In PRINCE2, what is the purpose of the Risk Register?

⚠ Common exam trap

Test-takers frequently confuse the Risk Register with the Issue Register, as both involve logging and tracking items, but PRINCE2 strictly separates risks (uncertain future events) from issues (current problems or requests for change).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

To record all identified risks and their management

The Risk Register in PRINCE2 is the central repository for recording all identified risks (both threats and opportunities) and their ongoing management actions, including analysis, response planning, and status updates. It is a key management product that supports the continuous management of risk throughout the project lifecycle, ensuring that risks are formally captured, assessed, and controlled.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • To record lessons learned

    Why it's wrong here

    Lessons are recorded in the Lessons Log.

  • To record quality review results

    Why it's wrong here

    Quality review results are recorded in the Quality Register.

  • To record all identified risks and their management

    Why this is correct

    The Risk Register captures risk identification, assessment, response planning, and status.

  • To record all issues raised during the project

    Why it's wrong here

    That is the Issue Register.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.