In PRINCE2, who is responsible for ensuring that project assurance is independent of the Project Manager?

⚠ Common exam trap

PRINCE2F often tests the principle that assurance must be independent of the Project Manager; candidates wrongly assign it to the Project Manager or Project Support because those roles are closest to day-to-day delivery.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project Board

In PRINCE2, the Project Board is accountable for project assurance, ensuring it is independent of the Project Manager. The Board appoints assurance roles (Business, User, Supplier assurance) that monitor the project on its behalf, providing independent oversight. This independence is a core governance principle.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project Board

    Why this is correct

    The Project Board owns the project assurance responsibility and must ensure it remains independent of the Project Manager, since the Project Manager cannot objectively assure their own work. Board members appoint assurance roles that report to them, preserving that independence throughout the project lifecycle.

  • ✗

    Senior User

    Why it's wrong here

    The Senior User represents user interests on the Project Board and holds no mandate to assure the project independently of the Project Manager. It is tempting because board members provide oversight, and the Senior User would be correct for confirming user requirements are met, not assurance independence.

  • ✗

    Project Manager

    Why it's wrong here

    The Project Manager executes the project and cannot assure their own work independently, defeating the assurance purpose. It is tempting because the role owns day-to-day delivery, and would be correct only where assurance is explicitly delegated and reported outside the Project Manager's line.

  • ✗

    Project Support

    Why it's wrong here

    Project Support administratively assists the Project Manager, so assurance performed there lacks independence from that role. It is tempting because support staff often gather progress data, and Project Support would be correct for maintaining configuration records and documentation, not for independent assurance.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,189-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.