Courseiva
PRINCE2 Practices →easyMultiple Choice

PRINCE2F PRINCE2 Practices Practice Question

Exhibit

Refer to the exhibit.

Exhibit:
Business Case:
  Expected Benefits:
    - Reduced operational costs by 15%
    - Improved customer satisfaction score to 90%
  Expected Dis-benefits:
    - Initial investment of $500,000
  Net Benefits: $1,200,000 over 3 years
  Risks:
    - Market changes may affect cost savings (probability: Medium, impact: High)

Based on the exhibit, what is the purpose of including expected dis-benefits in the Business Case?

⚠ Common exam trap

Candidates often confuse dis-benefits with risks or costs, but PRINCE2 explicitly separates them: dis-benefits are certain negative outcomes, risks are uncertain events, and costs are financial expenditures.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To provide a balanced view of the project's justification

The PRINCE2 Business Case must include expected dis-benefits to provide a balanced view of the project's justification. Dis-benefits are measurable negative outcomes that, when weighed against benefits, allow the Senior User and Senior Supplier to make an informed go/no-go decision. Without documenting dis-benefits, the Business Case would present an incomplete picture, potentially leading to approval of a project with hidden negative impacts.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To identify risks that could affect the project

    Why it's wrong here

    Expected dis-benefits are the negative outcomes stakeholders accept in exchange for the project's benefits, recorded so the Business Case presents a balanced justification. Risks are captured separately in the Risk Register, so this option substitutes risk identification, which is a distinct PRINCE2 activity, for documenting accepted negative consequences.

  • ✗

    To show the full cost of the project including ongoing operational costs

    Why it's wrong here

    Expected dis-benefits record negative outcomes the project will cause, not costs. Cost capture belongs in the Business Case's cost section, which is why this distractor tempts: both live in the same document. The question asks about dis-benefits specifically, so ongoing operational costs are irrelevant here.

  • ✓

    To provide a balanced view of the project's justification

    Why this is correct

    Expected dis-benefits record the negative outcomes a project will cause, so including them alongside benefits gives decision-makers a balanced, honest view of justification. Omitting them would overstate value, so this satisfies the stem's purpose of balanced justification.

  • ✗

    To document the project's key performance indicators

    Why it's wrong here

    Expected dis-benefits record the negative outcomes accepted in exchange for the project's benefits, giving the Business Case a balanced justification. Key performance indicators measure progress against objectives and belong in the Benefits Management Approach or project controls, so this option confuses performance measurement with documenting accepted negative consequences.

About these practice questions

One of 1,189 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.