Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

PRINCE2F PRINCE2 Practices Practice Question

A project manager is preparing the Business Case for a new project. The expected benefits are $500,000, and the expected costs are $400,000. However, there is a high risk that the benefits may be only $300,000 due to market uncertainty. According to PRINCE2 practices, how should the project manager reflect this in the Business Case?

⚠ Common exam trap

Many exam-takers choose a single 'conservative' estimate (Option B) thinking it is prudent, but PRINCE2 requires transparency through a range and risk assessment rather than hiding uncertainty or oversimplifying the analysis.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Include a cost-benefit analysis showing a range of benefits ($300,000-$500,000) and a risk assessment explaining the market uncertainty.

PRINCE2 requires the Business Case to be a living document that reflects realistic projections, including uncertainties. By showing a range of benefits ($300,000–$500,000) and a corresponding risk assessment, the project manager provides a balanced view that supports informed decision-making, aligning with the 'continued business justification' principle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Include a cost-benefit analysis showing a range of benefits ($300,000-$500,000) and a risk assessment explaining the market uncertainty.

    Why this is correct

    The Business Case should present realistic scenarios and associated risks.

  • Use the lower benefit estimate of $300,000 to be conservative.

    Why it's wrong here

    This may be too pessimistic; the Business Case should reflect the expected value.

  • Use the expected benefits of $500,000 as the primary figure, with a note that benefits may vary.

    Why it's wrong here

    The Business Case should include a range or probabilistic assessment, not just a note.

  • Omit the risk from the Business Case to avoid discouraging stakeholders.

    Why it's wrong here

    Risks must be included to ensure informed decision-making.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.