PRINCE2F PRINCE2 Practices Practice Question
During the Controlling a Stage process, the Team Manager completes a work package and delivers the products. What report does the Team Manager provide to the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Checkpoint Report
The Team Manager provides Checkpoint Reports at regular intervals. The Project Manager uses these to compile Highlight Reports for the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Highlight Report
Why it's wrong here
Highlight Reports are produced by the Project Manager for the Project Board.
- ✗
Exception Report
Why it's wrong here
Exception Reports are for tolerance breaches.
- ✗
End Stage Report
Why it's wrong here
End Stage Reports are produced at stage boundaries.
- ✓
Checkpoint Report
Why this is correct
Checkpoint Reports are from Team Manager to Project Manager.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.