PRINCE2F PRINCE2 Practices Practice Question
During which process is the Benefits Review Plan first created?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Initiating a Project
The Benefits Review Plan is created during the Initiating a Project process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Closing a Project
Why it's wrong here
Benefits review is performed, not created.
- ✓
Initiating a Project
Why this is correct
Correct.
- ✗
Managing a Stage Boundary
Why it's wrong here
Benefits Review Plan is updated but not first created.
- ✗
Starting up a Project
Why it's wrong here
SU produces the Project Brief, not Benefits Review Plan.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.