Which PRINCE2 principle is being applied when the Project Manager escalates a tolerance deviation to the Project Board?

⚠ Common exam trap

Candidates often confuse 'Manage by Exception' with 'Continued Business Justification' — the escalation of a tolerance breach is about exceeding delegated limits, not about the project's ongoing viability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Manage by Exception

The 'Manage by Exception' principle is applied when the Project Manager escalates a tolerance deviation to the Project Board. This principle delegates decision-making authority to the Project Manager within defined tolerances (e.g., time, cost, quality, scope, risk, and benefit). When a forecast indicates that a tolerance will be exceeded, the Project Manager must escalate the issue to the Project Board, which then decides on corrective action. This ensures that the Project Board only becomes involved when a deviation threatens the project's agreed limits, embodying the 'manage by exception' approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continued Business Justification

    Why it's wrong here

    This relates to the Business Case.

  • Manage by Exception

    Why this is correct

    Correct. Escalation of tolerance deviations is management by exception.

  • Learn from Experience

    Why it's wrong here

    This relates to lessons learned.

  • Focus on Products

    Why it's wrong here

    This relates to product-based planning.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

3 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which PRINCE2 principle is being applied when the Project Manager escalates an issue that is outside the stage tolerance?

medium
  • A.Manage by stages
  • B.Manage by exception
  • C.Tailor to suit the project environment
  • D.Continued business justification

Why B: The principle of 'Manage by exception' is applied when the Project Manager escalates an issue that exceeds the stage tolerance. This principle establishes that each management level (e.g., Project Manager, Project Board) has defined tolerances (e.g., time, cost, quality) for their delegated authority; if a forecast or actual deviation goes beyond those tolerances, the issue must be escalated to the next management level for a decision. By escalating the out-of-tolerance issue, the Project Manager is following the exception-based control mechanism that is core to PRINCE2.

Variation 2. Which PRINCE2 principle is being applied when a project uses management by exception?

medium
  • A.Continued business justification
  • B.Manage by exception
  • C.Manage by stages
  • D.Focus on products

Why B: Management by exception is a key principle where tolerances are set and escalation occurs only when tolerances are forecast to be exceeded.

Variation 3. Which PRINCE2 principle is applied when a Project Manager escalates a forecast tolerance deviation to the Project Board?

medium
  • A.Manage by stages
  • B.Focus on products
  • C.Manage by exception
  • D.Continued business justification

Why C: When a Project Manager forecasts that a tolerance (e.g., cost or time) will be exceeded, they escalate to the Project Board. This is the direct application of the 'Manage by exception' principle, which defines tolerances for each management level and requires escalation only when those tolerances are forecast to be breached, allowing normal management within tolerances without board intervention.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.