Courseiva
PRINCE2 Practices →mediumMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

During which process is the Benefits Review Plan first created?

⚠ Common exam trap

PRINCE2F often tests the distinction between processes that create a product versus processes that use or update it — candidates frequently pick 'Starting up a Project' because benefits are mentioned in the Business Case, missing that the formal Benefits Review Plan is created in Initiating a Project.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Initiating a Project

The Benefits Review Plan is created during the Initiating a Project process, where the Project Manager assembles the Project Initiation Documentation (PID). It defines how and when the project's benefits will be measured and reviewed, both during the project and after it closes. Because benefits realization often extends beyond project closure, the plan must be established early so that measurement responsibilities are clear.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Closing a Project

    Why it's wrong here

    Closing a Project uses the Benefits Review Plan to confirm benefits are measured after closure, but the plan is drafted far earlier and merely reviewed here. It tempts because closure activities revolve around benefit realisation and follow-on actions, so the plan's presence in this process suggests it originates there.

  • ✓

    Initiating a Project

    Why this is correct

    The Benefits Review Plan is first created during Initiating a Project, where the Project Initiation Documentation is assembled. It defines how and when the project's benefits will be measured and reviewed after closure, so it must exist before the project is authorised to proceed.

  • ✗

    Managing a Stage Boundary

    Why it's wrong here

    The Benefits Review Plan is first drafted during Starting Up a Project, as part of the Project Brief, then refined at each stage boundary. Managing a Stage Boundary updates it for the next stage, so it is tempting because that process genuinely revisits benefits, but it is not where the plan originates.

  • ✗

    Starting up a Project

    Why it's wrong here

    Starting up a Project produces the Project Brief and outline business case, not the Benefits Review Plan, which the Project Manager drafts during Initiating a Project as part of the detailed business case. It tempts because this process establishes the project's baseline documentation, so people assume all plans are created here.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.