Who is responsible for performing Project Assurance?

⚠ Common exam trap

A common mix-up: candidates confuse Project Assurance with Project Support or assume the Project Manager can handle it, but PRINCE2 explicitly separates the assurance role from management to maintain independence and objectivity.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Board members (or their delegates)

Project Assurance is a PRINCE2 responsibility that provides an independent check on the project's progress, compliance, and viability. The Project Board members (or their delegates) are accountable for this function because they represent the business, user, and supplier interests, ensuring objective oversight separate from day-to-day management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Support

    Why it's wrong here

    Project Support provides administrative tasks, not assurance.

  • Project Manager

    Why it's wrong here

    The Project Manager is responsible for management, not independent assurance.

  • Team Managers

    Why it's wrong here

    Team Managers manage delivery, not assurance.

  • Project Board members (or their delegates)

    Why this is correct

    Correct. Assurance is independent and typically delegated by the Board.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. In PRINCE2, who is responsible for project assurance?

easy
  • A.The Project Manager
  • B.The Senior Supplier
  • C.The Project Support
  • D.The Project Board

Why D: Project assurance is the responsibility of the Project Board, which provides independent assurance.

Variation 2. Who is responsible for project assurance in PRINCE2?

easy
  • A.Senior Supplier
  • B.Project Board
  • C.Project Support
  • D.Project Manager

Why B: Project Assurance is the Project Board's responsibility, but it can be delegated to individuals or teams independent of the Project Manager.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.