change is a proposal for a change to the project's baselines, while an Off-specification is something that should be provided but is not (or is forecast not to be).

282
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do?

A.Raise an Exception Report to the Project Board
B.Close the project immediately
C.Continue with the current plan and report at the next Highlight Report
D.Increase the budget and inform the Project Board
AnswerA

Correct action when tolerance is forecast to be exceeded.

Why this answer

When a tolerance is forecast to be exceeded, the PM must escalate via an Exception Report to the Project Board. This is management by exception.

283
MCQmedium

What is the difference between a Request for Change and an Off-specification?

A.A Request for Change is for any change, while an Off-specification is for a product that has not been approved
B.A Request for Change proposes a modification to an approved product, while an Off-specification identifies a product that does not meet its specification
C.A Request for Change is raised by the Project Manager, while an Off-specification is raised by the Team Manager
D.A Request for Change requires a change budget, while an Off-specification requires contingency
AnswerB

This is the correct distinction.

Why this answer

A Request for Change is a proposal for a modification to a product that has been approved, while an Off-specification is a product that does not meet its specification.

284
MCQmedium

In the Progress practice, who receives the Highlight Report?

A.Project Support
B.Senior User
C.Project Board
D.Team Manager
AnswerC

The Highlight Report is directed to the Project Board.

Why this answer

The Highlight Report is a progress report that provides the Project Board with a summary of the project's status at a frequency defined in the Communication Management Approach. It is specifically designed to keep the Project Board informed of progress, achievements, and any issues or risks that require their attention. The Project Board is the sole recipient of the Highlight Report, as they are responsible for overall project governance and decision-making.

Exam trap

A common pitfall in PRINCE2 exams is confusing who produces the Highlight Report (Project Manager) with who receives it (Project Board). Also, candidates may incorrectly think that individual Project Board members like the Senior User receive the report separately, but it is sent to the entire Project Board.

How to eliminate wrong answers

Option A is wrong because Project Support is responsible for preparing and distributing the Highlight Report, not receiving it. Option B is wrong because the Senior User is a member of the Project Board and receives the Highlight Report as part of the board, but the question asks for the recipient as a role, and the Project Board is the collective body that receives it; the Senior User alone is not the designated recipient. Option D is wrong because the Team Manager receives the Checkpoint Report from their team, not the Highlight Report, and they provide input to the Project Manager for the Highlight Report.

285
Multi-Selecthard

Which THREE of the following are true about the PRINCE2 Quality Review technique?

Select 3 answers
A.It can include participants external to the project team
B.It requires the presence of a Project Assurance representative
C.It involves defined roles such as Chair, Presenter, and Reviewer
D.It is a method of testing the product against its specification
E.It is a systematic examination of a product to identify defects
AnswersA, C, E

External experts can be invited to provide independent review.

Why this answer

Options A, C, and E are correct. The Quality Review technique is a structured review with defined roles (chair, presenter, reviewer, administrator) and involves a systematic examination of a product to identify defects. It may include participants external to the project team, such as subject matter experts.

Option B is false because Project Assurance representation is not mandatory for every review. Option D is false because the technique is a review/inspection, not a test against specification; testing is a separate quality method.

286
MCQmedium

Which risk response is appropriate for an opportunity that the project wants to make more likely to happen?

A.Reject
B.Exploit
C.Share
D.Enhance
AnswerB

Exploit aims to make the opportunity happen.

Why this answer

Exploit is the correct risk response for an opportunity the project wants to make more likely to happen. In PRINCE2, the Exploit response is specifically used when the project actively seeks to ensure that an opportunity is realized, often by allocating resources or taking direct actions to increase the probability of the positive event occurring. This contrasts with Enhance, which only increases the probability or impact without guaranteeing the outcome.

Exam trap

In PRINCE2, candidates often confuse Exploit and Enhance. Exploit is used when the project actively seeks to ensure the opportunity is realized, while Enhance only increases the probability or impact without guaranteeing the outcome.

How to eliminate wrong answers

Option A (Reject) is wrong because Reject is used for threats, not opportunities; it involves ignoring or not responding to a risk, which is inappropriate for a desired positive event. Option C (Share) is wrong because Share involves allocating ownership of the opportunity to a third party (e.g., through partnership or contract) to gain the benefit, not directly making it more likely to happen. Option D (Enhance) is wrong because Enhance only increases the probability or impact of an opportunity, but does not actively seek to make it happen; Exploit is the proactive response to ensure realization.

287
MCQhard

An issue is raised stating that a product has been delivered but does not meet its agreed specification. What type of issue is this?

