Courseiva
PRINCE2 PracticeshardMultiple ChoiceObjective-mapped

Maintaining the Risk Register in PRINCE2

In PRINCE2, which role is responsible for maintaining the risk register?

Quick Answer

The answer is the Project Manager, who holds the responsibility for maintaining the risk register as a core component of the PRINCE2 'Manage Risk' practice. This role ensures that all identified risks are recorded, updated, and reviewed throughout the project lifecycle, keeping the register an accurate reflection of current risk status. On the PRINCE2 Foundation exam, this question tests your understanding of role-specific accountabilities versus ownership, as the Project Manager manages the register itself but does not own individual risks—those are owned by the Risk Owner. A common trap is confusing the Project Manager’s administrative duty with the Project Board’s strategic oversight or the Risk Owner’s specific risk management. To remember this, think of the register as the project’s central risk logbook: the Project Manager is the librarian who keeps it organized and current, while others contribute entries.

⚠ Common exam trap

Test-takers frequently confuse the 'Risk Owner' (who manages a specific risk) with the role responsible for maintaining the entire risk register, leading them to select Option B instead of the correct Project Manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Manager

The Project Manager is responsible for maintaining the risk register as part of the 'Manage Risk' practice. This includes ensuring that risks are recorded, updated, and reviewed throughout the project, and that the register reflects the current risk status. The Project Manager does not own individual risks but manages the register as a key project document.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Senior User

    Why it's wrong here

    The Senior User does not maintain the risk register.

  • The Risk Owner

    Why it's wrong here

    The risk owner is responsible for managing a specific risk, not the entire register.

  • The Project Assurance

    Why it's wrong here

    Project Assurance provides independent oversight, not maintenance.

  • The Project Manager

    Why this is correct

    The Project Manager maintains the risk register.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Who is responsible for the day-to-day management of project risks?

easy
  • A.Executive
  • B.Risk Actionee
  • C.Project Manager
  • D.Risk Owner

Why C: The Project Manager is responsible for the day-to-day management of risks, including maintaining the Risk Register and coordinating risk responses. Option A is wrong because the Executive owns the Business Case, not risk management. Option B is wrong because the Risk Actionee implements a specific risk response, not overall management. Option D is wrong because the Risk Owner is assigned for a specific risk and is accountable for its management, but the Project Manager handles day-to-day activities.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.