PRINCE2F PRINCE2 Practices Practice Question
Exhibit
Refer to the exhibit.
Exhibit:
Business Case:
Expected Benefits:
- Reduced operational costs by 15%
- Improved customer satisfaction score to 90%
Expected Dis-benefits:
- Initial investment of $500,000
Net Benefits: $1,200,000 over 3 years
Risks:
- Market changes may affect cost savings (probability: Medium, impact: High)Based on the exhibit, what is the purpose of including expected dis-benefits in the Business Case?
⚠ Common exam trap
Candidates often confuse dis-benefits with risks or costs, but PRINCE2 explicitly separates them: dis-benefits are certain negative outcomes, risks are uncertain events, and costs are financial expenditures.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
To provide a balanced view of the project's justification
The PRINCE2 Business Case must include expected dis-benefits to provide a balanced view of the project's justification. Dis-benefits are measurable negative outcomes that, when weighed against benefits, allow the Senior User and Senior Supplier to make an informed go/no-go decision. Without documenting dis-benefits, the Business Case would present an incomplete picture, potentially leading to approval of a project with hidden negative impacts.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
To identify risks that could affect the project
Why it's wrong here
Dis-benefits are not risks; they are certain negative outcomes.
- ✗
To show the full cost of the project including ongoing operational costs
Why it's wrong here
The dis-benefit shown is an initial investment, which is a cost, but the purpose is broader: to show negative impacts.
- ✓
To provide a balanced view of the project's justification
Why this is correct
Dis-benefits are included to give a complete picture of the project's value, including both positive and negative outcomes.
- ✗
To document the project's key performance indicators
Why it's wrong here
KPIs are not dis-benefits; they measure performance.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.