A.Request for Change
B.Risk
C.Problem/Concern
D.Off-specification
AnswerD

This describes a product not meeting its specification.

Why this answer

An off-specification (Off-spec) is the correct type of issue when a product has been delivered but does not meet its agreed specification. In PRINCE2, an off-specification is defined as a situation where a product should be produced according to its specification but is not, or where a product is delivered that does not meet its specification. This directly matches the scenario described.

Exam trap

The trap here is that candidates often confuse an off-specification with a Request for Change, but the key distinction is that an off-specification is about a product not meeting its current specification, while an RFC is about proposing a change to the specification itself.

How to eliminate wrong answers

Option A is wrong because a Request for Change (RFC) is a proposal for a change to a product's specification or baseline, not a report of a product failing to meet its existing specification. Option B is wrong because a risk is an uncertain event that, if it occurs, will affect project objectives, whereas this is a certainty that a product does not meet its specification. Option C is wrong because Problem/Concern is a generic term and not a formal PRINCE2 issue type; PRINCE2 defines three specific issue types: Request for Change, Off-specification, and Problem/Concern (which is used for issues that are neither an RFC nor an off-specification, such as a query or a suggestion).

288
MCQeasy

What does the 'management by exception' principle in PRINCE2 mean?

A.The Project Board sets tolerances and only reviews the project if tolerances are forecast to be exceeded
B.The Project Manager must report all decisions to the Project Board immediately
C.The Project Board makes all decisions for the project
D.The Project Manager can ignore plans and work independently
AnswerA

This is the core of management by exception.

Why this answer

The 'management by exception' principle in PRINCE2 means that the Project Board sets tolerances for time, cost, quality, scope, risk, and benefits, and only requires the Project Manager to escalate if those tolerances are forecast to be exceeded. This allows the Project Manager to manage within tolerances without constant board involvement, empowering them to make day-to-day decisions while the Board focuses on strategic issues.

289
MCQmedium

Which document describes the quality expectations and acceptance criteria for a project's products?

A.Product Description
B.Quality Management Approach
C.Project Product Description
D.Quality Register
AnswerB

This document sets out the quality procedures, standards, and acceptance criteria for the project.

Why this answer

The Quality Management Approach defines how quality will be managed, including quality criteria and acceptance methods.

290
MCQmedium

Which PRINCE2 principle is being applied when a project uses management by exception?

A.Continued business justification
B.Manage by exception
C.Manage by stages
D.Focus on products
AnswerB

Correct principle.

Why this answer

Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.

291
Multi-Selectmedium

Which TWO of the following are types of issue in PRINCE2?

Select 2 answers
A.Exception Plan
B.Off-specification
C.Risk
D.Lessons Report
E.Request for Change
AnswersB, E

A product that does not meet its specification.

Why this answer

In PRINCE2, an issue is a relevant event that has occurred and requires management attention. The two types of issue are 'Off-specification' (something that should be provided but is not) and 'Request for Change' (a proposal for a change to a baseline). Options B and E are correct because they directly match these defined types.

Exam trap

The trap here is confusing management products (like Exception Plan or Lessons Report) or risk concepts with the specific PRINCE2 issue types, leading candidates to select options that are not defined as issue categories.

292
MCQmedium

A project is forecast to exceed its cost tolerance. What should the Project Manager do first?

A.Close the project immediately
B.Issue an Exception Report to the Project Board
C.Increase the budget to cover the extra cost
D.Continue with the current plan and report at the end of the stage
AnswerB

The Project Manager must escalate via an Exception Report when tolerances are forecast to be exceeded.

Why this answer

According to the management by exception principle, when a tolerance is forecast to be exceeded, the Project Manager must escalate to the Project Board via an Exception Report.

293
MCQhard

In product-based planning, what is the purpose of a Product Flow Diagram?

A.To show the hierarchical breakdown of products
B.To identify the resources needed for each product
C.To list the quality criteria for each product
D.To show the sequence and dependencies of product creation
AnswerD

The Product Flow Diagram maps the order and dependencies of product development.

Why this answer

A Product Flow Diagram shows the order in which products will be developed and the dependencies between them. It is a key input to the activity network.

294
MCQmedium

Which of the following is an opportunity response in PRINCE2?

A.Exploit
B.Accept
C.Transfer
D.Avoid
AnswerA, B

Correct. Exploit is a response that aims to make the opportunity happen.

Why this answer

PRINCE2 defines five threat responses (Avoid, Transfer, Mitigate, Accept, Contingent) and five opportunity responses (Exploit, Share, Enhance, Accept, Contingent). 'Exploit' is a specific opportunity response that seeks to make the opportunity happen. 'Accept' is also an opportunity response, meaning the opportunity is accepted without proactive action, but with a contingency plan. Therefore, both A and B are correct opportunity responses.

