Courseiva
PRINCE2 PracticeseasyMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

Who is responsible for approving the Project Plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board

The Project Plan is approved by the Project Board as part of the PID approval.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior User

    Why it's wrong here

    The Senior User is on the Board but approval is collective.

  • Project Manager

    Why it's wrong here

    The PM creates the plan but does not approve it.

  • Project Board

    Why this is correct

    The Project Board approves the Project Plan.

  • Executive

    Why it's wrong here

    The Executive is part of the Board but approval is a collective decision.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.