295
MCQmedium

What is the purpose of the Managing a Stage Boundary process?

A.To manage the day-to-day activities of the team
B.To plan the next stage in detail and obtain Project Board approval
C.To close the project and produce the End Project Report
D.To initiate the project and create the PID
AnswerB

This is the core purpose of SB: to plan the next stage and seek approval.

Why this answer

Managing a Stage Boundary (SB) is designed to provide the Project Board with information to review the current stage's performance, approve the next stage plan, and update the Business Case and project plan.

296
Multi-Selecthard

Which TWO statements correctly describe the difference between the risk owner and the risk actionee?

Select 2 answers
A.There can be multiple risk actionees for a single risk; there is only one risk owner
B.The risk owner is always a member of the Project Board; the risk actionee is always a team member
C.The risk owner is responsible for updating the risk register; the risk actionee is not
D.The risk actionee is responsible for identifying new risks; the risk owner is responsible for implementing responses
E.The risk owner is accountable for the risk; the risk actionee carries out actions
AnswersA, E

This is correct.

Why this answer

The risk owner is responsible for managing the risk, while the risk actionee performs specific actions.

297
MCQhard

What is the difference between a Request for Change (RFC) and an Off-specification (Off-spec)?

A.An RFC is a threat; an Off-spec is an opportunity
B.An RFC requires a change budget; an Off-spec does not
C.An RFC proposes a change to a baselined product; an Off-spec is a product that does not meet its specification
D.An RFC is raised by the Project Manager; an Off-spec is raised by the Project Board
AnswerC

This is the key distinction.

Why this answer

An RFC proposes a modification to a product that has been approved or baselined; an Off-spec is something that should be provided but is not (or will not be) as specified.

298
MCQmedium

In the Organising practice, what is the single point of accountability for the project's business justification?

A.The Project Manager
B.The Executive (Senior Responsible Owner)
C.The Senior User
D.The Project Board
AnswerB

The Executive is accountable for the Business Case and business justification.

Why this answer

In PRINCE2, the Executive (Senior Responsible Owner) is the single point of accountability for the project's business justification. This role owns the business case, ensures the project remains viable, and has ultimate authority over its initiation, continuation, and closure. The Project Manager is accountable for day-to-day management, not the business justification.

Exam trap

The trap here is that candidates often confuse the Project Board's collective responsibility with the Executive's singular accountability, or mistakenly assign business justification to the Project Manager who manages the business case but does not own it.

How to eliminate wrong answers

Option A is wrong because the Project Manager is accountable for managing the project on a day-to-day basis and delivering the products, not for the business justification. Option C is wrong because the Senior User is accountable for specifying the needs of users and ensuring the solution delivers expected benefits, but does not own the business case. Option D is wrong because the Project Board is a collective decision-making body that includes the Executive, Senior User, and Senior Supplier; accountability for business justification rests solely with the Executive, not the board as a whole.

299
MCQhard

What is the difference between a Request for Change and an Off-specification?

A.There is no difference; the terms are interchangeable
B.A Request for Change is raised by the Project Board; an Off-specification is raised by the Project Manager
C.A Request for Change seeks to change a product without a baseline; an Off-specification relates to a baselined product
D.An Off-specification is a failure to meet a specification; a Request for Change is a proposal to change a specification
AnswerD

Off-specification indicates non-conformance; Request for Change proposes a deliberate change.

Why this answer

An Off-specification is something that should be provided but is not (or is wrong). A Request for Change is a proposed modification to a baselined product.

300
Multi-Selectmedium

Which TWO of the following are responsibilities of the Project Board?

Select 2 answers
A.Providing overall direction and control of the project
B.Managing day-to-day activities of the project
C.Approving the Project Plan and any stage plans
D.Maintaining the Business Case
E.Producing Team Plans
AnswersA, C

The Project Board is accountable for the project's success and provides direction and control.

Why this answer

Options A and C are correct. The Project Board is responsible for providing overall direction and control of the project (A) and approving the Project Plan and any stage plans (C). Managing day-to-day activities (B) is the Project Manager's responsibility.

Maintaining the Business Case (D) is the Project Manager's responsibility, not a Project Board responsibility. Producing Team Plans (E) is the Team Manager's responsibility.

← PreviousPage 4 of 8 · 596 questions totalNext →

Ready to test yourself?

Try a timed practice session using only PRINCE2 Practices questions.